Detail | Activity Code | Activity Name | Status | Critical | Percent Complete | Start | Finish |
---|---|---|---|---|---|---|---|
View Details | A1000 | Contract signature | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-05-15T08:00:00 |
View Details | A1010 | Mobilization (phase 1) | Not Started | No | 0.0 | 2014-05-29T08:00:00 | 2014-05-29T08:00:00 |
View Details | A1020 | Free issue Main pipe line material | Not Started | Yes | 0.0 | 2014-05-29T08:00:00 | 2014-05-29T08:00:00 |
View Details | A1030 | Engineering completion (As built doc not included) | Not Started | No | 0.0 | 2014-08-27T08:00:00 | 2014-08-27T08:00:00 |
View Details | A1040 | Main pipe line Hydrotest (phase 2) | Not Started | No | 0.0 | 2014-11-27T08:00:00 | 2014-11-27T08:00:00 |
View Details | A1050 | PO of Flare system | Not Started | No | 0.0 | 2014-07-26T08:00:00 | 2014-07-26T08:00:00 |
View Details | A1060 | Arrival of the final balance of Bulk material to site | Not Started | No | 0.0 | 2014-11-22T08:00:00 | 2014-11-22T08:00:00 |
View Details | A1070 | Mechanical completion work | Not Started | Yes | 0.0 | 2014-12-27T08:00:00 | 2014-12-27T08:00:00 |
View Details | A1080 | Provisional acceptance & Project hand over | Not Started | Yes | 0.0 | 2015-02-16T08:00:00 | 2015-02-16T08:00:00 |
View Details | A1090 | Data gathering (OMV) - Flare system | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-05-15T08:00:00 |
View Details | A1100 | FEED review & endorsment | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-06-11T17:00:00 |
View Details | A1110 | Issue of DCR | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-06-11T17:00:00 |
View Details | A1120 | Piping engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-08-20T17:00:00 |
View Details | A1130 | Mechanical engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-08-20T17:00:00 |
View Details | A1140 | Electrical engineering | Not Started | Yes | 0.0 | 2014-06-20T08:00:00 | 2014-08-21T17:00:00 |
View Details | A1150 | Instrumentation engineering | Not Started | No | 0.0 | 2014-06-30T08:00:00 | 2014-08-22T17:00:00 |
View Details | A1160 | Civil & Strucural engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-08-08T17:00:00 |
View Details | A1170 | Process engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-07-31T17:00:00 |
View Details | A1180 | Piping engineering | Not Started | Yes | 0.0 | 2014-06-30T08:00:00 | 2014-08-08T17:00:00 |
View Details | A1190 | Mechanical engineering | Not Started | Yes | 0.0 | 2014-06-30T08:00:00 | 2014-08-08T17:00:00 |
View Details | A1200 | Electrical engineering | Not Started | Yes | 0.0 | 2014-07-16T08:00:00 | 2014-08-26T17:00:00 |
View Details | A1210 | Instrumentation engineering | Not Started | Yes | 0.0 | 2014-07-16T08:00:00 | 2014-08-26T17:00:00 |
View Details | A1220 | Civil & Structural engineering | Not Started | Yes | 0.0 | 2014-07-16T08:00:00 | 2014-08-26T17:00:00 |
View Details | A1230 | Procurement of Bulk material | Not Started | Yes | 0.0 | 2014-07-28T08:00:00 | 2014-11-21T17:00:00 |
View Details | A1250 | Procurement of Flare system | Not Started | Yes | 0.0 | 2014-07-28T08:00:00 | 2014-12-12T17:00:00 |
