Project Planning & Scheduling

Percent Complete

The Power of Percent Complete: Navigating the Hold State

In project management, the "hold" state often signifies a temporary pause in an activity, awaiting a specific condition or decision before resuming. Determining the remaining duration of a held activity can be challenging, but one essential tool emerges: Percent Complete.

Percent Complete: A Key Metric for Progress Tracking

Percent complete acts as a powerful indicator of an activity's progress, even when it's in a hold state. It quantifies the work already completed, providing valuable insights into:

  • Remaining Work: By subtracting the percent complete from 100%, we can determine the remaining effort needed to finish the activity. This helps us estimate the time required for completion once the hold is lifted.
  • Realistic Timelines: Understanding the percent complete allows for more accurate forecasts and timelines. It prevents overly optimistic estimations and helps manage stakeholder expectations effectively.
  • Resource Allocation: Knowing the completion status of held activities informs resource allocation decisions. We can prioritize resources for activities nearing completion, ensuring efficient utilization.

Defining Percent Complete in Hold State

However, defining percent complete for a held activity requires a nuanced approach. Simple percentage calculations based on initial estimates may not be accurate. Instead, consider these approaches:

  • Milestone-Based: If the activity has well-defined milestones, assign a percentage value to each milestone. The sum of the completed milestones reflects the percent complete.
  • Work Package Completion: If the activity is broken down into smaller work packages, assess the completion status of each package. The combined percentage represents the overall progress.
  • Expert Judgment: In cases where concrete metrics are unavailable, rely on expert judgment from the team responsible for the activity. This ensures a realistic and informed estimate.

Challenges and Best Practices

Using percent complete effectively during a hold state can present challenges:

  • Subjectivity: Determining the percentage can be subjective, especially if the activity is complex or lacks clear milestones.
  • Changing Scope: If the scope of the held activity changes during the hold period, the percent complete needs to be recalculated.
  • Unforeseen Delays: External factors might cause delays upon resuming the activity, affecting the estimated completion time.

To mitigate these challenges, adopt these best practices:

  • Clear Communication: Ensure open communication between stakeholders about the rationale for the hold, the expected duration, and the impact on the overall project.
  • Regular Updates: Monitor the percent complete regularly and communicate changes to stakeholders to maintain transparency.
  • Contingency Planning: Prepare for potential delays and adjust the project plan accordingly to minimize impact.

Conclusion:

Percent complete is a powerful tool for navigating the hold state in project management. By understanding its application and addressing potential challenges, we can ensure accurate progress tracking, realistic timelines, and informed resource allocation, ultimately contributing to successful project delivery.


Test Your Knowledge

Quiz: The Power of Percent Complete in Hold State

Instructions: Choose the best answer for each question.

1. What does the "hold" state in project management typically indicate? a) A permanent suspension of an activity. b) A temporary pause in an activity awaiting specific conditions or decisions. c) The completion of an activity. d) A critical milestone in the project.

Answer

b) A temporary pause in an activity awaiting specific conditions or decisions.

2. How can percent complete be used to track progress during a hold state? a) It indicates the amount of time that has passed since the activity was put on hold. b) It quantifies the work already completed, providing insights into remaining work and realistic timelines. c) It helps determine the cost of the hold state. d) It ensures the activity will be completed on time.

Answer

b) It quantifies the work already completed, providing insights into remaining work and realistic timelines.

3. Which of the following is NOT a recommended approach for defining percent complete in a hold state? a) Milestone-based approach. b) Work package completion approach. c) Simple percentage calculation based on initial estimates. d) Expert judgment approach.

Answer

c) Simple percentage calculation based on initial estimates.

4. What is a significant challenge associated with using percent complete during a hold state? a) The absence of stakeholders' involvement. b) The difficulty in accessing historical project data. c) The potential for subjectivity in determining the percentage. d) The lack of available project management tools.

Answer

c) The potential for subjectivity in determining the percentage.

5. What is a best practice for mitigating challenges associated with using percent complete in a hold state? a) Avoiding communication with stakeholders to avoid confusion. b) Focusing on completing other activities while the held activity is paused. c) Regularly monitoring and communicating the percent complete to stakeholders. d) Ignoring potential delays and assuming the activity will resume as planned.

