Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDMmH4ADHtQWO2NdaJ0f3tSQ
Unique ID2907458
Activity NameAccess Roads & Parkings
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307550
Total Float768.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration216.0
2
Primary ConstraintCS_MSOA
Secondary ConstraintNone
Primary Constraint DateMay 1, 2014, 8 a.m.
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartMay 1, 2014, 8 a.m.
Actual StartNone
Activity IDM411101
Early StartMay 1, 2014, 8 a.m.
Late StartAug. 21, 2014, 8 a.m.
Remaining Early FinishJune 1, 2014, 4 p.m.
Remaining Early StartMay 1, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDBeH6ydqk40OEFyi2jH78Ag
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJune 1, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJune 1, 2014, 4 p.m. 
Late FinishSept. 21, 2014, 4 p.m. 
Remaining Late FinishSept. 21, 2014, 4 p.m. 
Remaining Late StartAug. 21, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
216.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  

Successors

6
  Task Id    Lag (day)     Succ Type  
29074650.0 PR_FS
29071410.0 PR_SS
Back