This Project Documentation Administration Procedure or also known as Document Control Procedure system describes the responsibilities and systems for the receiving, distribution, maintenance and management of all project documents, which have been approved by the responsible individuals/ organizations involved in the PROJECT.
S2.SCOPE
This example of previous project made according to client requirements, provides guide line to establish the actual project procedure covering document & drawing control, document numbering system, and electronic document management system (EDMS). This procedure defines forms and formats for all documents including drawing title and establishes numbering system, etc. This document control program gives principle on how to:
CONTRACTOR shall implement and maintain an Electronic Document Management System (EDMS) for the duration of the Project, so as EDMS ensures all deliverables needed to operate plant is electronically registered, and deliverables is easily and reliably available to CONTRACTOR, COMPANY, Home Office, Site, and other execution locations throughout the course of the Project.
COMPANY given EDMS system architecture will be based on the integration of industry standard, nonproprietary, commercially available software application and hardware components, which meet and undertake the requirements as follows:
Imaging
Deliverables
Workflow
Distribution
Redlining
Indexing
Replication
EDMS/Documents Replication
Scanning
System reporting
Storage Medium
Contractor Hardware/Software
System Testing
System Preference
The following documents (but not limited to) shall be transmitted to the Document Control Group and distributed according to this and the reference procedures.
COMPANY’s Documents
Drawings
Project Execution Plan and Work Procedures
Technical Specifications
Welding Procedure Specification (WPS)
Approved Vendor List revisions
Design Change Notes (DCN), Field Change Notes (FCN), Technical Queries (TQs), Non Conformance Reports (NCRs), Site Queries/Instructions, Variations, Clarifications etc.
The Document Control Group shall maintain and file the current documents and revisions in the EDMS using the agreed structure/hierarchy for document storage.
The Document Control Group shall make available to COMPANY controlled hard copies of all documents including superseded documents such as IFC.
Document Control Group shall ensure that the requirements of preparation, review, approval and distribution of the controlled documents are summarized as shown on the Document Control Chart (Attachment #1).
Document Control Group shall ensure that the latest revision is highlighted by a vertical line in the right-hand margin of changed area. And the revision of form shall be identified by encompassing the changed area with a cloud mark on the form. All denotations of previous revision shall be eliminated.
For Information (IFI)
For Comment (IFC)
For Review (IFR)
For Approval (IFA)
All deliverables shall be issued to COMPANY and must clearly state to whom and for what purpose the document is sent.
All documents shall be prepared according to the applicable procedures, which meet with the requirements of contractual documents and all applicable codes, procedures and standards.
The document numbers shall be assigned according to the relevant procedures depending on the document type. This holds for all documents also generated by COMPANY for example, TQs, NCRs, etc.
A Master Distribution List containing drawings, documents and other deliverables related to the project work shall be prepared and issued to COMPANY and maintained on the EDMS throughout the project duration.
All prepared documents shall be reviewed and approved internally by the responsible Manager for suitability, completeness and accuracy prior to the issue.
All personnel in charge of preparation review and approval shall identify the initial name on the relevant documents. All documents shall be prepared and reviewed by assigned personnel, and approved by responsible Manager.
All revisions of documentation shall be electronically stored within the EDMS.
The documents for COMPANY’s approval shall be internally approved by the CONTRACTOR Project Manager or Site Manager and shall be submitted to COMPANY for review & approval/information as required via the respective organizational DCCs.
CONTRACTOR shall implement all changes to documents that shall be checked, controlled and distributed in the same manner as the original documents.
Document Control Group shall control the document status for approval, distribution and revision status using the EDMS.
The personnel who prepared the documents, which are controlled by the relevant procedures, shall send the documents as an Electronic File to the Document Control Group for distribution of internal organization (Head and/or Site office). The Document Control Group shall designate the “√” in the “□” of the Correspondence Registry Slip (Attachment #2) in accordance with Document Control Chart.
