Cost Estimation & Control

Variance

Variance: A Key Tool for Cost Estimation and Control

In the realm of cost estimation and control, variance serves as a critical indicator for tracking deviations from planned budgets and identifying potential areas for improvement. This article will delve into the concept of variance, exploring its different types and significance in effective project management.

What is Variance?

In its simplest form, variance refers to the difference between a planned or expected measure and the actual measure achieved. In cost estimation and control, this typically involves comparing the budgeted cost of a project or task with the actual cost incurred.

Types of Variance:

  1. Cost Variance: This measures the difference between the budgeted cost and the actual cost incurred for a specific project or task. A positive variance indicates that the actual cost is lower than the budgeted cost, while a negative variance signifies that the actual cost is higher than the budgeted cost.

  2. Schedule Variance: This compares the planned schedule for completing a project or task with the actual completion time. A positive schedule variance means the project is ahead of schedule, while a negative variance implies it is behind schedule.

  3. Performance Variance: This focuses on the difference between the planned performance and the actual performance achieved, often measured in terms of units produced, defects found, or customer satisfaction levels. A positive performance variance indicates exceeding expectations, while a negative variance signifies falling short of the planned goals.

Significance of Variance in Cost Estimation and Control:

  • Early Warning System: Variances act as early warning signals, highlighting potential problems or opportunities within a project. Analyzing these discrepancies can reveal underlying issues such as poor planning, inefficient resource allocation, or unforeseen challenges.

  • Improved Accuracy: Regular monitoring and analysis of variances help refine future cost estimations by learning from past experiences. Identifying recurring variances can lead to adjustments in budgeting practices, resource allocation, or project planning.

  • Enhanced Control: By actively managing and investigating variances, project managers can identify areas for improvement, take corrective action, and ensure projects remain within budget and schedule constraints.

Addressing Variance:

  • Investigate the Cause: Understanding the root cause of the variance is crucial for effective action. Was it due to unforeseen circumstances, inaccurate estimations, or inefficient processes?
  • Implement Corrective Measures: Depending on the nature of the variance, corrective actions may include adjusting the budget, reallocating resources, or revising project plans.
  • Monitor and Adapt: Continuous monitoring and analysis of variances are vital to ensure corrective measures are effective and to adapt to changing project circumstances.

Conclusion:

Variance is a powerful tool in cost estimation and control, providing insights into project performance and facilitating proactive management. By understanding the different types of variances, their significance, and effective methods for addressing them, organizations can improve project outcomes, minimize financial risks, and ultimately achieve project success.


Test Your Knowledge

Quiz: Variance in Cost Estimation and Control

Instructions: Choose the best answer for each question.

1. What is the definition of variance in cost estimation and control?

a) The difference between actual performance and planned performance. b) The difference between the budgeted cost and the actual cost incurred. c) The difference between the planned schedule and the actual completion time. d) The difference between the projected profit and the actual profit earned.

Answer

b) The difference between the budgeted cost and the actual cost incurred.

2. Which type of variance indicates that a project is ahead of schedule?

a) Negative schedule variance b) Positive schedule variance c) Negative cost variance d) Positive cost variance

Answer

b) Positive schedule variance

3. Which of the following is NOT a benefit of analyzing variances in project management?

a) Early warning system for potential problems. b) Improved accuracy in future cost estimations. c) Enhanced control over project resources. d) Increased project complexity and time consumption.

Answer

d) Increased project complexity and time consumption.

4. A project manager identifies a negative cost variance. What should they do first?

a) Immediately revise the project budget. b) Ignore the variance as it is a common occurrence. c) Investigate the cause of the variance. d) Increase the project scope to offset the cost overrun.

Answer

c) Investigate the cause of the variance.

5. Which of the following is NOT a step in addressing variance in project management?

a) Investigating the cause of the variance. b) Implementing corrective measures. c) Increasing the project budget. d) Monitoring and adapting to changes.

Answer

c) Increasing the project budget.

Exercise: Project Variance Analysis

Scenario:

You are managing a website development project with a budget of $10,000. The initial project plan estimated a completion time of 8 weeks. Here are the actual figures after 6 weeks:

  • Actual Cost: $8,500
  • Project Completion: 50%

Task:

  1. Calculate the Cost Variance (CV) and Schedule Variance (SV).
  2. Interpret the results and explain their significance for the project.
  3. Suggest two possible corrective actions based on your analysis.

Exercice Correction

**1. Calculating Variances:** * **Cost Variance (CV) = Budgeted Cost - Actual Cost** * CV = $10,000 - $8,500 = $1,500 (Positive) * **Schedule Variance (SV) = Planned Completion - Actual Completion** * Since 6 weeks have passed, planned completion should be 75% (6 weeks/8 weeks = 0.75). * SV = 75% - 50% = 25% (Positive) **2. Interpretation:** * **Positive Cost Variance:** The project is under budget, which is a favorable outcome. * **Positive Schedule Variance:** The project is ahead of schedule, another positive indicator. This suggests that the project is currently progressing well in terms of cost and time. **3. Corrective Actions (even though not needed in this case):** * **Maintain current performance:** Since both variances are positive, the best course of action might be to maintain the current efficient practices and resource allocation. * **Proactive Resource Planning:** If the team anticipates future challenges, they can proactively plan for resource reallocation or budget adjustments to maintain the positive variances.


Books

  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner: A comprehensive guide to project management, including detailed sections on cost estimation, budgeting, and variance analysis.
  • Cost Management for Project Managers by William T. Moore: Focuses specifically on cost management practices, including variance analysis techniques for controlling project expenses.
  • Cost Estimating by Norman R. Augustine: An insightful book on the principles and methodologies of cost estimation, with practical examples and case studies.
  • The PMBOK Guide (Project Management Institute): A standard guide for project management professionals, encompassing best practices and methodologies, including cost management and variance analysis.

Articles

  • "Variance Analysis: A Powerful Tool for Cost Control" by Project Management Institute: A practical guide to variance analysis, outlining steps for identifying, analyzing, and addressing cost variances.
  • "Understanding and Managing Cost Variance in Projects" by Construction Management and Economics: A detailed analysis of cost variance in construction projects, exploring causes and mitigation strategies.
  • "Cost Variance Analysis in Project Management: A Critical Review" by International Journal of Project Management: A research-based article examining the importance and limitations of cost variance analysis in project management.

Online Resources

  • Project Management Institute (PMI): Offers a wealth of resources, including articles, webinars, and certifications related to project management, including cost management and variance analysis.
  • *MindTools: * Provides practical guidance on variance analysis, including templates and examples for applying the concepts in real-world scenarios.
  • Investopedia: Offers definitions and explanations of financial concepts, including variance analysis, in an easy-to-understand format.

Search Tips

  • "Variance Analysis in Project Management"
  • "Cost Variance Calculation Examples"
  • "Types of Project Variance"
  • "Managing Schedule Variance in Projects"
  • "Project Management Software with Variance Analysis"

Techniques

Similar Terms
Cost Estimation & ControlProject Planning & Scheduling