Project Planning & Scheduling

Program Evaluation and Review Technique ("PERT")

PERT: Planning and Managing Complex Projects

The Program Evaluation and Review Technique (PERT) is a powerful project management tool used to plan, schedule, and monitor complex projects. This technique provides a framework for:

  • Defining project activities: Breaking down a large project into smaller, manageable tasks.
  • Estimating activity durations: Determining the time required to complete each task.
  • Identifying dependencies: Understanding the order in which tasks must be completed.
  • Calculating project completion time: Estimating the overall project duration.
  • Identifying critical path activities: Identifying the sequence of tasks that directly impacts the project completion date.

PERT Network Diagram:

The core of PERT is the network diagram. This visual representation displays project activities as nodes (circles or boxes) and the dependencies between them as arrows. These arrows indicate the order in which activities must be completed.

Key Features of PERT:

  • Precedence Constraints: The arrows in the PERT network diagram show the precedence relationships between activities. This means that an activity cannot start until its predecessor is complete.
  • Activity Durations: Each node in the diagram contains an estimate of the time required to complete the corresponding activity. These durations can be based on historical data, expert opinion, or other relevant information.
  • Critical Path: The longest path through the network diagram is called the critical path. Activities on the critical path must be completed on time for the project to finish as planned. Delays in these activities will directly impact the project completion date.
  • Slack Time: Activities not on the critical path have some "slack" time. This means they can be delayed without affecting the overall project completion time.

Benefits of Using PERT:

  • Improved Project Planning: PERT provides a structured approach to project planning, ensuring that all tasks are considered and their dependencies are understood.
  • Better Time Management: PERT helps identify the critical path and estimate the project completion time, allowing for more accurate time management and resource allocation.
  • Increased Efficiency: PERT's focus on task dependencies and critical path analysis helps to identify potential bottlenecks and improve project efficiency.
  • Improved Communication: The network diagram provides a clear visual representation of the project plan, facilitating communication and understanding among stakeholders.

Limitations of PERT:

  • Data Accuracy: The accuracy of the PERT analysis depends on the reliability of the activity duration estimates. Inaccurate estimates can lead to unrealistic project timelines.
  • Complexity: For large, complex projects, the PERT network diagram can become very intricate, making it challenging to analyze and understand.
  • Static Nature: The PERT network diagram is a static representation of the project plan. It does not account for unforeseen changes or disruptions that may occur during project execution.

Conclusion:

PERT remains a valuable tool for managing complex projects. By using the network diagram to identify dependencies, calculate project completion time, and prioritize critical path activities, project managers can improve planning, scheduling, and overall project success. However, it's important to be aware of the limitations of the technique and adjust the approach as needed to account for the dynamic nature of real-world projects.


Test Your Knowledge

PERT Quiz

Instructions: Choose the best answer for each question.

1. What is the primary purpose of a PERT network diagram?

(a) To visually represent the project budget. (b) To show the sequence of project activities and their dependencies. (c) To track the progress of individual team members. (d) To identify the project stakeholders.

Answer

(b) To show the sequence of project activities and their dependencies.

2. What are the arrows in a PERT network diagram called?

(a) Nodes (b) Activities (c) Dependencies (d) Precedence constraints

Answer

(d) Precedence constraints

3. Which of the following is NOT a benefit of using PERT?

(a) Improved project planning (b) Better time management (c) Increased efficiency (d) Guaranteed project success

Answer

(d) Guaranteed project success

4. What is the critical path in a PERT network diagram?

(a) The shortest path through the network (b) The path with the most activities (c) The path that takes the longest time to complete (d) The path with the highest risk

Answer

(c) The path that takes the longest time to complete

5. Which of the following is a limitation of PERT?

(a) It can only be used for small projects. (b) It does not account for changes in project scope. (c) It requires a lot of data that may not be readily available. (d) It is too complex for most project managers to understand.

Answer

(c) It requires a lot of data that may not be readily available.

PERT Exercise

Scenario: You are the project manager for a new software development project. The project has the following activities:

  • A: Requirements gathering (5 days)
  • B: Design (3 days)
  • C: Coding (10 days)
  • D: Testing (4 days)
  • E: Deployment (2 days)

Dependencies:

  • B depends on A
  • C depends on B
  • D depends on C
  • E depends on D

Task:

  1. Create a PERT network diagram for this project.
  2. Identify the critical path.
  3. Calculate the project completion time.

Exercice Correction

1. PERT Network Diagram:

A (5) --> B (3) --> C (10) --> D (4) --> E (2)

2. Critical Path: A - B - C - D - E

3. Project Completion Time: 5 + 3 + 10 + 4 + 2 = 24 days


Books

  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner - This comprehensive textbook covers a wide range of project management techniques, including PERT.
  • Project Management: The Managerial Process by Meredith and Mantel - This book offers a detailed explanation of PERT and its application in project planning and scheduling.
  • Project Management for Dummies by Kathy Schwalbe - This guide provides a beginner-friendly introduction to PERT and other project management tools.

Articles

  • "PERT: A Method for Estimating Project Time" by D. G. Malcolm, J. H. Roseboom, C. E. Clark, and W. Fazar (Operations Research, 1959) - This original paper introduces the concept of PERT.
  • "A Practical Guide to Using PERT for Project Planning" by Project Management Institute - This article provides a step-by-step guide to implementing PERT in real-world projects.
  • "PERT and CPM: A Comparison of Two Project Management Techniques" by Project Management Tools - This article compares PERT with another popular technique, Critical Path Method (CPM).

Online Resources


Search Tips

  • "PERT project management": This basic search term will provide a range of relevant articles, tutorials, and resources.
  • "PERT vs CPM": This search will help you understand the differences and similarities between PERT and CPM.
  • "PERT software": This search will lead you to software tools that can assist you in creating and managing PERT diagrams.

Techniques

Similar Terms
Drilling & Well Completion
Legal & Compliance
Quality Assurance & Quality Control (QA/QC)
Procurement & Supply Chain Management
Geology & Exploration
Project Planning & Scheduling
Oil & Gas Processing
Asset Integrity Management
Pipeline Construction
General Technical Terms
Reservoir Engineering
Most Viewed

Comments

No Comments
POST COMMENT
captcha
Back