Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDw6lIwlxtSRax+gtGJC+01Q
Unique ID2908263
Activity NameDelivery Time (incl. Detail Engineering) - Fresh Water System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307896
Total Float592.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1680.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 29, 2014, 8 a.m.
Actual StartNone
Activity IDJ4560
Early StartJune 29, 2014, 8 a.m.
Late StartSept. 11, 2014, 8 a.m.
Remaining Early FinishJan. 24, 2015, 4 p.m.
Remaining Early StartJune 29, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDqbMVrNcY3UW42rA9vo5wkw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJan. 24, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJan. 24, 2015, 4 p.m. 
Late FinishApril 8, 2015, 4 p.m. 
Remaining Late FinishApril 8, 2015, 4 p.m. 
Remaining Late StartSept. 11, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1680.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29082620.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2908264-112.0 PR_FS
29082650.0 PR_FS
Back