Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDx/cQbXeFTtaM8rnEujnr7A
Unique ID2908116
Activity NamePO placed - Plant Communication and Visualization System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307873
Total Float1000.0
Activity LocationNone
Est Weight0.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration0.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 29, 2014, 8 a.m.
Actual StartNone
Activity IDJ1790
Early StartJune 29, 2014, 8 a.m.
Late StartNov. 1, 2014, 8 a.m.
Remaining Early FinishJune 29, 2014, 8 a.m.
Remaining Early StartJune 29, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID5exVTlO7VUub03Akvq01dQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 29, 2014, 8 a.m. 
Actual FinishNone 
Activity TypeTT_Mile 
Early FinishJune 29, 2014, 8 a.m. 
Late FinishNov. 1, 2014, 8 a.m. 
Remaining Late FinishNov. 1, 2014, 8 a.m. 
Remaining Late StartNov. 1, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29081150.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29081170.0 PR_FS
Back