Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique ID0xzBwgMVToKFOJEchEVNPw
Unique ID2907329
Activity NameEngineering - Methanol injection interconnecting piping
Added DateNov. 25, 2013, 2:41 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307498
Total Float1000.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration920.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:41 p.m.
Planned StartMarch 31, 2014, 8 a.m.
Actual StartNone
Activity IDJ4185
Early StartMarch 31, 2014, 8 a.m.
Late StartAug. 3, 2014, 8 a.m.
Remaining Early FinishJuly 23, 2014, 4 p.m.
Remaining Early StartMarch 31, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDSziMBXQE1kWHKE605fhuMg
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 23, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJuly 23, 2014, 4 p.m. 
Late FinishNov. 25, 2014, 4 p.m. 
Remaining Late FinishNov. 25, 2014, 4 p.m. 
Remaining Late StartAug. 3, 2014, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
920.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
29073680.0 PR_FS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907983-560.0 PR_FS
Back