Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDNn15gGcQQBG9jgKiIBZ1yg
Unique ID2907582
Activity NameErection - Small Power System (Ende 1. civil - start letzte civil works-4w Dauer anpassen)
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307635
Total Float1280.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration300.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMay 12, 2015, 8 a.m.
Actual StartNone
Activity IDJ1570
Early StartMay 12, 2015, 8 a.m.
Late StartOct. 19, 2015, 8 a.m.
Remaining Early FinishJune 18, 2015, noon
Remaining Early StartMay 12, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDmCSbaEFGGUmaMGwUG/03Yg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 18, 2015, noon 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 18, 2015, noon 
Late FinishNov. 25, 2015, noon 
Remaining Late FinishNov. 25, 2015, noon 
Remaining Late StartOct. 19, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
300.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29081990.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075830.0 PR_FS
Back