Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDZPA9If4BRRatDsJMba+6aQ
Unique ID2907572
Activity NamePiping - Chlorination System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307623
Total Float696.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration624.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMarch 25, 2015, 8 a.m.
Actual StartNone
Activity IDM4132102
Early StartMarch 25, 2015, 8 a.m.
Late StartJuly 5, 2015, 8 a.m.
Remaining Early FinishJune 23, 2015, 4 p.m.
Remaining Early StartMarch 25, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDOSP8zO8bskylg3KeZdRJSw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 23, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 23, 2015, 4 p.m. 
Late FinishOct. 3, 2015, 4 p.m. 
Remaining Late FinishOct. 3, 2015, 4 p.m. 
Remaining Late StartJuly 5, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
624.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075740.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075730.0 PR_FS
Back