In case the documents are distributed to COMPANY, a subcontractor and/or vendor, the document transmittal forms (letter, facsimile and transmittal) shall be numbered in accordance with the approved numbering system specified in the Coordination Procedure.
Upon the receipt of the external document, Document Control Group shall convert the document into a pdf File, and submit it to the Project Manager or Site Manager for listing of document distribution. The Document Control Group shall designate the “√” in the “□” of the Correspondence Registry Slip (Attachment #2) in accordance with Document Control Chart.
When a document is transmitted from the Document Control Group to the COMPANY, a notification via email shall be sent to all relevant parties indicating that documents have been added to the EDMS. The recipient DCCs shall distribute all relevant documents for review, approval and /or information.
The Document Control Group shall also be responsible for the timely distribution to all parties involved, both internal and external parties.
All revisions of the documents shall be checked, controlled and distributed in the same manner as the original
When revised documents are received, all superseded hard copies of the documents shall be clearly marked “OBSOLETE” by the Document Control Group.
However, the electronic file of each expired or obsolete document shall be kept at EDMS as a reference and for historical purposes.
Documents shall have a unique number and shall be stored in the EDMS and numbered in accordance with the relevant numbering procedures.
All electronic documents stored in the EDMS should be treated with confidentiality and should not be used at anybody's discretion in line with CONTRACTOR Company policies
The Document Control Group shall allocate numbers to all outgoing correspondence and transmittals in accordance with the Coordination Procedure.
Both correspondence and transmittals will be stored electronically in the EDMS. Scanned copies of correspondence and transmittals will only be uploaded after relevant signatures have been received from relevant parties.
Correspondence from CONTRACTOR will be loaded into the EDMS and a notification via email shall be sent to COMPANY, referencing a web hyperlink to the item.
Transmittals for any document will be attached to an email as a File Download Notification, which shall be sent to COMPANY focal points, referencing a web hyperlink to documents/drawings or item being transmitted. On receipt of the email COMPANY will sign transmittal, scan and send back a copy to CONTRACTOR. CONTRACTOR Project/Site Doc Control will load the final transmittal into the EDMS for all parties to view.
COMPANY shall use the CONTRACTOR Correspondence/ Transmittal Numbering Procedure for their issued documents associated with the project. They shall then be attached via email directly to the CONTRACTOR Project/Site Document Control Group for load into the EDMS.
Documents ‘For Information’
CONTRACTOR shall submit ‘For Information’ such drawings and documents specified in the CONTRACT as requiring submission ‘For Information’.
Documents ‘For Comment’
CONTRACTOR shall submit ‘For Comment’ such drawings and documents specified in the CONTRACT as requiring submission ‘For Comment’.
CONTRACTOR shall correct all comments identified by COMPANY. Any disagreements shall be formally resolved with COMPANY prior to the implementation of the document. When implementation of the comments results in substantial modification to the document, COMPANY shall re-issue the modified document, which shall be clearly marked ‘Re-issued For Comment’.
Documents ‘For Approval’
The number of documents requiring approval by COMPANY has been limited in view of the overall responsibility assigned to CONTRACTOR. COMPANY’s predominant role shall be to audit the CONTRACTOR’s review systems to ensure that they meet the specified requirements and that the control system is implemented correctly.
CONTRACTOR shall submit to COMPANY the key drawings and documents specified in the Document Deliverables Register clearly marked ‘For Approval’.
‘Released’ Documents
CONTRACTOR shall issue all drawings and documents, which have been through the necessary review / approvals cycle, as ‘Released’ for procurement, manufacturing, construction, commissioning, etc.
Where significant changes / modifications have been made to documents or drawings issued ‘For Approval’ or ‘For Comment’, the document or drawing shall be re-issued as ‘Re-issued For Approval’ or ‘Re-issued For Comment’ before being issued as ‘Released’.
Significant changes / modifications shall be determined by Lead Engineer.
If ‘Released’ documents are found to be incorrect or earlier comments have not been observed, CONTRCATOR shall immediately undertake all required remedial action. (re-issue, correction note, etc.)
