Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDI2AKqsYQT2eL5FMsqZ9xQQ
Unique ID2908213
Activity NameShipment (Placeholder / MIG Scope) - Nitrogen System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307886
Total Float256.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration360.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMay 2, 2015, 8 a.m.
Actual StartNone
Activity IDM3100
Early StartMay 2, 2015, 8 a.m.
Late StartJune 3, 2015, 8 a.m.
Remaining Early FinishJune 15, 2015, 4 p.m.
Remaining Early StartMay 2, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDSuj2n6k9MEavFu57ZG1rsA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 15, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 15, 2015, 4 p.m. 
Late FinishJuly 17, 2015, 4 p.m. 
Remaining Late FinishJuly 17, 2015, 4 p.m. 
Remaining Late StartJune 3, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
360.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29082150.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29082140.0 PR_FS