Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDdKjZS0kwS7CkhKYTEbosMw
Unique ID2907712
Activity NamePaiting & Insulation - Industrial Water System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307720
Total Float1232.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration96.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 22, 2015, 8 a.m.
Actual StartNone
Activity IDM4132306
Early StartJune 22, 2015, 8 a.m.
Late StartDec. 19, 2015, 8 a.m.
Remaining Early FinishJuly 5, 2015, 4 p.m.
Remaining Early StartJune 22, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDfqS8DzbiTkCI0alQdvAnoA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 5, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJuly 5, 2015, 4 p.m. 
Late FinishDec. 31, 2015, 4 p.m. 
Remaining Late FinishDec. 31, 2015, 4 p.m. 
Remaining Late StartDec. 19, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float1696.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
96.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29077030.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  