Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDQOzbWMKZSs2tNWybj+4bRg
Unique ID2908241
Activity NameDelivery Time - Chlorination System Piping
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307892
Total Float816.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1200.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJuly 6, 2014, 8 a.m.
Actual StartNone
Activity IDJ3660
Early StartJuly 6, 2014, 8 a.m.
Late StartOct. 16, 2014, 8 a.m.
Remaining Early FinishDec. 2, 2014, 4 p.m.
Remaining Early StartJuly 6, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDyLWIW9vQ6ECk6PR0lJeBnA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishDec. 2, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishDec. 2, 2014, 4 p.m. 
Late FinishMarch 14, 2015, 4 p.m. 
Remaining Late FinishMarch 14, 2015, 4 p.m. 
Remaining Late StartOct. 16, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1200.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29082400.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29082420.0 PR_FS