Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID8kmm1qiPRfaxaSMuewdAXQ
Unique ID2907499
Activity NamePiping - Instrument & Plant Air System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307564
Total Float216.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration624.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 16, 2015, 8 a.m.
Actual StartNone
Activity IDM4132802
Early StartJune 16, 2015, 8 a.m.
Late StartJuly 18, 2015, 8 a.m.
Remaining Early FinishSept. 14, 2015, 4 p.m.
Remaining Early StartJune 16, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDE4qxv0rikk+leLRFtLLFfw
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishSept. 14, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishSept. 14, 2015, 4 p.m. 
Late FinishOct. 15, 2015, 4 p.m. 
Remaining Late FinishOct. 15, 2015, 4 p.m. 
Remaining Late StartJuly 18, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
624.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29075010.0 PR_FS
29080220.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29075000.0 PR_FS