Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDeAy7PfnhRF+3tnX3IWCcYQ
Unique ID2908003
Activity NamePurchasing - Amine Piping
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307845
Total Float704.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration560.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 28, 2014, 8 a.m.
Actual StartNone
Activity IDJ4250
Early StartJune 28, 2014, 8 a.m.
Late StartSept. 24, 2014, 8 a.m.
Remaining Early FinishSept. 5, 2014, 4 p.m.
Remaining Early StartJune 28, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID9WZb3JXcNES2nT0qAJSeQg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishSept. 5, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishSept. 5, 2014, 4 p.m. 
Late FinishDec. 2, 2014, 4 p.m. 
Remaining Late FinishDec. 2, 2014, 4 p.m. 
Remaining Late StartSept. 24, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
560.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907330-560.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2908004-440.0 PR_FS