Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDAr3djOWyTiiOQYjO4Q39Zg
Unique ID2907540
Activity NamePre-commissioning - Test Separation and Metering System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307584
Total Float696.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration192.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJuly 28, 2015, 8 a.m.
Actual StartNone
Activity IDM413507
Early StartJuly 28, 2015, 8 a.m.
Late StartNov. 7, 2015, 8 a.m.
Remaining Early FinishAug. 24, 2015, 4 p.m.
Remaining Early StartJuly 28, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDJRyX8BVzOUikoo8+J9ZKBA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishAug. 24, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishAug. 24, 2015, 4 p.m. 
Late FinishDec. 3, 2015, 4 p.m. 
Remaining Late FinishDec. 3, 2015, 4 p.m. 
Remaining Late StartNov. 7, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float464.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
192.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075330.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29071360.0 PR_FS
29084120.0 PR_FS