Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID9eRDdrJZQ82rnxsI9xe0sg
Unique ID2907421
Activity NameMechanical / Equipment - Produced Water System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307522
Total Float-128.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration384.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartAug. 5, 2015, 8 a.m.
Actual StartNone
Activity IDM4131803
Early StartAug. 5, 2015, 8 a.m.
Late StartJuly 18, 2015, 8 a.m.
Remaining Early FinishSept. 29, 2015, 4 p.m.
Remaining Early StartAug. 5, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDgND2qWP1mUGAC2qzShGiTg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishSept. 29, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishSept. 29, 2015, 4 p.m. 
Late FinishSept. 10, 2015, 4 p.m. 
Remaining Late FinishSept. 10, 2015, 4 p.m. 
Remaining Late StartJuly 18, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
384.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29078270.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907417256.0 PR_SS
29074120.0 PR_FS
29074150.0 PR_FS