Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDtxJ2CeBOTuihRTdZ4TYjMw
Unique ID2907380
Activity NameFinal Documentation - Condensate Storage and Metering System
Added DateNov. 25, 2013, 2:41 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307502
Total Float376.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar22303
Percent Complete TypeCP_Phys
Auto Compute ActualsN
Remaining Duration720.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:41 p.m.
Planned StartJuly 26, 2015, 8 a.m.
Actual StartNone
Activity IDM3890
Early StartJuly 26, 2015, 8 a.m.
Late StartSept. 19, 2015, 8 a.m.
Remaining Early FinishNov. 7, 2015, 4 p.m.
Remaining Early StartJuly 26, 2015, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDfF6SIOQ6CkC7bqXCBxu4uA
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishNov. 7, 2015, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishNov. 7, 2015, 4 p.m. 
Late FinishDec. 31, 2015, 4 p.m. 
Remaining Late FinishDec. 31, 2015, 4 p.m. 
Remaining Late StartSept. 19, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float792.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
720.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29083970.0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
29071380.0 PR_FS