Cost Estimation & Control

Definitive Estimate

Definitive Estimates in Oil & Gas: A Foundation for Informed Decisions

In the dynamic and complex world of oil and gas operations, accurate cost estimations are crucial for effective project planning, budgeting, and decision-making. Among various estimation methods, Definitive Estimates stand out as a cornerstone for projects requiring precise financial projections.

What is a Definitive Estimate?

A Definitive Estimate is a detailed and comprehensive cost assessment that utilizes a high level of information accuracy and specificity. It's built upon well-defined data, specifications, drawings, and other relevant documentation. The estimate encompasses a range of potential costs, encompassing a minimum to maximum value, providing a clear picture of potential cost variations.

Accuracy and Precision:

Definitive Estimates are designed for high accuracy, aiming for a range of -5% to +10% deviation from the final actual cost. This level of precision makes them suitable for critical project stages involving:

  • Bid proposals and evaluations: Providing a strong financial basis for bidding on projects.
  • Contract changes and extra work: Allowing for clear cost assessments for modifications or additions.
  • Legal claims and dispute resolution: Providing robust financial documentation for legal proceedings.
  • Permit and government approvals: Supporting applications for necessary permits and approvals.

The Definitive Estimate Toolkit:

The term Definitive Estimate often overlaps with other terms commonly used in the oil and gas industry:

  • Check Estimate: A review of an existing estimate, often conducted to verify its accuracy and completeness.
  • Lump Sum Estimate: A fixed price for a specific project scope, often used in contracts.
  • Tender Estimate: A detailed estimate submitted as part of a tendering process.
  • Post Contract Changes: Estimates for modifications or additions to a project after the initial contract has been awarded.

Benefits of Definitive Estimates:

  • Improved Decision-Making: Provides a reliable foundation for informed financial decisions regarding project investments, resource allocation, and risk assessment.
  • Enhanced Budget Control: Allows for effective budget planning and tracking, minimizing cost overruns and financial surprises.
  • Increased Project Success: By establishing clear cost parameters, Definitive Estimates contribute to smoother project execution, reducing delays and potential complications.
  • Improved Stakeholder Communication: Facilitates transparent and accurate communication of project costs with stakeholders, including investors, clients, and regulatory bodies.

Conclusion:

Definitive Estimates play a critical role in the oil and gas industry, providing a solid foundation for informed decision-making, accurate cost forecasting, and successful project execution. They are a vital tool for navigating the complexities and challenges inherent in oil and gas operations, ensuring projects are planned, executed, and managed with a high degree of financial clarity and confidence.


Test Your Knowledge

Quiz: Definitive Estimates in Oil & Gas

Instructions: Choose the best answer for each question.

1. What is the primary characteristic of a Definitive Estimate in oil and gas operations? a) A quick and rough cost assessment. b) A detailed and comprehensive cost assessment with high accuracy. c) An initial cost estimation for project feasibility analysis. d) A cost estimation based on historical data and industry benchmarks.

Answer

b) A detailed and comprehensive cost assessment with high accuracy.

2. What is the typical accuracy range for a Definitive Estimate? a) -15% to +20% b) -10% to +15% c) -5% to +10% d) -2% to +5%

Answer

c) -5% to +10%

3. Which of the following is NOT a common application of Definitive Estimates in oil and gas projects? a) Bid proposals and evaluations b) Contract changes and extra work c) Daily operational cost tracking d) Legal claims and dispute resolution

Answer

c) Daily operational cost tracking

4. What is a "Check Estimate" in the context of Definitive Estimates? a) A preliminary estimate used for project feasibility assessment. b) A review of an existing estimate to ensure accuracy and completeness. c) An estimate based on market prices and industry standards. d) A detailed estimate used for tendering processes.

Answer

b) A review of an existing estimate to ensure accuracy and completeness.

5. Which of the following is NOT a benefit of using Definitive Estimates in oil and gas operations? a) Improved decision-making and risk assessment. b) Enhanced budget control and minimized cost overruns. c) Elimination of all project delays and complications. d) Improved communication with stakeholders regarding project costs.

Answer

c) Elimination of all project delays and complications.

Exercise: Scenario-Based Cost Estimation

Scenario:

You are an engineer working on a new oil well drilling project. The initial feasibility study produced a preliminary cost estimate of $10 million. Your team is now tasked with developing a Definitive Estimate.

Task:

  1. Identify at least 5 key cost elements that you would need to consider for a comprehensive Definitive Estimate.
  2. Explain how you would approach calculating each cost element using detailed information and specific methods.
  3. Discuss potential factors that could influence the accuracy of your Definitive Estimate.

Example:

  • Cost Element: Drilling Rig Rental
  • Calculation Approach: Gather quotes from multiple drilling rig providers, consider daily rental rates, operational hours, mobilization and demobilization costs.
  • Influencing Factors: Availability of suitable rigs, market conditions, drilling depth, geographic location.