View Details | A1240 | Arrival of Flare system site | Not Started | No | 0.0 | 2014-12-13T08:00:00 | 2014-12-13T08:00:00 |
View Details | A1260 | Civil work | Not Started | No | 0.0 | 2014-08-07T08:00:00 | 2014-12-12T16:00:00 |
View Details | A1270 | Main pipe line works | Not Started | Yes | 0.0 | 2014-06-16T08:00:00 | 2014-12-08T16:00:00 |
View Details | A1280 | Electrical work | Not Started | No | 0.0 | 2014-11-01T08:00:00 | 2014-12-23T16:00:00 |
View Details | A1290 | Instrumentation work | Not Started | No | 0.0 | 2014-10-09T08:00:00 | 2014-12-23T16:00:00 |
View Details | A1300 | Piping works | Not Started | No | 0.0 | 2014-11-15T08:00:00 | 2014-12-19T16:00:00 |
View Details | A1310 | Civil & Structural works (including pipe rack fabrication) | Not Started | No | 0.0 | 2014-08-27T08:00:00 | 2014-12-03T16:00:00 |
View Details | A1320 | Mechanical work | Not Started | Yes | 0.0 | 2014-11-22T08:00:00 | 2014-12-27T08:00:00 |
View Details | A1330 | Electrical works | Not Started | No | 0.0 | 2014-10-18T08:00:00 | 2014-12-20T16:00:00 |
View Details | A1340 | Instrumentation works | Not Started | No | 0.0 | 2014-11-13T08:00:00 | 2014-12-23T16:00:00 |
View Details | A1350 | Precommissioning works | Not Started | Yes | 0.0 | 2014-12-27T08:00:00 | 2015-01-24T16:00:00 |
View Details | A1360 | Commissioning work | Not Started | Yes | 0.0 | 2015-01-25T08:00:00 | 2015-02-15T16:00:00 |
View Details | A1370 | Other engineering | Not Started | No | 0.0 | 2014-05-29T08:00:00 | 2015-02-04T17:00:00 |
View Details | A1380 | Piping work | Not Started | No | 0.0 | 2014-11-13T08:00:00 | 2014-12-23T16:00:00 |
View Details | A1390 | Procurement of PR & PL | Not Started | Yes | 0.0 | 2014-08-11T08:00:00 | 2014-12-05T17:00:00 |
View Details | A1400 | Procurement of LVS | Not Started | Yes | 0.0 | 2014-08-11T08:00:00 | 2014-12-05T17:00:00 |
View Details | A1410 | Procurement of Slug catcher | Not Started | Yes | 0.0 | 2014-08-11T08:00:00 | 2014-12-05T17:00:00 |
View Details | A1420 | PO of Slug catcher | Not Started | No | 0.0 | 2014-08-09T08:00:00 | 2014-08-09T08:00:00 |
View Details | A1430 | PO of PL, PR | Not Started | No | 0.0 | 2014-08-09T08:00:00 | 2014-08-09T08:00:00 |
View Details | A1440 | PO of LVS | Not Started | No | 0.0 | 2014-08-09T08:00:00 | 2014-08-09T08:00:00 |
View Details | A1450 | Arrival of PL & PR to site | Not Started | No | 0.0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
View Details | A1470 | Arrival of Slug catcher to site | Not Started | No | 0.0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
View Details | A1480 | Arrival of LVS to site | Not Started | No | 0.0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
View Details | A1460 | Land transportation of main pipe line | Not Started | Yes | 0.0 | 2014-05-29T08:00:00 | 2014-06-14T16:00:00 |
Project ID | : | 1230010 | |||
Project Flag | : | Y | Project Web Site URL | : | None |
Default Cost Account | : | Rate Type | : | COST_PER_QTY | |
Link Percent Complete With Actual | : | Y | Drive Activity Dates Default | : | Y |
Link actual to date and actual this period units and costs | : | Y | Default Activity Type | : | TT_Task |
Add Actual To Remain | : | N | Project Forecast Start | : | None |
Added By | : | admin | Financial Period Calendar ID | : | None |
