Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID6y66x1MTTAmuT/lZkxNRFQ
Unique ID2907818
Activity NameReady for Shipment - Flare interconnecting piping
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307810
Total Float720.0
Activity LocationNone
Est Weight0.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration0.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartNov. 10, 2014, 8 a.m.
Actual StartNone
Activity IDJ2970
Early StartNov. 10, 2014, 8 a.m.
Late StartFeb. 8, 2015, 8 a.m.
Remaining Early FinishNov. 10, 2014, 8 a.m.
Remaining Early StartNov. 10, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDfe721h88pk+eJ2SwqFGNnw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishNov. 10, 2014, 8 a.m. 
Actual FinishNone 
Activity TypeTT_Mile 
Early FinishNov. 10, 2014, 8 a.m. 
Late FinishFeb. 8, 2015, 8 a.m. 
Remaining Late FinishFeb. 8, 2015, 8 a.m. 
Remaining Late StartFeb. 8, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDrtn 
Planned Duration
Original or Planned Duration
0.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29078170.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29078210.0 PR_FS
Back