Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDDHO5CkQZTFKdNukJDKzR7g
Unique ID2907534
Activity NamePiping - Test Separation and Metering System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307581
Total Float960.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration704.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJan. 12, 2015, 8 a.m.
Actual StartNone
Activity IDM413502
Early StartJan. 12, 2015, 8 a.m.
Late StartJune 1, 2015, 8 a.m.
Remaining Early FinishApril 23, 2015, 4 p.m.
Remaining Early StartJan. 12, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDKafKOV66k0yYNBXbTViKBA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishApril 23, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishApril 23, 2015, 4 p.m. 
Late FinishSept. 10, 2015, 4 p.m. 
Remaining Late FinishSept. 10, 2015, 4 p.m. 
Remaining Late StartJune 1, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
704.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075360.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075350.0 PR_FS
Back