Date Added | : | 2014-05-04 00:00 | Fiscal Year Begins | : | 1 |
Can resources mark activities completed | : | Y | Global Unique ID | : | vcgMYr6PyE6GxfbHxoTXbQ |
Allow Negative Actual Units | : | N | History Interval | : | |
Last Apply Actuals Date | : | None | History Level | : | |
Baseline Type | : | None | Integrated Project | : | |
Enable Summarization | : | Y | Last Update Date | : | None |
Date Checked Out | : | Last Checksum | : | None | |
Project Check-out Status | : | N | Financial Period | : | None |
Checked Out By | : | Last Leveled Date | : | ||
Resources Edit Percent Complete | : | Last Recalc Date | : | 2014-05-04 00:00 | |
Default Calendar | : | 178 | Last Scheduled Date | : | |
Status Update Control | : | Last Summarized Date | : | None | |
Cost Qty Recalc Flag | : | N | Project Location | : | None |
Content Repository External UUID | : | None | MS Project Managed Flag | : | |
Critical activities have float less than or equal to | : | 0 | Code Separator | : | . |
critical_path_type | : | CT_TotFloat | Original Project | : | None |
Default Percent Complete Type | : | CP_Drtn | Must Finish By | : | None |
Default Price / Unit | : | 0.0000 | Planned Start | : | 2014-05-15 00:00 |
Default Duration Type | : | DT_FixedDUR2 | Project Leveling Priority | : | 10 |
Default Price Time Units | : | QT_Hour | Unique ID | : | 4560 |
Change Chart Timescale
Code | Name | Status | Critical | Percent Complete | Start | Finish |
---|---|---|---|---|---|---|
26063 | EPCC TRUNK LINE REV 01 | |||||
26064 | PROJECT MANAGEMENT | |||||
26065 | KEY MILESTONES | |||||
A1000 | Contract signature | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-05-15T08:00:00 |
A1010 | Mobilization (phase 1) | Not Started | No | 0.0 | 2014-05-29T08:00:00 | 2014-05-29T08:00:00 |
A1020 | Free issue Main pipe line material | Not Started | Yes | 0.0 | 2014-05-29T08:00:00 | 2014-05-29T08:00:00 |
A1030 | Engineering completion (As built doc not included) | Not Started | No | 0.0 | 2014-08-27T08:00:00 | 2014-08-27T08:00:00 |
A1040 | Main pipe line Hydrotest (phase 2) | Not Started | No | 0.0 | 2014-11-27T08:00:00 | 2014-11-27T08:00:00 |
A1050 | PO of Flare system | Not Started | No | 0.0 | 2014-07-26T08:00:00 | 2014-07-26T08:00:00 |
A1060 | Arrival of the final balance of Bulk material to site | Not Started | No | 0.0 | 2014-11-22T08:00:00 | 2014-11-22T08:00:00 |
A1070 | Mechanical completion work | Not Started | Yes | 0.0 | 2014-12-27T08:00:00 | 2014-12-27T08:00:00 |
A1080 | Provisional acceptance & Project hand over | Not Started | Yes | 0.0 | 2015-02-16T08:00:00 | 2015-02-16T08:00:00 |
A1090 | Data gathering (OMV) - Flare system | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-05-15T08:00:00 |
A1240 | Arrival of Flare system site | Not Started | No | 0.0 | 2014-12-13T08:00:00 | 2014-12-13T08:00:00 |
A1420 | PO of Slug catcher | Not Started | No | 0.0 | 2014-08-09T08:00:00 | 2014-08-09T08:00:00 |
A1430 | PO of PL, PR | Not Started | No | 0.0 | 2014-08-09T08:00:00 | 2014-08-09T08:00:00 |
A1440 | PO of LVS | Not Started | No | 0.0 | 2014-08-09T08:00:00 | 2014-08-09T08:00:00 |
A1450 | Arrival of PL & PR to site | Not Started | No | 0.0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