A document title page and drawing title are provided in Attachment #3.. CONTRACTOR has adopted examples as guidance.
Example
The code, which identifies the Units into which the PLANT has been subdivided, shall be included in every technical document and it is assigned as follows:
General
000 General
Process Systems
100 SEAWATER INTAKE
200 SAND FILTERS
300 ENERGY RECOVERY 2
400 ENERGY RECOVERY 1
500 SWRO SKID 1
600 SWRO SKID 2
700 BWRO SKID 1
800 WATER STORAGE
Utilities Systems
1010 Steam System
1020 NEP
1030 CHEMICAL DOSING SKIDS
1040 Electrical Distribution
1050 Instrument and Utility Air System
1060 Interconnecting Systems
1070 Storage Tanks
1080 Drainage and Sewer System
1090 Waste Water Treatment System
1100 Integrated Control System (ICS)
1110 Fire Protection System
1100 Telecommunications System
1110 Fire and Gas Detection System
1120 Buildings
1130 Roads and Fencing
The identification number (item number), is a group of alphanumerical characters unequivocally identifying the type of equipment as per the “Equipment Designation Codes” section (below) and its numerical sequence (for the same type of equipment) in the Unit.
YYYY-X(XX)-NNN Z-(XXNN)
where:
YYYY is the code of the Unit the equipment belongs to.
X(XX) is the code identifying the “type” of equipment (as per “Equipment Designation Code” section)
NN(N) is the sequential number for the same type of equipment in same unit (from 001 to 999)
Z(/Z) is a reference letter for twin, or more, pieces (from A to Z). Equipment serving two or more main equipment shall be tagged by Z/Z(/Z)
(XXNN) to be used only to define ancillary equipment and belonging to an equipment or to a package unit
Example A
| 100 – P - 003 C | ||||
---|---|---|---|---|---|
Unit Code (Process Unit N° 100) |
|
|
|
| |
Pump |
|
|
| ||
3rdpump of Unit 1803 |
|
| |||
Spare (of twin or more pieces) |
|
Drivers shall be identified by the same code as the driven equipment, with the addition of a prefix letter for type (M = Motor, etc.), e.g.:
100 - MP - 003 C |
meaning the electric motor of the 3rd spare pump of Unit 100.
INSTRUMENTATION
Instrument symbols and nomenclature on P&IDs and Utility Flow Diagrams are derived from the Instrument Society of America (ISA) Specification ISA S5.1. However, instrument function codes shall match the respective Refinery.
XXXX - XXXXX - XXX - X
ELECTRICAL
Electrical Tagging system shall be in accordance with the requirements described in 5578-AMD-EU-001, Electrical Design Guidelines.
LINE NUMBERING
Line numbering will be in accordance with the following example:
6” – XXXX – XX – XXX – XXXXXXX - XX
In addition to having a line serial number, all lines get a plant number from the plant in which they originate and they keep that number up to their termination point (unit battery limit). When these are travelling from one area to another area, plant number will change and the line sequence number might change.
Note: The piping class designation for new piping systems under the PROJECT shall follow the criteria given below. This is only for piping classes that do not already exist and need to be added to the PROJECT.
Piping Class number comprises of normally six digits however seven digits may be used for the PROJECT when need arises for a new piping class and shall be as follows:
1 | 2 | 3 | 4 | 5 | 6 | 7 |
First two digits of the Piping class reserved for ASME rating or tubing (1-150#, 3-300#, 6-600#, 9-900#, 15-1500#, 12-125# , T-Tubing).
Third digits reserved for Material (1 - Carbon steel, 2 - low and intermediate alloy steel, 3 - Stainless Steel, 4 - Aluminium and Aluminium alloy, 5 - Copper and copper alloy, 6 - nickel and nickel alloy, 7 - non metallic material, and 8 - lined/galvanized steel).
