Project Planning & Scheduling

Rolling Wave

Rolling Wave Planning: Keeping Your Project Agile and Focused

In the dynamic world of project management, uncertainty is a constant companion. Deadlines shift, requirements change, and unforeseen challenges emerge. To navigate this landscape effectively, project managers often employ a powerful tool: Rolling Wave Planning.

Understanding the Concept

Rolling Wave Planning is a scheduling methodology that combines the need for detailed planning with the reality of evolving project information. It emphasizes a short-term, iterative approach. Instead of meticulously outlining every detail of the project upfront, Rolling Wave Planning focuses on planning the immediate future. As the project progresses, the plan is "rolled forward" – new activities are added, existing ones are refined, and the planning horizon extends.

Key Characteristics:

  • Incremental Planning: Only the activities within a defined timeframe (typically the next few weeks or months) are planned in detail.
  • Focused Detail: The focus is on providing detailed schedules and resource allocation for the upcoming timeframe, ensuring a clear understanding of immediate priorities.
  • Flexibility and Adaptability: The rolling wave approach allows for incorporating changes and updates as the project unfolds, ensuring the plan remains aligned with the latest information.
  • Continuous Refinement: Regularly reviewing and updating the plan based on feedback, performance data, and changing circumstances keeps the project on track.

Benefits of Rolling Wave Planning:

  • Reduced Risk: By focusing on the immediate future, Rolling Wave Planning allows for more accurate risk assessment and mitigation strategies.
  • Enhanced Agility: The ability to adapt to changing circumstances ensures that the project remains relevant and responsive.
  • Improved Resource Allocation: By planning in smaller chunks, resources can be allocated more effectively and efficiently.
  • Increased Stakeholder Engagement: Regular updates and discussions regarding the evolving plan promote transparency and facilitate stakeholder involvement.

Example in Action:

Imagine a software development project. The initial plan might include high-level milestones like design, coding, testing, and deployment. Using a rolling wave approach, the team will first plan and schedule the detailed activities for the design phase, focusing on deliverables, timelines, and resource allocation. Once the design phase is completed, they will then move on to planning and scheduling the coding phase, taking into account the outcomes of the design phase and any new requirements that have emerged.

Rolling Wave Planning: A Powerful Tool for Project Success

Rolling Wave Planning is a dynamic and effective approach to project management. By combining a focus on the immediate future with the flexibility to adapt to changing circumstances, it empowers project teams to navigate complexity, embrace change, and achieve successful outcomes.


Test Your Knowledge

Rolling Wave Planning Quiz

Instructions: Choose the best answer for each question.

1. What is the primary characteristic of Rolling Wave Planning? a) Detailed planning of the entire project from the start. b) Short-term, iterative planning with a focus on the immediate future. c) Static planning with no room for adjustments. d) Planning based on fixed deadlines and requirements.

Answer

b) Short-term, iterative planning with a focus on the immediate future.

2. Which of the following is NOT a benefit of Rolling Wave Planning? a) Reduced risk. b) Enhanced agility. c) Improved resource allocation. d) Increased project complexity.

Answer

d) Increased project complexity.

3. How does Rolling Wave Planning help to improve resource allocation? a) By allocating resources for the entire project at the beginning. b) By planning in smaller chunks, allowing for more efficient allocation. c) By avoiding the need for resource allocation. d) By using a fixed resource allocation plan throughout the project.

Answer

b) By planning in smaller chunks, allowing for more efficient allocation.

4. In which scenario would Rolling Wave Planning be most beneficial? a) A project with clear, unchanging requirements and a predictable timeline. b) A project with complex, evolving requirements and frequent changes. c) A project with a fixed budget and strict deadline. d) A project with a highly specialized team and established processes.

Answer

b) A project with complex, evolving requirements and frequent changes.

5. Which of the following is NOT a key characteristic of Rolling Wave Planning? a) Incremental planning. b) Focused detail. c) Flexibility and adaptability. d) Fixed project scope.

Answer

d) Fixed project scope.

Rolling Wave Planning Exercise

Scenario: You are managing a website redesign project. The initial project plan includes a high-level outline of the phases: user research, design, development, testing, and launch.

Task:

  1. Apply Rolling Wave Planning to the project: Choose one phase (e.g., user research) and outline the detailed activities, deadlines, and resource allocation for that phase.
  2. Explain how you would adjust the plan if a new requirement is introduced after the user research phase is completed.

Exercice Correction

Here's a possible approach to the exercise:

1. Detailed Plan for the User Research Phase:

  • Activities:
    • Conduct user interviews (3 days)
    • Conduct usability testing (2 days)
    • Analyze user data (2 days)
    • Prepare a user research report (1 day)
  • Deadlines:
    • Start date: [insert start date]
    • End date: [insert end date]
  • Resources:
    • 1 UX Researcher
    • 2 Research assistants
    • User testing participants (20 people)

2. Adjusting the Plan for a New Requirement:

  • Identify the impact: Assess how the new requirement affects the existing plan. Does it require additional user research or changes to the design phase?
  • Revise the plan: Update the plan with the new requirement, including any necessary adjustments to activities, deadlines, or resources.
  • Communicate the changes: Inform stakeholders about the revised plan and any potential impacts on the project timeline or budget.

Key Points to Remember:

  • Flexibility: Rolling Wave Planning allows for continuous adaptation to new information.
  • Prioritization: Focus on the most critical activities for the current phase.
  • Communication: Regular updates and discussions are crucial to keep everyone informed.


Books

  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner: This comprehensive book covers various project management methodologies, including Rolling Wave Planning, in detail.
  • Agile Project Management with Scrum by Ken Schwaber and Mike Beedle: Although focusing on Scrum, this book highlights the importance of iterative planning and adaptation, which are core principles of Rolling Wave Planning.
  • The Phoenix Project: A Novel About IT, DevOps, and Helping Your Business Win by Gene Kim, Kevin Behr, and George Spafford: While fictional, this novel provides an engaging and practical example of applying rolling wave planning principles in a real-world IT context.

Articles

  • Rolling Wave Planning: A Guide for Project Managers by ProjectManager.com: Provides a comprehensive overview of Rolling Wave Planning, outlining its benefits, steps, and considerations.
  • Rolling Wave Planning: How To Make It Work for You by Smartsheet: Offers a practical approach to implementing Rolling Wave Planning, including best practices and templates.
  • The Power of Rolling Wave Planning by PM World Today: Explores the advantages of using Rolling Wave Planning for various projects and stakeholders.

Online Resources

  • Rolling Wave Planning - Wikipedia: Provides a basic understanding of Rolling Wave Planning, its history, and common applications.
  • Rolling Wave Planning - PMI.org: Offers resources and articles on Rolling Wave Planning from the Project Management Institute, a leading professional organization in the field.
  • Rolling Wave Planning: Definition, Steps and Benefits by PM Hut: Offers a structured explanation of Rolling Wave Planning, outlining the key steps involved and the benefits it provides.

Search Tips

  • "Rolling Wave Planning" + [industry/context]: For example, "Rolling Wave Planning Software Development" or "Rolling Wave Planning Construction Projects" to find relevant resources.
  • "Rolling Wave Planning" + [software/tool]: Use specific software names to explore how they support Rolling Wave Planning.
  • "Rolling Wave Planning" + [problem/challenge]: For example, "Rolling Wave Planning Uncertainty Management" or "Rolling Wave Planning Change Management" to find resources focused on specific issues.

Techniques

Similar Terms
Drilling & Well CompletionGeology & ExplorationProject Planning & SchedulingProduction FacilitiesReservoir Engineering
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back