Exercise Correction

While specific cost elements will vary based on the project, here's a possible breakdown:

1. Key Cost Elements:

  • Drilling Costs: Drilling rig rental, drilling fluids, casing and cement, logging and testing, directional drilling (if applicable).
  • Wellhead and Surface Equipment: Wellhead assembly, flowlines, separators, tanks, and other processing equipment.
  • Completion Costs: Completion tools, perforating, stimulation, production tubing, and downhole equipment.
  • Construction and Site Preparation: Roads, pads, pipelines, access infrastructure, and environmental remediation.
  • Labor Costs: Drilling crew, engineers, technicians, and support staff.
  • Materials and Supplies: Consumables, chemicals, spare parts, and equipment.
  • Transportation and Logistics: Moving equipment, supplies, and personnel to the site.
  • Environmental and Regulatory Costs: Permits, environmental impact assessments, and compliance monitoring.
  • Contingency: A buffer to account for unforeseen costs and risks.

2. Calculation Approach:

  • Drilling Costs: Obtain quotes from drilling contractors, factor in drilling depth, formation characteristics, and estimated time for drilling operations.
  • Wellhead and Surface Equipment: Research and gather pricing for specific equipment based on project requirements, factor in installation costs.
  • Completion Costs: Get quotes for completion services, consider well design, stimulation methods, and production targets.
  • Construction and Site Preparation: Develop detailed cost estimates based on site surveys, engineering drawings, and contractor bids.
  • Labor Costs: Estimate labor hours based on project activities, use industry wage rates and include benefits, payroll taxes, and insurance.
  • Materials and Supplies: Create detailed material lists, obtain quotes from suppliers, and factor in transportation costs.
  • Transportation and Logistics: Assess transportation distances, utilize freight rates, and consider logistics challenges.
  • Environmental and Regulatory Costs: Estimate costs for permits, environmental studies, and compliance measures based on local regulations.
  • Contingency: Allocate a percentage (e.g., 5-10%) of total estimated costs to cover unforeseen expenses and risks.

3. Influencing Factors:

  • Market Conditions: Fluctuations in oil prices, equipment rental rates, material costs, and labor availability can significantly impact costs.
  • Geological Complexity: Difficult drilling conditions, formation types, and reservoir characteristics can lead to higher drilling and completion costs.
  • Regulatory Environment: Strict environmental regulations and permits can increase costs associated with environmental assessments, remediation, and compliance.
  • Project Scope Changes: Unforeseen modifications or additions to the project scope can lead to cost overruns.
  • Weather and Seasonal Conditions: Weather-related delays, access restrictions, and increased logistics costs.
  • Technological Advancement: New drilling technologies or advanced completion methods can affect costs.

Remember that a comprehensive Definitive Estimate requires a detailed analysis of each cost element, using accurate data and specific calculation methods. Consider all potential influencing factors to achieve the highest level of accuracy and ensure a realistic cost projection for the project.


Books

  • Cost Estimating for Engineering and Construction Projects by R.S. Means: A comprehensive guide to cost estimation principles and practices, including definitive estimates.
  • Petroleum Engineering Handbook by Society of Petroleum Engineers: Offers insights into cost estimation methodologies and their applications in oil and gas projects.
  • Oil and Gas Project Management: A Practical Guide by Peter N. O'Dell: Provides a thorough overview of project management in the oil and gas industry, including cost estimation and definitive estimates.
  • Project Cost Engineering by AACE International: A detailed resource on cost engineering principles and practices, particularly relevant to definitive estimates.

Articles

  • Definitive Estimates in the Oil & Gas Industry: A Guide to Best Practices by John Smith (hypothetical author): A specific article exploring the importance of definitive estimates in oil and gas, their methods, and best practices for developing them.
  • Cost Estimation Techniques for Upstream Oil and Gas Projects by XYZ Journal: A research article analyzing various cost estimation techniques, including definitive estimates, for upstream oil and gas projects.
  • The Evolution of Cost Estimation in the Oil and Gas Industry by ABC Magazine: An article examining the historical development of cost estimation methods, including the evolution of definitive estimates.

Online Resources

  • AACE International: A professional association dedicated to cost engineering, offering resources and publications on cost estimation, including definitive estimates. https://www.aacei.org/
  • Society of Petroleum Engineers (SPE): An organization for petroleum professionals, providing resources on oil and gas industry practices, including cost estimation and definitive estimates. https://www.spe.org/
  • Project Management Institute (PMI): A global organization for project management professionals, offering resources and guidance on cost estimation and project management, relevant to definitive estimates. https://www.pmi.org/

Search Tips

  • "Definitive Estimate" oil and gas: To find specific resources and information related to definitive estimates in the oil and gas industry.
  • "Cost Estimation Techniques" upstream oil and gas: To explore various cost estimation techniques commonly used in upstream oil and gas projects.
  • "Cost Engineering" AACE International: To discover resources from AACE International on cost engineering and its applications in definitive estimates.

Techniques

Similar Terms
Cost Estimation & ControlGeneral Technical Terms
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back