A1470 | Arrival of Slug catcher to site | Not Started | No | 0.0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
A1480 | Arrival of LVS to site | Not Started | No | 0.0 | 2014-12-06T08:00:00 | 2014-12-06T08:00:00 |
26067 | ENGINEERING | |||||
26068 | PROCUREMENT | |||||
26069 | CONSTRUCTION | |||||
26070 | COMMISSIONING & START UP | |||||
A1350 | Precommissioning works | Not Started | Yes | 0.0 | 2014-12-27T08:00:00 | 2015-01-24T16:00:00 |
A1360 | Commissioning work | Not Started | Yes | 0.0 | 2015-01-25T08:00:00 | 2015-02-15T16:00:00 |
26071 | GENERAL | |||||
A1100 | FEED review & endorsment | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-06-11T17:00:00 |
A1110 | Issue of DCR | Not Started | Yes | 0.0 | 2014-05-15T08:00:00 | 2014-06-11T17:00:00 |
A1370 | Other engineering | Not Started | No | 0.0 | 2014-05-29T08:00:00 | 2015-02-04T17:00:00 |
26072 | PIPE LINE | |||||
26073 | WAHA RECEPTION FACILITY | |||||
26074 | PROCESS | |||||
A1170 | Process engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-07-31T17:00:00 |
26075 | PIPING | |||||
A1120 | Piping engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-08-20T17:00:00 |
26076 | MECHANICAL | |||||
A1130 | Mechanical engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-08-20T17:00:00 |
26077 | ELECTRICAL | |||||
A1140 | Electrical engineering | Not Started | Yes | 0.0 | 2014-06-20T08:00:00 | 2014-08-21T17:00:00 |
26078 | INSTRUMENTATION | |||||
A1150 | Instrumentation engineering | Not Started | No | 0.0 | 2014-06-30T08:00:00 | 2014-08-22T17:00:00 |
26079 | CIVIL & STRUCTURAL | |||||
A1160 | Civil & Strucural engineering | Not Started | Yes | 0.0 | 2014-06-12T08:00:00 | 2014-08-08T17:00:00 |
26080 | PIPING | |||||
A1180 | Piping engineering | Not Started | Yes | 0.0 | 2014-06-30T08:00:00 | 2014-08-08T17:00:00 |
26081 | MECHANICAL | |||||
A1190 | Mechanical engineering | Not Started | Yes | 0.0 | 2014-06-30T08:00:00 | 2014-08-08T17:00:00 |
26082 | ELECTRICAL | |||||
A1200 | Electrical engineering | Not Started | Yes | 0.0 | 2014-07-16T08:00:00 | 2014-08-26T17:00:00 |
26083 | INSTRUMENTATION | |||||
A1210 | Instrumentation engineering | Not Started | Yes | 0.0 | 2014-07-16T08:00:00 | 2014-08-26T17:00:00 |
26084 | CIVIL & STRUCTURAL | |||||
A1220 | Civil & Structural engineering | Not Started | Yes | 0.0 | 2014-07-16T08:00:00 | 2014-08-26T17:00:00 |
26085 | BULK MATERIAL ( INCLUDING ELECTRICAL & INSTRUMENTATION ) | |||||
A1230 | Procurement of Bulk material | Not Started | Yes | 0.0 | 2014-07-28T08:00:00 | 2014-11-21T17:00:00 |
26086 | MECHANICAL EQUIPMENT | |||||
A1250 | Procurement of Flare system | Not Started | Yes | 0.0 | 2014-07-28T08:00:00 | 2014-12-12T17:00:00 |
A1390 | Procurement of PR & PL | Not Started | Yes | 0.0 | 2014-08-11T08:00:00 | 2014-12-05T17:00:00 |
A1400 | Procurement of LVS | Not Started | Yes | 0.0 | 2014-08-11T08:00:00 | 2014-12-05T17:00:00 |
A1410 | Procurement of Slug catcher | Not Started | Yes | 0.0 | 2014-08-11T08:00:00 | 2014-12-05T17:00:00 |
26087 | MAIN PIPE LINE | |||||
26088 | MECHANICAL WORK | |||||
A1270 | Main pipe line works | Not Started | Yes | 0.0 | 2014-06-16T08:00:00 | 2014-12-08T16:00:00 |
A1460 | Land transportation of main pipe line | Not Started | Yes | 0.0 | 2014-05-29T08:00:00 | 2014-06-14T16:00:00 |
