Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDTcDLOvBmRMeA9ApDbIaqTw
Unique ID2908269
Activity NamePurchasing - Fresh Water System Piping
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307897
Total Float592.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration560.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 21, 2014, 8 a.m.
Actual StartNone
Activity IDJ4760
Early StartJune 21, 2014, 8 a.m.
Late StartSept. 3, 2014, 8 a.m.
Remaining Early FinishAug. 29, 2014, 4 p.m.
Remaining Early StartJune 21, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDbQVbHNsnV0WV4wpDy/nfbQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishAug. 29, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishAug. 29, 2014, 4 p.m. 
Late FinishNov. 11, 2014, 4 p.m. 
Remaining Late FinishNov. 11, 2014, 4 p.m. 
Remaining Late StartSept. 3, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
560.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907333-560.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2908270-440.0 PR_FS
Back