Fourth digits reserved for Corrosion Allowance (0 - 0 mm, 1 - less than or equal to 1mm and above 0mm, 2 - less than or equal to 2mm and above 1mm, 3 - less than or equal to 3 mm and above 2mm, 5 – less than or equal to 5 mm and above 3 mm, 6 - less than or equal to 6mm and above 3mm, 9 - above 6mm).
Fifth digits for Service (A - Acid, C - Caustic, D - Drain/Sewer, H - Hydrogen, P – Process (General Hydrocarbons), Q - Chlorination Gas, T - Wellhead Piping, U - Utility).
Sixth digit is reserved for numbers (0-9) Sour/Non Sour (1 - Sour, 2 - Non Sour)
Seventh digit (Alpha Character) shall be used only when there is any modification to the original TAKREER piping class. This digit is to make a distinction between like materials (A, B, C, etc.)
P&IDS STREAM NUMBERING
Main process and utilities lines with exception of vent, drain, PSVs, etc., shall be identified by means of a sequence number which define relative process conditions.
This section defines the numbering requirements for general reference documents.
1) PROJECT DOCUMENT/DRAWING CODING SYSTEM
A suitable code shall be attributed to any document prepared within the PROJECT framework in order to allow a functional subdivision of same type of documents and to identify each of them promptly for filing purposes. Any documents, drawing, specification, list etc. will be numbered with COMPANY codes. Refer to Document Class Codes System section (below) for detail codes.
2) NUMBERING SYSTEM
Documentation, drawings and data sheets will be coded as per the rules described in this document. COMPANY coding structure is based on a group of alphanumeric characters to be filled in according to the following criteria.
Drawings example
| X | X | X | X |
| Y | Y | Y | Y | B | B |
|
| Z |
|
|
| W | W | W |
| ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| |||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
| ||||||||||||||||||||||||||
Project Number |
|
|
|
|
| ||||||||||||||||||||||||||||||
Unit Number (See Unit Coding section) |
|
|
|
| |||||||||||||||||||||||||||||||
Document Class Code (See Document Class Codes System section for Details) |
|
|
| ||||||||||||||||||||||||||||||||
Sheet Size ( See Drawing Size Code section for details) |
|
| |||||||||||||||||||||||||||||||||
Serial Number |
|
Drawing serial numbers shall be controlled and allocated by each discipline leader however, the following system can be adopted:
Process and Utility Flow Diagrams (PFD and UFD) 001 through 099
Piping and Instrument Diagrams (P&ID’s) 100 through 199
Utility Distribution Diagrams (UDD) 200 through 299
Auxiliary Flow Diagrams (AFD) 300 through 399
Material Selection Diagrams (MSD) 400 through 499
Piping Drawings 500 through 999
Civil Drawings – Control Building 001 through 049
Civil Drawings – Substation Building 050 through 099
Civil Drawings – Composite Plans of units w/underground 100 through 200
Mechanical Equipment Details 001 through 099
Mechanical Drawing – Equipment 100 through 200
Electrical Single Line Diagrams 001 through 050
Electrical Area Classification Drawings 051 through 100
Electrical Plan Drawings 101 through 200
Instrument System Drawings 101 through 200
Instrument Main cable Routing Drawings 201 through 300
Instrument Location Plan Drawings 301 through 400
Instrument Typical Loop Drawings 401 through 500
Instrument Equipment Layout Drawings 501 through 600
Instrument Logic Diagrams 601 through 700
Instrument Power Distribution Drawings 701 through 800
Note 1: For PFD, UFD and P&ID’s drawing serial number could be of six digits (00101A, 00101B, etc.) in case same drawing is divided in several sheets to permit PDS2D file structure management.
