Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDooa6vz2gRHC0bgdzeiuHXg
Unique ID2907325
Activity NameEngineering - Condensate Piping
Added DateNov. 25, 2013, 2:41 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307498
Total Float4160.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar19658
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration920.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:41 p.m.
Planned StartApril 7, 2014, 8 a.m.
Actual StartNone
Activity IDJ4130
Early StartApril 7, 2014, 8 a.m.
Late StartSept. 9, 2015, 8 a.m.
Remaining Early FinishJuly 30, 2014, 4 p.m.
Remaining Early StartApril 7, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDlnc1qSeXYUiQ3OJ6lX5tlQ
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishJuly 30, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishJuly 30, 2014, 4 p.m. 
Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late FinishJan. 1, 2016, 4 p.m. 
Remaining Late StartSept. 9, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float4696.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
920.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
290722656.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  