In the fast-paced and dynamic world of oil and gas, unforeseen circumstances are inevitable. Sometimes, modifications or adjustments to a project are necessary, leading to work that was not initially planned for and therefore not included in the original price. This is where the term Authorized Unpriced Work (AUW) comes into play.
What is Authorized Unpriced Work (AUW)?
AUW refers to work that is approved by the project owner or operator, but was not included in the original contract scope and price. This type of work often arises due to:
How AUW Impacts Oil & Gas Projects:
While necessary, AUW can significantly impact project timelines and budgets. Here's how:
Managing AUW for Project Success:
To mitigate the risks associated with AUW, it is crucial to:
Conclusion:
Authorized Unpriced Work is an inherent aspect of oil and gas projects. Understanding its implications and implementing effective management strategies are key to ensuring project success. By embracing clear communication, robust change management practices, and a proactive approach to unforeseen circumstances, stakeholders can mitigate the risks and optimize the outcomes of their ventures.
Instructions: Choose the best answer for each question.
1. What does AUW stand for?
(a) Approved Unpriced Work (b) Authorized Unpriced Work (c) Additional Unplanned Work (d) Authorized Underpriced Work
(b) Authorized Unpriced Work
2. Which of the following is NOT a common reason for AUW?
(a) Unexpected site conditions (b) Design changes (c) Equipment failures (d) Project budget overruns
(d) Project budget overruns
3. How can AUW impact a project's timeline?
(a) It can speed up the project. (b) It can delay the project. (c) It has no impact on the timeline. (d) It depends on the size of the AUW.
(b) It can delay the project.
4. Which of the following is NOT a strategy for managing AUW effectively?
(a) Clearly defining the project scope (b) Establishing change management processes (c) Avoiding any changes to the original plan (d) Utilizing project management tools
(c) Avoiding any changes to the original plan
5. Why is negotiating clear pricing for AUW essential?
(a) To prevent disputes between contractors and owners. (b) To ensure the contractor makes a profit. (c) To ensure the project stays within budget. (d) All of the above
(d) All of the above
Scenario: An oil and gas company is constructing a new pipeline. During the excavation process, they discover a large, unexpected rock formation that wasn't shown on the geological survey. This necessitates a change in the pipeline route, requiring additional labor and materials for rerouting.
Task:
**Explanation:** This scenario is an example of AUW because the unexpected rock formation was not included in the original project scope and price. The company needs to perform additional work (rerouting the pipeline) that was not originally planned for.
**Potential Impacts:**
**Actions to Manage AUW:**