Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDOq2PBQ3vQUOEwJVCqxkllw
Unique ID2907814
Activity NameEngineering - Flare interconnecting piping
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307498
Total Float720.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration920.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartApril 14, 2014, 8 a.m.
Actual StartNone
Activity IDJ2925
Early StartApril 14, 2014, 8 a.m.
Late StartJuly 13, 2014, 8 a.m.
Remaining Early FinishAug. 6, 2014, 4 p.m.
Remaining Early StartApril 14, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDwf0paM7x6Eer4oMcpH7yQQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishAug. 6, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishAug. 6, 2014, 4 p.m. 
Late FinishNov. 4, 2014, 4 p.m. 
Remaining Late FinishNov. 4, 2014, 4 p.m. 
Remaining Late StartJuly 13, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
920.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
290731956.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907815-560.0 PR_FS