Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDCDeR6VTFSxab4leNUvG5+g
Unique ID2908041
Activity NameAt site - Gas Wells System (Skid 4-6)
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307858
Total Float-384.0
Activity LocationNone
Est Weight0.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration0.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJuly 6, 2015, 4 p.m.
Actual StartNone
Activity IDM6130
Early StartJuly 6, 2015, 4 p.m.
Late StartMay 19, 2015, 4 p.m.
Remaining Early FinishJuly 6, 2015, 4 p.m.
Remaining Early StartJuly 6, 2015, 4 p.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDOWZFf0toSV28VRiEXs4CQA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 6, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_FinMile 
Early FinishJuly 6, 2015, 4 p.m. 
Late FinishMay 19, 2015, 4 p.m. 
Remaining Late FinishMay 19, 2015, 4 p.m. 
Remaining Late StartMay 19, 2015, 4 p.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29080400.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29076450.0 PR_FS
Back