Glossary of Technical Terms Used in Project Planning & Scheduling: Cost Types

Cost Types

Understanding Cost Types in Estimation & Control: A Guide for Project Management

Effective cost estimation and control are crucial for successful project delivery. This process requires a comprehensive understanding of different cost types, as they help determine the financial health of a project at any given point. This article delves into the four primary cost types commonly used in project management and explores their significance within the overall cost estimation and control framework.

The Four Key Cost Types:

  1. Authorized Appropriation: This represents the maximum amount of funds approved for a specific cost class within the project budget. It often includes contingencies to account for unforeseen circumstances or potential cost overruns.
  2. Committed Cost Expenditure (or Actual): This captures the actual cost incurred for the project up to a certain point in time. It includes all contractually committed expenses, including payments made and invoices received.
  3. Estimate to Complete (ETC) or Forecast to Complete (FTC): This estimates the remaining cost required to complete the project based on the current progress and anticipated future expenditures. It can vary depending on the level of detail and accuracy desired.
  4. Uncommitted: This represents the potential costs yet to be committed. It includes the anticipated award cost (the estimated cost of future contracts), which may incorporate an allowance for inflation or escalation. This type also contains contingencies for unforeseen events.

Interrelationships and Significance:

  • The sum of Committed Cost Expenditure (Type 2) and Uncommitted (Type 4) represents the Estimated Cost at Completion (EAC), which provides a projection of the total project cost.
  • Type 1 (Authorized Appropriation) and Type 4 (Uncommitted) incorporate contingencies, offering a safety net for potential cost overruns.
  • Type 3 (ETC/FTC) is further subdivided into payments (actual money disbursed) and retentions (holdbacks), which are typically a percentage of the payment withheld until project completion.

Practical Applications:

  • Budget Tracking and Monitoring: By tracking these cost types, project managers can closely monitor budget utilization, identify potential overruns, and take corrective actions to stay within the approved budget.
  • Risk Assessment and Management: Contingencies within Type 1 and Type 4 serve as buffers for unforeseen risks. Analyzing these contingencies helps in identifying potential risk areas and formulating mitigation strategies.
  • Decision Making and Forecasting: The different cost types provide valuable insights for making informed decisions regarding project scope, schedule, and resource allocation. By projecting the ETC/FTC (Type 3), managers can forecast future expenses and adjust plans accordingly.

Conclusion:

Understanding the different cost types in cost estimation and control is crucial for effective project management. By meticulously tracking and analyzing these costs, project managers gain valuable insights into the project's financial health, enabling them to make informed decisions, manage risks, and ultimately ensure successful project delivery within budget and timeline constraints.


Test Your Knowledge

Quiz: Understanding Cost Types in Estimation & Control

Instructions: Choose the best answer for each question.

1. Which cost type represents the maximum amount of funds approved for a project?

a) Committed Cost Expenditure b) Authorized Appropriation c) Estimate to Complete d) Uncommitted

Answer

b) Authorized Appropriation

2. What does the "Estimate to Complete" (ETC) reflect?

a) The total project cost. b) The cost incurred so far. c) The estimated remaining cost to complete the project. d) The potential costs yet to be committed.

Answer

c) The estimated remaining cost to complete the project.

3. Which two cost types, when added together, provide the Estimated Cost at Completion (EAC)?

a) Committed Cost Expenditure and Authorized Appropriation b) Estimate to Complete and Uncommitted c) Committed Cost Expenditure and Uncommitted d) Authorized Appropriation and Uncommitted

Answer

c) Committed Cost Expenditure and Uncommitted

4. What is the primary purpose of contingencies included in "Authorized Appropriation" and "Uncommitted"?

a) To cover unexpected cost overruns. b) To track actual expenses. c) To calculate the Estimated Cost at Completion. d) To forecast future payments.

Answer

a) To cover unexpected cost overruns.

5. How can tracking cost types benefit project managers?

a) By identifying potential risks and formulating mitigation strategies. b) By providing insights for making informed decisions about project scope, schedule, and resource allocation. c) By monitoring budget utilization and identifying potential overruns. d) All of the above.

Answer

d) All of the above.

Exercise: Cost Tracking Scenario

Scenario: You are managing a software development project with an authorized appropriation of $500,000. So far, you have incurred $250,000 in committed cost expenditure. You estimate that $100,000 is needed to complete the remaining development tasks. There are also anticipated award costs of $50,000 for future contracts, and a contingency of $20,000 for potential risks.

Task: Calculate the following:

  1. Estimate to Complete (ETC)
  2. Uncommitted
  3. Estimated Cost at Completion (EAC)
  4. Contingency Percentage (calculated as a percentage of the EAC)

Exercise Correction

1. **Estimate to Complete (ETC):** $100,000 2. **Uncommitted:** $50,000 (anticipated award cost) + $20,000 (contingency) = $70,000 3. **Estimated Cost at Completion (EAC):** $250,000 (committed cost) + $70,000 (uncommitted) = $320,000 4. **Contingency Percentage:** ($20,000 / $320,000) x 100% = 6.25%


Books

  • Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Seventh Edition. Project Management Institute. This comprehensive guide provides a detailed overview of cost management, including cost types, estimation techniques, and control measures.

Articles

  • "Cost Types in Project Management" by [Your Name] (This article). This resource provides a concise and focused explanation of the four key cost types and their significance in project management.

Online Resources

  • Project Management Institute (PMI) website: The PMI website offers a wealth of resources on project management, including articles, webinars, and online courses on cost management, including explanations of various cost types.

Search Tips

  • Use specific keywords: Include terms like "cost types," "project management," "cost estimation," "cost control," and specific cost type names like "Authorized Appropriation" or "Estimate to Complete."
Similar Terms
Oil & Gas Processing
Cost Estimation & Control
Project Planning & Scheduling
Budgeting & Financial Control
Oil & Gas Specific Terms
General Technical Terms
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back