General Engineering Documents, SPECIFICATIONS and Standards
| X | X | X | X |
| Y | Y | Y |
| B | B |
|
| D | D | D |
|
|
|
|
| ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
| ||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
| ||||||||||||||||||||||||||
TAKREER Project Number |
|
|
|
|
| ||||||||||||||||||||||||||||||
Document Prefix (See “Document Prefix Codes System“ section) |
|
|
|
| |||||||||||||||||||||||||||||||
Document Class Code (See “Document Class Codes System” section) |
|
|
| ||||||||||||||||||||||||||||||||
Serial Number (Maximum 5 Digits) |
|
|
Data Sheets (Mechanical)
| X | X | X | X |
| D | S |
| B | B | B | B | D | (D | D | D) |
|
| W | W | W |
| ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
| |||||||||||||||||||||||||
TAKREER Project Number |
|
|
|
|
| |||||||||||||||||||||||||||||
Pre-printed Format |
|
|
|
| ||||||||||||||||||||||||||||||
Unit Number (See “Unit Coding” section) |
|
|
| |||||||||||||||||||||||||||||||
See allocated “Equipment Designation Codes” section |
|
| ||||||||||||||||||||||||||||||||
Instrument/Equipment Serial Number |
|
Example: For Mechanical Equipment: 5578-DS-1815-B-001 – Data sheet for Heater in Unit 1815
Data Sheets (Instrument)
| X | X | X | X |
| D | S |
| B | B | B | B | X | X | X | X |
|
| W | W | W |
| ||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
| |||||||||||||||||||||||||
Project Number |
|
|
|
|
| |||||||||||||||||||||||||||||
Pre-printed Format |
|
|
|
| ||||||||||||||||||||||||||||||
Unit Number (See “Unit Coding” section) |
|
|
| |||||||||||||||||||||||||||||||
Allocated Instrument Code (See P&ID Lead Sheets for description) |
|
| ||||||||||||||||||||||||||||||||
Instrument/Equipment Serial Number |
|
Example: For Instrument: 5578-DS-1804-PT-101- – Data sheet for Pressure Transmitter in Unit 1804.
Summaries, Lists, Material Selection Guides. Calculation Notes, MTO, Process Design Basis
| X | X | X | X | Y | Y | Y | Y |
| B | B |
|
| D | D | D |
|
|
|
|
| |||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| ||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
| |||||||||||||||||||||||||
TAKREER Project Number |
|
|
|
| ||||||||||||||||||||||||||||||
Unit Number (See “Unit Coding” section) |
|
|
| |||||||||||||||||||||||||||||||
Document Class Code (See “Document Class Codes System” section) |
|
| ||||||||||||||||||||||||||||||||
Serial Number |
|
Material Requisitions/Subcontract Agreements
| X | X | X | X |
| 0 | 0 | 0 | 0 |
| B | B |
|
|
|
|
|
| W | W |
| ||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| |||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
| |||||||||||||||||||||||||
TAKREER Project Number |
|
|
|
|
| ||||||||||||||||||||||||||||||
Unit Number (See “Unit Coding” section) |
|
|
|
| |||||||||||||||||||||||||||||||
Document Prefix (See “Doc. Prefix Code System” section) |
|
|
| ||||||||||||||||||||||||||||||||
Blank (Not Used) |
|
| |||||||||||||||||||||||||||||||||
Serial Number |
|
Electronic File Naming of PROJECT documents and Engineering documents and drawings shall be as follows:
General Engineering Documents, Specification, Standards, Lists, MRS
Electronic file naming shall be the COMPANY number adding at the end, before the file extension, attachment indication (if any) and the revision index.
Example: 5578-EPC-PA-015_RA.doc
5578-EPC-PA-004-ATT-3_R1.doc
5578-SP-CU-013_RB.doc
Data Sheets
Electronic file naming shall be the COMPANY number adding at the end, before the file extension, the revision index.
Example: 5578-DS-803-F-001_PRA.xls
5578-DS-803-B-003_R0.xls
Engineering Drawing
Electronic file naming shall be the COMPANY number adding at the end, before the file extension, the sheet number and the revision index.
