Cost Estimation & Control

Estimated Actual at Completion ("EAC")

Understanding Estimated Actual at Completion (EAC): A Key Metric for Cost Control

In the realm of project management, accurately predicting the final cost of a project is crucial for effective budgeting and decision-making. One of the most important metrics used to estimate this final cost is the Estimated Actual at Completion (EAC). This article will delve into the concept of EAC, its significance, and how it can be calculated.

What is EAC?

The EAC is an estimate of the total cost required to complete a project, considering both the cost already incurred and the estimated cost of the remaining work. It is a dynamic metric that adjusts as the project progresses and new information becomes available.

Why is EAC important?

EAC plays a pivotal role in cost control by:

  • Providing a realistic forecast: It allows project managers to assess the current cost situation and predict the final cost, enabling informed decision-making.
  • Facilitating resource allocation: Based on the EAC, project managers can adjust resource allocation and prioritize tasks effectively.
  • Identifying potential cost overruns: Early detection of cost overruns through EAC monitoring allows for corrective action and risk mitigation.
  • Measuring project performance: By comparing the EAC to the original budget, project managers can assess the project's financial health and identify areas for improvement.

Calculating EAC:

The EAC can be calculated in several ways, depending on the project's current status and the available data. One common approach is:

EAC = ACWP + (BAC - EV)

Where:

  • ACWP (Actual Cost of Work Performed): The actual cost incurred for the work completed so far.
  • BAC (Budget at Completion): The original planned budget for the entire project.
  • EV (Earned Value): The value of the work completed so far, based on the planned schedule and budget.

Different EAC calculation methods:

Depending on the specific project scenario and available data, other methods for calculating EAC may be more appropriate, including:

  • EAC based on the current performance: This method uses the current cost performance index (CPI) to adjust the remaining budget.
  • EAC based on specific factors: This method considers specific factors like changes in scope, schedule, or resource availability to refine the cost estimate.

EAC in Practice:

In practice, EAC is a valuable tool for project managers across various industries. From construction projects to software development, monitoring and adjusting the EAC helps ensure projects stay within budget and deliver on their objectives.

Conclusion:

Estimated Actual at Completion (EAC) is a crucial metric for effective cost estimation and control in project management. By providing a realistic forecast of the total project cost, it enables informed decision-making, facilitates resource allocation, and facilitates early identification of potential cost overruns. By adopting a proactive approach to EAC monitoring, project managers can enhance project success and ensure projects are delivered on time and within budget.


Test Your Knowledge

EAC Quiz:

Instructions: Choose the best answer for each question.

1. What does EAC stand for? a) Estimated Actual Cost b) Estimated Actual Completion c) Estimated at Completion d) Expected Actual Cost

Answer

b) Estimated Actual Completion

2. Which of the following is NOT a benefit of using EAC in project management? a) Provides a realistic forecast of project cost. b) Helps identify potential cost overruns. c) Determines the final project schedule. d) Measures project performance against the original budget.

Answer

c) Determines the final project schedule.

3. What is the formula for calculating EAC using ACWP, BAC, and EV? a) EAC = ACWP + (BAC - EV) b) EAC = BAC - ACWP c) EAC = BAC / EV d) EAC = EV / ACWP

Answer

a) EAC = ACWP + (BAC - EV)

4. Which EAC calculation method adjusts the remaining budget based on the current cost performance index (CPI)? a) EAC based on specific factors b) EAC based on the current performance c) EAC based on historical data d) EAC based on the original budget

Answer

b) EAC based on the current performance

5. Why is EAC considered a dynamic metric? a) Because it is calculated based on the original budget. b) Because it changes as the project progresses and new information becomes available. c) Because it is calculated at the end of the project. d) Because it is always based on historical data.

Answer

b) Because it changes as the project progresses and new information becomes available.

EAC Exercise:

Scenario:

You are managing a software development project with a budget of $500,000 (BAC). The project is currently 40% complete. The actual cost incurred so far (ACWP) is $220,000. The earned value (EV) is $200,000.

Task:

Calculate the EAC for the project using the formula provided in the article. Based on your calculation, is the project on track to meet the budget? If not, what actions should be taken?

Exercise Correction

**Calculation:** EAC = ACWP + (BAC - EV) EAC = $220,000 + ($500,000 - $200,000) **EAC = $520,000** **Analysis:** The EAC of $520,000 is higher than the original budget of $500,000. This indicates that the project is currently over budget. **Actions:** * **Investigate the reasons for the cost overrun:** Analyze the project's performance, identify areas of inefficiency, and determine if any scope changes or unforeseen circumstances have impacted costs. * **Develop a corrective action plan:** Implement cost-saving measures, negotiate with vendors, adjust the project scope, or explore alternative solutions to bring the project back on track. * **Communicate the situation:** Inform stakeholders about the cost overrun and the corrective actions being taken. Be transparent about the potential impact on the project timeline and budget. * **Monitor the EAC closely:** Continuously track the EAC and adjust it as needed to ensure accurate cost forecasting and effective cost control.


Books

  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - This comprehensive guide from the Project Management Institute (PMI) provides a detailed explanation of EAC and its role in cost management.
  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner - This classic textbook covers a wide range of project management concepts, including EAC and other cost estimation techniques.
  • Project Management: The Managerial Process by Joseph Phillips - This textbook offers a practical approach to project management, with specific chapters dedicated to cost management and EAC calculations.

Articles

  • "Estimated At Completion (EAC): A Guide to Cost Control" by PM Solutions - This article provides a detailed explanation of EAC, its importance, and different methods for calculating it.
  • "Earned Value Management: A Guide to Project Cost and Schedule Control" by The Project Management Institute - This article covers the fundamental concepts of earned value management, including EAC and its role in project performance measurement.
  • "How to Calculate Estimated Actual at Completion (EAC)" by ProjectManager.com - This article provides a practical guide to calculating EAC, with step-by-step instructions and examples.

Online Resources

  • Project Management Institute (PMI) - The PMI website provides valuable resources for project management professionals, including articles, research reports, and webinars on EAC and other cost management topics.
  • ProjectManager.com - This website offers a wealth of information on project management, including articles, guides, and software tools that can help you calculate and track EAC.
  • Earned Value Management (EVM) Primer by The Project Management Institute - This primer provides a comprehensive overview of EVM, including the calculation and interpretation of EAC.

Search Tips

  • Use specific keywords: When searching for information on EAC, use specific keywords such as "Estimated Actual at Completion," "EAC calculation," "EAC methods," "EAC in project management."
  • Combine keywords: Use multiple keywords to narrow down your search results. For example, "EAC project management," "EAC formula," or "EAC examples."
  • Use quotation marks: Enclose specific phrases in quotation marks to find exact matches. For instance, "Estimated Actual at Completion (EAC)."
  • Use advanced search operators: Explore advanced operators like "site:" to restrict your search to specific websites, or "filetype:" to find specific file formats (e.g., PDF, DOC).

Techniques

Similar Terms
Commissioning ProceduresGeneral Technical TermsProject Planning & SchedulingCommunication & ReportingDrilling & Well CompletionAsset Integrity ManagementReservoir EngineeringProcurement & Supply Chain ManagementCost Estimation & Control
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back