Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDVYTr+pc/SySspIfxHAWtEw
Unique ID2907414
Activity NamePiping - Produced Water and Evaporation Pond System
Added DateNov. 25, 2013, 2:42 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307517
Total Float296.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration624.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:42 p.m.
Planned StartApril 30, 2015, 8 a.m.
Actual StartNone
Activity IDM4131802
Early StartApril 30, 2015, 8 a.m.
Late StartJune 13, 2015, 8 a.m.
Remaining Early FinishJuly 29, 2015, 4 p.m.
Remaining Early StartApril 30, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDm4kzdQ4A5Um/QT7C1AGwhQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 29, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJuly 29, 2015, 4 p.m. 
Late FinishSept. 10, 2015, 4 p.m. 
Remaining Late FinishSept. 10, 2015, 4 p.m. 
Remaining Late StartJune 13, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float424.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
624.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29074160.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
29074150.0 PR_FS