Example: 5578-1000-CU-D-00001-01_RA.dwg
5578-1001-PU-D-00501-02_R0.dwg
For P&IDs, PFDs and MSDs electronic file names shall be as follows:
| X | X | X | X |
| Y | Y | Y | Y |
|
| Z |
| W |
| K | K | K | K |
| |||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
| ||||||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
| |||||||||||||||||||||||||
Unit |
|
|
|
|
|
| |||||||||||||||||||||||||||||
Serial number (last four digit) |
|
|
|
|
| ||||||||||||||||||||||||||||||
Sheet number |
|
|
|
| |||||||||||||||||||||||||||||||
Revision number |
|
|
| ||||||||||||||||||||||||||||||||
Extension |
|
|
|
For piping layout, electronic file names shall be as follows:
| X | X | X | X |
| Y | Y |
|
| Z |
| WWW |
| K |
|
| |||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
| ||||||||||||||||||||||||||||||
|
|
|
|
|
|
|
|
|
|
| |||||||||||||||||||||
Unit (See “Unit Coding” section) |
|
|
|
|
|
| |||||||||||||||||||||||||
Document Class Code (See “Document Class Codes System” section) |
|
|
|
|
| ||||||||||||||||||||||||||
Size Code (See “Drawing Size Code” section) |
|
|
|
| |||||||||||||||||||||||||||
Drawing Serial Number |
|
|
| ||||||||||||||||||||||||||||
Sheet Progressive Number |
|
|
|
For isometric sketches, electronic file names shall be as follows:
| XX | - YYYY | FF | ZZZ. | iNN | ||||||||||||||
|
|
|
|
|
| ||||||||||||||
|
|
|
|
|
|
|
|
|
|
|
| ||||||||
Area (1) |
|
|
|
|
| ||||||||||||||
Unit (2) |
|
|
|
|
| ||||||||||||||
Fluid (3) |
|
|
|
|
| ||||||||||||||
Line Serial Number (4) |
|
|
|
|
| ||||||||||||||
Sheet Progressive Number (5) |
|
|
|
|
|
(1) Possible values: A1, A2, A3, A4, A5, A6, A7, A8, B, C, CCR, D, E F, G
(2) Two or three digits
(3) One to four digits
(4) Three digits. When provided by line list, a two-letter code may be added before the digits
(5) Two digits
Hyphen (-), dot (.) and letter “i” are fixed
PIPING SPECIALTY ITEMS
Equipment Code | Equipment Name |
CPL | Coupler / Adapter |
EJT | Expansion Joint |
FAB | Fabrication (i.e. Injection nozzle, spargers) |
FLX | Flexible Hose |
FTA | Float Trap Assembly |
MROV | Multiple Restriction Orifice Plate |
NOZ | Spray Nozzle |
SC | Sample Connection Assembly |
SSW | Safety Shower and Eye Wash |
STA | Steam Traps |
STR | Permanent Strainer |
ELECTRICAL EQUIPMENT
Equipment Code | Equipment Name |
MCC | Motor Control Centre |
TPC | Turnaround Power Centre |
ASP | Aux. Panel Board |
DC | Distribution Board |
LP | Lighting Panel |
PFI | Capacitor Panel |
AB | Accumulator Battery |
EPB | Emergency Diesel Generator Set |
TMM + TMC | Power Transformer |
MS + MCCM | Switchgears 3.3 kV |
MMS | Switchgears 11 kV |
PC | Switchgears 415 V |
EE | Electrical Heater |
BD | Bus Duct |
NGR | Neutral Grounding Resistor |
UPS | AC UPS System/Boards |
IPCS | Integrated Prot-Control System |
MECHANICAL EQUIPMENT
Equipment Code | Equipment Name |
B | Heater, Furnace & Boiler |
C | Columns |
D | Drums & Reactors |
P | Internals |
E | Exchangers & Condensers |
EA | Air Coolers |
EX | Expander |
MEA | Motors for Air Coolers |
F | Tanks |
G | Pumps |
H | Ejectors |
K | Compressors & Blowers |
V | Miscellaneous (Filters, etc.) |
MV | Motor for Miscellaneous Equipment |
W | Desalinator |
EG | Diesel Engine for Pumps |
MG | Motors for Pumps |
TG | Drivers or Alternators for Pumps |
EK | Diesel Engine for Compressors |
MK | Motors for Compressors |
TK | Drivers for Compressors |
VC | Electrochlorinator |
EP | Diesel Generators |
VLA | Loading Arms |
GT | Gas Turbines |
GTG | Gas Turbine Generators |
ST | Steam Turbines |
STG | Steam Turbine Generators |
WHB | Waste Heat Boiler |
ME | Miscellaneous Packaged Equipment |
VH | Miscellaneous Handling Equipment (i.e. hoist) |
MVH | Motor for Misc. Handling Equipment |
AHU | Air Handling Unit |
ACCU | Air Cooled Condensing Unit |
CFU | Chemical Filtration Unit |
The term “INTERNAL TREATED” indicates linings and/or internal coatings. Refer to piping line class for details.
