Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDCPYI6gDyRwqTz4UzY6s6JQ
Unique ID2908186
Activity NamePurchasing - Cables and Cable Trays
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307882
Total Float2136.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration240.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMay 30, 2014, 8 a.m.
Actual StartNone
Activity IDJ1870
Early StartMay 30, 2014, 8 a.m.
Late StartFeb. 21, 2015, 8 a.m.
Remaining Early FinishJune 28, 2014, 4 p.m.
Remaining Early StartMay 30, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDIhDgvv33WEGZiD31mHtumw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 28, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 28, 2014, 4 p.m. 
Late FinishMarch 22, 2015, 4 p.m. 
Remaining Late FinishMarch 22, 2015, 4 p.m. 
Remaining Late StartFeb. 21, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
240.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907286-240.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29081870.0 PR_FS
Back