In the dynamic world of oil and gas projects, unexpected situations arise frequently. Sometimes, work beyond the initial scope needs to be performed, creating a grey area in contract terms. This is where the term Authorized Unpriced Work (AUW) comes into play. It describes efforts that have been approved to proceed, but for which a specific cost has not been formally agreed upon.
Understanding the Concept:
Imagine a construction project where unforeseen geological conditions require additional drilling to ensure stability. The contractor may request permission to proceed with the extra work, but the exact cost associated with it is yet to be determined. This situation exemplifies Authorized Unpriced Work.
Key Features of AUW:
Benefits of AUW:
Potential Drawbacks of AUW:
Best Practices for Managing AUW:
Conclusion:
Authorized Unpriced Work is a necessary tool in managing the complex and unpredictable nature of oil and gas projects. By understanding the concept, its benefits, and potential drawbacks, stakeholders can mitigate risks and ensure smooth project execution while maintaining fair and transparent relationships.
Instructions: Choose the best answer for each question.
1. Which of the following BEST describes Authorized Unpriced Work (AUW)?
a) Work that is not part of the original contract but is approved by the owner. b) Work that is done without authorization and needs to be priced afterward. c) Work that is included in the original contract but has a price that needs to be adjusted. d) Work that is done by a third party without the knowledge of the owner.
The answer is **a) Work that is not part of the original contract but is approved by the owner.**
2. Which of the following is a KEY FEATURE of AUW?
a) The cost is predetermined before the work begins. b) The work is always approved through formal bidding processes. c) The work is usually done without any specific documentation. d) The work is authorized by the project owner or their representative.
The answer is **d) The work is authorized by the project owner or their representative.**
3. What is a potential DRAWBACK of AUW?
a) It allows for greater flexibility in project execution. b) It can prevent delays in critical work. c) It can create unpredictable costs and potential disputes. d) It facilitates immediate action in emergencies.
The answer is **c) It can create unpredictable costs and potential disputes.**
4. Which of the following is a BEST PRACTICE for managing AUW?
a) Avoid documenting the work performed. b) Negotiate the price of the work after it is completed. c) Obtain specific written authorization for the work. d) Keep the owner uninformed of the work progress.
The answer is **c) Obtain specific written authorization for the work.**
5. Which of the following statements is TRUE about AUW?
a) AUW is always a negative aspect of oil and gas projects. b) AUW should never be used in oil and gas projects. c) AUW is a valuable tool for managing unforeseen situations. d) AUW eliminates all risk and uncertainty in oil and gas projects.
The answer is **c) AUW is a valuable tool for managing unforeseen situations.**
Scenario:
You are a project manager on a large oil and gas drilling project. During the drilling process, unforeseen geological conditions are encountered, requiring additional cementing operations to ensure well stability. The contractor requests permission to proceed with the extra work, but the exact cost is yet to be determined.
Task:
**1. Key Features of AUW in this Scenario:** * **Authorization:** The contractor needs specific authorization from the project owner to proceed with the additional cementing work. * **Unpriced:** The exact cost of the extra cementing operations is not yet known, requiring a negotiation process to determine the final price. * **Time Sensitivity:** The extra work is likely needed urgently to ensure well stability and prevent potential accidents or delays. **2. Benefits and Drawbacks:** * **Benefits:** * **Project Continuity:** Allowing the extra work prevents delays and potential losses due to the unforeseen geological conditions. * **Addressing Emergencies:** The immediate action taken with AUW ensures well stability and mitigates potential safety risks. * **Drawbacks:** * **Cost Uncertainty:** The lack of upfront pricing for the extra work can lead to unpredictable costs and potential disputes later. * **Contractual Ambiguity:** If not properly managed, the AUW situation can create complex legal challenges and erode trust between the contractor and the owner. **3. Best Practices:** * **Clear Authorization:** Obtain specific written authorization from the owner, clearly outlining the scope of the extra cementing work and the reason for its authorization. * **Transparent Communication:** Keep the owner informed of the progress of the extra work, any potential cost implications, and any issues that arise. * **Detailed Documentation:** Maintain meticulous records of the work performed, including hours, materials, and any additional expenses incurred. This documentation is crucial for the cost negotiation process.
Comments