The term “EXTERNAL COATED” indicates applies to polymeric and/or asphaltic (not painting). Refer to the coatings SPECIFICATION for details.
COATINGS – INSULATED OR PAINTED LINE | |
CODE | DESCRIPTION |
A | INTERNAL TREATED + EXTERNAL COATED LINE |
B | EXTERNAL COATED LINE ONLY |
E | ELECTRIC TRACED LINE + INSULATED + PAINTED |
F | COLD INSULATED LINE + PAINTED |
I | HOT INSULATED LINE + PAINTED |
N | NOT PAINTED/INSULATED LINE |
S | INTERNAL TREATED + EXTERNAL PAINTED LINE |
T | STEAM TRACED LINE + INSULATED + PAINTED |
V | EXTERNAL PAINTED LINE ONLY |
W | STEAM JACKET + INSULATED + PAINTED |
PP | PERSONNEL PROTECTION + PAINTED |
AA | ACOUSTIC ATTENUATION INSULATION + PAINTED |
| SPECIAL APPLICATIONS |
EXAMPLE |
| |||||||||
S | P |
|
| M | K |
| 0 | 0 | 1 |
Document Prefix | Document Class | Serial Number | |
|
| Code |
|
|
| (See Below) |
|
| FIRST DIGIT | Process/Piping | ‘P’ |
|
| Mechanical | ‘M’ |
|
| MET | ‘N’ |
|
| Electrical | ‘E’ |
|
| Instrumentation | ‘I’ |
|
| Civil/Structural | ‘C’ |
|
| Architectural | ‘A’ |
|
| Loss Prevention | ‘F’ |
|
| Health Safety & Environmental | ‘H’ |
| SECOND DIGIT |
|
|
|
|
|
|
|
|
NOTE: |
|
|
|
|
|
|
|
|
|
a. | The term “general” refers to project wide documents (overall plot plan, single lines, grading, etc.). |
|
|
|
|
|
|
|
|
b. | The term “others” applies to plant specific documents. |
|
|
|
|
| (1) | Process/Piping – General | ‘U’ |
|
|
| Process/Piping – Others | ‘P’ |
|
|
|
|
|
|
| (2) | Mechanical – General | ‘U’ |
|
|
| Mechanical – Others | See Attached |
|
|
|
|
|
|
| (3) | Electrical – General | ‘U’ |
|
|
| Electrical – Others | ‘E’ (Equipment) |
|
|
|
|
|
|
| (4) | Instrumentation – General | ‘U’ |
|
|
| Instrumentation – Others | ‘E’ (Equipment) |
|
|
| Instrumentation – Systems | ‘S’ |
|
|
|
|
|
|
| (5) | Civil/Structural/Arch. – General | ‘U’ |
|
|
| Civil/Structural/Arch. – Others | ‘C’
|
|
|
|
|
|
|
| (6) | MET – General | ‘U’
|
MECHANICAL (SECOND DIGIT DESIGNATION) | |
| |
| Package Equipment ‘A’ |
| Columns, Splitters, Scrubbers ‘C’ |
| Reactor, Vert. Drum, Vessels, Horizontal Vessels, Separators ‘D’ |
| Heaters ‘B’ |
| Pumps ‘G’ |
| Compressors, Blowers, Fans ‘K’ |
| Turbines ‘T’ |
| Ejectors, Mixers ‘V’ |
| Heat Exchangers, Generators (Steam) ‘E’ |
| Air Coolers ‘P’ |
| Storage Tanks ‘F’ |
| Loading Arm ‘L’ |
| Insulation ‘N’ |
