Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID2sYnA8fCQYio5ClnQzuwMw
Unique ID2907856
Activity NamePurchasing - Chemical Injection System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307819
Total Float432.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration336.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMay 17, 2014, 8 a.m.
Actual StartNone
Activity IDF2800
Early StartMay 17, 2014, 8 a.m.
Late StartJuly 10, 2014, 8 a.m.
Remaining Early FinishJune 27, 2014, 4 p.m.
Remaining Early StartMay 17, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDk2y5TffF7UiD1miyX0X73Q
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 27, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 27, 2014, 4 p.m. 
Late FinishAug. 20, 2014, 4 p.m. 
Remaining Late FinishAug. 20, 2014, 4 p.m. 
Remaining Late StartJuly 10, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
336.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907367616.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
29078570.0 PR_FS
Back