Project Cloud System

Job N° : 1260014

Task Detail

1
General Informations
Project22726
Global Unique IDyj7YvvQuQMim5ejS5L5Rjg
Unique ID2907203
Activity NameEngineering - Civil
Added DateNov. 25, 2013, 2:41 p.m.
Added Byadmin
Activity StatusTK_NotStart
WBS307483
Total Float2736.0
Activity LocationNone
Est Weight1.0
Phys Complete Pct0.0
Calendar1183
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1440.0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0.0
Actual This Period Nonlabor Units0.0
Actual This Period Labor Units0.0
Actual Labor Units0.0
Planned Labor Units
Budgeted or Planned Labor Units
0.0
Remaining Nonlabor Units0.0
Remaining Labor Units0.0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0.0
3
Last Modified DateNov. 25, 2013, 2:41 p.m.
Planned StartMarch 31, 2014, 8 a.m.
Actual StartNone
Activity IDF5060
Early StartMarch 31, 2014, 8 a.m.
Late StartMarch 8, 2015, 8 a.m.
Remaining Early FinishSept. 26, 2014, 4 p.m.
Remaining Early StartMarch 31, 2014, 8 a.m.
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDNone
Lock RemainingN
4
Last Modified Byadmin 
Planned FinishSept. 26, 2014, 4 p.m. 
Actual FinishNone 
Activity TypeTT_Task 
Early FinishSept. 26, 2014, 4 p.m. 
Late FinishSept. 3, 2015, 4 p.m. 
Remaining Late FinishSept. 3, 2015, 4 p.m. 
Remaining Late StartMarch 8, 2015, 8 a.m. 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0.0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1440.0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
2907367240.0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
2907204240.0 PR_SF
2907265480.0 PR_SS