| Welding & Metallurgy ‘W’ |
| Painting ‘X’ |
| Coating/Wrapping ‘Y’ |
| HVAC ‘H’ |
| Motors ‘M’ |
|
|
| Note: all discipline General Specifications to be designated ‘U’ |
|
|
FOR PROJECT GENERAL MANUALS USE THE ADDITIONAL DESIGNATIONS | |
| |
| Project Management ‘PA’ |
| Procurement ‘PB’ |
| Project Controls ‘PC’ |
DOCUMENT PREFIX CODES SYSTEM
PREFIX | DOCUMENT |
AMD | AMENDMENT TO DESIGN GENERAL SPECIFICATION (DGS) |
MAN | MANUAL |
STU | STUDIES |
REP | REPORTS |
EPC | EPC PACKAGES |
| - PROJECT PROCEDURES |
| - PROJECT PLAN |
EST | COST ESTIMATES |
TEC | TECHNICAL DOCUMENTS (MISC.) |
| - PHILOSOPHIES |
| - EVALUATIONS |
| - PROJECT SCHEDULES AND SUMMARIES |
| - PARTICULAR TERMS AND CONDITIONS |
| - QUALITY CONTROL PLAN |
MR | MATERIAL REQUISITION |
SR | SCOPE OF SUPPLY |
AW | AWARD RECOMMENDATION |
SP | PROJECT SPECIFICATION |
DS | DATA SHEET |
VR | DOCUMENT & DRAWING SUPPLY |
PC | PROJECT CONTROL PROCEDURE |
ITP | INSPECTION TEST PLAN |
QE | QUESTIONNAIRE |
NM | DEVIATION LIST |
IRC | INSPECTION RELEASE CERTIFICATE |
RN | RELEASE FOR DELIVERY |
NCR | NON CONFORMANCE REPORT |
MT | TECHNICAL TABULATION |
PS | PRICE SCHEDULE |
CS | SUBCONTRACT AGREEMENT |
MS | METHOD STATEMENT |
STD | STANDARDS |
PSD | PROJECT STANDARD DRAWING |
MDRB | MANUFACTURING DATA REPORT BOOK |
PEP | PROJECT EXECUTION PLAN |
HSE | HEALTH, SAFETY & ENVIRONMENTAL PLAN |
QA | QUALITY ASSURANCE PLAN |
SOW | SCOPE OF WORK |
DRAWING SIZE CODE
Code | Size | Dimensions (mm) |
A | A4 | 210 X 297 |
B | A3 | 294 X 420 |
C | A2 | 420 X 594 |
D | A1 | 594 X 841 |
E | A0 | 841 X 1189 |
Engineering Manager shall maintain the numbering system for VENDOR documents for the WORK. All Vendor documents shall be numbered and sorted as per vendor package category.
Vendor Deliverable Register (Supplier Document Schedule) shall be submitted to COMPANY. COMPANY defines the requirement of review/information documents. As per the instructed Vendor Deliverable Register from COMPANY, CONTRACTOR shall submit to COMPANY all the documents and drawings upon receipt from the Vendor.
Vendor document will be managed as the same manner of engineering deliverables. The Vendor Deliverable Register maintenance shall be as same as the DDR.
ATTACHMENT 1 – Document Control Chart
ATTACHMENT 2 - Correspondence Registry Slip
ATTACHMENT 3 - Document Title Page and Drawing Title Block