Answer

c) Regularly monitoring and communicating the percent complete to stakeholders.

Exercise: Project Planning with a Hold State

Scenario: You are managing a project to develop a new software application. One activity, "User Interface Design", is currently on hold pending approval from the client for the design concept. This activity was initially estimated to take 10 days.

Task:

  1. Assume that 3 days of work were completed on "User Interface Design" before it was put on hold. Calculate the percent complete for this activity.
  2. Develop a strategy for tracking the percent complete for this activity while it's in the hold state. Consider using milestones or work packages.
  3. Explain how this information can help you estimate the remaining time needed to complete "User Interface Design" once the hold is lifted.

Exercice Correction

**1. Percent Complete Calculation:**

Percent Complete = (Work Completed / Total Estimated Work) * 100%

Percent Complete = (3 days / 10 days) * 100% = 30%

Therefore, the "User Interface Design" activity is 30% complete.

2. Tracking Percent Complete During Hold State:

  • Milestone-Based Approach: Divide the "User Interface Design" activity into specific milestones:

    • Milestone 1: Initial Design Concept (Completed - 30%)
    • Milestone 2: Client Approval (Pending)
    • Milestone 3: Detailed UI Design (Not yet started)
    • Milestone 4: UI Testing (Not yet started)
  • Work Package Completion Approach: Break down the "User Interface Design" activity into work packages:

    • Work Package 1: Wireframing (Completed - 100%)
    • Work Package 2: Visual Design (Completed - 50%) - Assuming half the visual design work is completed
    • Work Package 3: Prototyping (Not yet started)
    • Work Package 4: User Testing (Not yet started)

3. Estimating Remaining Time:

  • Once the client approves the design concept (Milestone 2), you can assess the remaining work based on the chosen approach:

    • Milestone-Based: Milestone 3 and 4 would need to be completed.
    • Work Package Completion: Work Packages 3 and 4 would need to be completed.
  • By tracking the percent complete and using the defined milestones or work packages, you can accurately estimate the remaining time needed for "User Interface Design" after the hold is lifted. This will help in managing expectations and adjusting the project timeline accordingly.


Books

  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide) by Project Management Institute (PMI): Chapter 10, "Project Communications Management," provides a comprehensive overview of communication in project management, including the importance of accurate progress reporting.
  • The Project Management Institute (PMI) Agile Practice Guide: This guide discusses Agile methodologies, which emphasize frequent updates and transparency. This aligns with using percent complete to track progress even in a hold state.
  • Effective Project Management by Kerzner: This classic book explores various aspects of project management, including progress reporting and tracking.
  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner: Covers in-depth strategies for effective project management, including the use of percent complete.

Articles

  • How to Accurately Measure Project Completion: A Guide to Percent Complete by The Project Management Institute (PMI): This article explains the importance of defining and tracking percent complete accurately, especially for complex projects.
  • The Importance of Percent Complete in Project Management by ProjectManager.com: This article highlights the benefits of using percent complete as a crucial metric for effective project management.
  • How to Track Progress in the Hold State by ProjectManagement.com: Discusses strategies for tracking progress for activities in a hold state, including the use of percent complete.

Online Resources

  • ProjectManagement.com: Offers various articles, tutorials, and tools related to project management, including resources on percent complete and project progress tracking.
  • The Project Management Institute (PMI): The official website of PMI provides resources, certifications, and training related to project management, including information on best practices for project communication and progress reporting.
  • Project Management Institute (PMI) Academy: Online training courses and certification programs offered by PMI, which delve into the nuances of project management, including accurate progress reporting and using percent complete.

Search Tips

  • "Percent complete" "project management" "hold state": This search phrase will yield relevant articles and resources on the specific topic of tracking percent complete during a project hold.
  • "Project progress tracking" "methods" "best practices": This broad search will provide you with a range of information on different project progress tracking methods, including using percent complete.
  • "Project Management Body of Knowledge (PMBOK® Guide)" "percent complete": This search will help you find information within the PMBOK® Guide on how to effectively use percent complete in project management.

Techniques

Similar Terms
General Technical Terms
  • Complete Complete: A Crucial Term in O…
Drilling & Well CompletionProject Planning & SchedulingCost Estimation & ControlQuality Control & Inspection
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back