26089 | ELECTRICAL WORK | |||||
A1280 | Electrical work | Not Started | No | 0.0 | 2014-11-01T08:00:00 | 2014-12-23T16:00:00 |
26090 | INSTRUMENTATION | |||||
A1290 | Instrumentation work | Not Started | No | 0.0 | 2014-10-09T08:00:00 | 2014-12-23T16:00:00 |
26091 | CIVIL & STRUCTURAL WORK | |||||
A1260 | Civil work | Not Started | No | 0.0 | 2014-08-07T08:00:00 | 2014-12-12T16:00:00 |
26092 | WAHA ECEPTION FACILITY | |||||
26093 | PIPING WORK | |||||
A1300 | Piping works | Not Started | No | 0.0 | 2014-11-15T08:00:00 | 2014-12-19T16:00:00 |
26094 | CIVIL & STRUCTURAL WORK | |||||
A1310 | Civil & Structural works (including pipe rack fabrication) | Not Started | No | 0.0 | 2014-08-27T08:00:00 | 2014-12-03T16:00:00 |
26095 | MECHANICAL WORK | |||||
A1320 | Mechanical work | Not Started | Yes | 0.0 | 2014-11-22T08:00:00 | 2014-12-27T08:00:00 |
26096 | ELECTRICAL WORK | |||||
A1330 | Electrical works | Not Started | No | 0.0 | 2014-10-18T08:00:00 | 2014-12-20T16:00:00 |
26097 | INSTRUMENTATION WORK | |||||
A1340 | Instrumentation works | Not Started | No | 0.0 | 2014-11-13T08:00:00 | 2014-12-23T16:00:00 |
26098 | Piping work | |||||
A1380 | Piping work | Not Started | No | 0.0 | 2014-11-13T08:00:00 | 2014-12-23T16:00:00 |
Unique ID | Title | Author | Description | External Document Key | Deliverable | Document Category | Revision Date |
Unique ID | WBS Code | WBS Name | Project Status | Sort Order | Project Node | Project | WBS Category | Parent WBS | Original Budget | Independent ETC Total Cost | Independent ETC Labor Units | Responsible Manager | User Reviewing Status | Contains Summary Data | Methodology Global Unique ID | ||
26063 | EPCC TRUNK LINE REV 01 | ||||||||||||||||
26064 | PROJECT MANAGEMENT | ||||||||||||||||
26065 | KEY MILESTONES | ||||||||||||||||
26067 | ENGINEERING | ||||||||||||||||
26068 | PROCUREMENT | ||||||||||||||||
26069 | CONSTRUCTION | ||||||||||||||||
26070 | COMMISSIONING & START UP | ||||||||||||||||
26071 | GENERAL | ||||||||||||||||
26072 | PIPE LINE | ||||||||||||||||
26073 | WAHA RECEPTION FACILITY | ||||||||||||||||
26074 | PROCESS | ||||||||||||||||
26075 | PIPING | ||||||||||||||||
26076 | MECHANICAL | ||||||||||||||||
26077 | ELECTRICAL | ||||||||||||||||
26078 | INSTRUMENTATION | ||||||||||||||||
26079 | CIVIL & STRUCTURAL | ||||||||||||||||
26080 | PIPING | ||||||||||||||||
26081 | MECHANICAL | ||||||||||||||||
26082 | ELECTRICAL | ||||||||||||||||
26083 | INSTRUMENTATION | ||||||||||||||||
26084 | CIVIL & STRUCTURAL | ||||||||||||||||
26085 | BULK MATERIAL ( INCLUDING ELECTRICAL & INSTRUMENTATION ) | ||||||||||||||||
26086 | MECHANICAL EQUIPMENT | ||||||||||||||||
26087 | MAIN PIPE LINE | ||||||||||||||||
26088 | MECHANICAL WORK | ||||||||||||||||
26089 | ELECTRICAL WORK | ||||||||||||||||
26090 | INSTRUMENTATION | ||||||||||||||||
26091 | CIVIL & STRUCTURAL WORK | ||||||||||||||||
26092 | WAHA ECEPTION FACILITY | ||||||||||||||||
26093 | PIPING WORK | ||||||||||||||||
26094 | CIVIL & STRUCTURAL WORK | ||||||||||||||||
26095 | MECHANICAL WORK | ||||||||||||||||
26096 | ELECTRICAL WORK | ||||||||||||||||
26097 | INSTRUMENTATION WORK | ||||||||||||||||
26098 | Piping work |