Task Detail

1
General Informations
Project22726
Global Unique IDxYWW1P/NQuC9nzISa4GYuA
Unique ID2907457
Activity NamePersonnel Camp Accomodation
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307550
Total Float3368.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration480.0
2
Primary ConstraintCS_MSOA
Secondary ConstraintNone
Primary Constraint DateJune 1, 2014, 8 a.m.
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartJune 2, 2014, 8 a.m.
Actual StartNone
Activity IDM411111
Early StartJune 2, 2014, 8 a.m.
Late StartOct. 6, 2015, 8 a.m.
Remaining Early FinishAug. 10, 2014, 4 p.m.
Remaining Early StartJune 2, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDLGDlSvZDCEWhscWMVrOidg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishAug. 10, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishAug. 10, 2014, 4 p.m. 
Late FinishDec. 14, 2015, 4 p.m. 
Remaining Late FinishDec. 14, 2015, 4 p.m. 
Remaining Late StartOct. 6, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
480.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29074650.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907463120.0 PR_SS
2907459120.0 PR_SS
2907469120.0 PR_SS