Glossary of Technical Terms Used in Project Planning & Scheduling: Percentage Completion

Percentage Completion

Percentage Completion: A Flawed but Common Metric for Project Progress

In the world of project management, it's tempting to rely on percentage completion as a quick and easy way to track progress. After all, it seems straightforward: what percentage of the work is done? However, this deceptively simple metric often falls short, leading to inaccurate assessments and potential project delays.

What is Percentage Completion?

Percentage completion measures the progress of a task or project as a proportion of its total duration. It's often expressed as a percentage, with 100% representing completion. For example, if a task is scheduled to take 10 days and 5 days have passed, the percentage completion is 50%.

The Flaw of Subjectivity

The primary problem with percentage completion lies in its inherent subjectivity. There's no single, objective way to determine how much progress has been made. Different individuals may have vastly different interpretations of what constitutes 50% complete. This can lead to discrepancies between project managers, team members, and stakeholders, creating confusion and hindering accurate progress monitoring.

Beyond the Limitations of Percentage Completion

While easy to understand, percentage completion lacks the sophistication to accurately reflect the true progress of a project. It fails to account for:

  • Task complexity: A seemingly simple task might take longer than a more complex one, even if they have the same duration. Percentage completion doesn't differentiate between these scenarios.
  • Resource availability: Delays due to resource constraints aren't reflected in simple percentage calculations.
  • Work quality: Percentage completion doesn't consider the quality of work performed. A task might be technically complete but require rework, leading to delays and wasted resources.

A Better Alternative: Earned Value Analysis

For a more robust and accurate assessment of project progress, Earned Value Analysis (EVA) is recommended. EVA measures work completed against planned work, considering both schedule and budget. It utilizes key metrics like:

  • Planned Value (PV): The budgeted cost of work scheduled to be completed by a specific point in time.
  • Earned Value (EV): The actual value of work completed.
  • Actual Cost (AC): The actual cost incurred to complete the work.

By comparing these metrics, EVA provides valuable insights into project performance, highlighting potential risks and opportunities for improvement.

Conclusion

Percentage completion might appear user-friendly, but its inherent subjectivity renders it unreliable for accurate project progress assessment. By embracing more sophisticated methods like Earned Value Analysis, project managers can gain a clearer understanding of actual progress, manage risks effectively, and ensure project success.


Test Your Knowledge

Quiz: Percentage Completion: A Flawed Metric

Instructions: Choose the best answer for each question.

1. What is the primary problem with using percentage completion as a project progress metric? a) It is too difficult to calculate. b) It does not consider task dependencies. c) It is subjective and can be interpreted differently by individuals. d) It does not account for changes in project scope.

Answer

c) It is subjective and can be interpreted differently by individuals.

2. Which of the following factors does percentage completion NOT account for? a) Task complexity b) Resource availability c) Work quality d) Project budget

Answer

d) Project budget

3. What is a better alternative to percentage completion for assessing project progress? a) Gantt charts b) Earned Value Analysis (EVA) c) Critical Path Method (CPM) d) Agile methodologies

Answer

b) Earned Value Analysis (EVA)

4. What does "Earned Value" represent in Earned Value Analysis? a) The budgeted cost of work scheduled to be completed. b) The actual cost incurred to complete the work. c) The actual value of work completed. d) The difference between the planned value and actual cost.

Answer

c) The actual value of work completed.

5. What is a potential drawback of using percentage completion to track project progress? a) It can lead to inaccurate progress assessments. b) It can create confusion among team members and stakeholders. c) It can hinder effective risk management. d) All of the above.

Answer

d) All of the above.

Exercise: Evaluating Project Progress

Scenario: You are managing a web development project with the following tasks:

  • Task 1: Design website layout (Estimated time: 5 days)
  • Task 2: Develop front-end code (Estimated time: 10 days)
  • Task 3: Develop back-end code (Estimated time: 8 days)
  • Task 4: Implement database (Estimated time: 3 days)
  • Task 5: Testing and deployment (Estimated time: 4 days)

Current Progress:

  • Task 1 is 100% complete.
  • Task 2 is 50% complete.
  • Task 3 is 25% complete.
  • Task 4 has not started.
  • Task 5 has not started.

Instructions:

  1. Calculate the project completion percentage using the simple percentage completion method.
  2. Explain why this calculation is flawed and what information it does not consider.
  3. Suggest an alternative approach to assessing project progress, using the concept of Earned Value Analysis.

Exercice Correction

1. **Simple Percentage Completion:** Total estimated time: 5 + 10 + 8 + 3 + 4 = 30 days Completed time: 5 (Task 1) + 5 (half of Task 2) = 10 days Percentage completion: (10 / 30) * 100 = **33.33%** 2. **Flawed Calculation:** This calculation is flawed because it only considers the time spent on tasks, not the actual work completed. It doesn't account for the fact that Task 2, which is 50% complete, may be more complex than Task 3, which is only 25% complete. Additionally, it doesn't consider the fact that Task 4 and Task 5 haven't started, even though they are scheduled to take a significant amount of time. 3. **Earned Value Analysis (EVA):** To use EVA, we need to define the following: * **Planned Value (PV):** The budgeted cost of work scheduled to be completed by a specific point in time. * **Earned Value (EV):** The actual value of work completed. * **Actual Cost (AC):** The actual cost incurred to complete the work. For example, let's assume a simple scenario where each task has a fixed budget: * **Task 1:** PV = 100, EV = 100, AC = 100 (assuming it was completed on budget) * **Task 2:** PV = 200, EV = 100, AC = 150 (assuming half the work is done but the cost is higher than planned) * **Task 3:** PV = 160, EV = 40, AC = 50 (assuming only 25% is done and the cost is higher than planned) * **Task 4:** PV = 60, EV = 0, AC = 0 (not started) * **Task 5:** PV = 80, EV = 0, AC = 0 (not started) By calculating PV, EV, and AC for each task, we can get a better understanding of the project's progress and potential risks. For example, we see that Task 2 and Task 3 are over budget, which might require adjustments to the project plan.


Books

  • Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition. PMI Publishing.
    • This foundational text for project management covers percentage completion as part of its discussion on project scheduling and progress tracking. It also outlines alternatives like Earned Value Analysis.
  • Kerzner, H. (2020). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley.
    • This comprehensive guide delves into various project management methodologies, including a detailed analysis of percentage completion's limitations and the advantages of more robust methods.
  • Cleland, D. I., & Gareis, R. (2016). Project Management: Strategic Design and Implementation. McGraw-Hill Education.
    • This text provides a detailed examination of project planning and control, emphasizing the importance of accurate progress measurement and the drawbacks of simplistic approaches like percentage completion.

Articles

  • "The Pitfalls of Percentage Completion" by David H. Olson, Project Management Journal, 2008.
    • This article explores the inherent problems of relying on percentage completion for project progress measurement, highlighting its subjectivity and lack of accuracy.
  • "Why Percentage Completion is Not Enough" by Michael DeMarco, Project Management Institute, 2017.
    • This article outlines the limitations of percentage completion and presents compelling arguments for using more robust methods like Earned Value Management for accurate progress evaluation.
  • "The Art and Science of Project Progress Measurement" by Jeff Sutherland, Scrum.org, 2019.
    • This article delves into various methods for measuring project progress, emphasizing the importance of considering task complexity, resource availability, and work quality beyond simple percentage calculations.

Online Resources

  • Project Management Institute (PMI): https://www.pmi.org/
    • PMI's website offers a wealth of resources on project management, including articles, research papers, and training materials related to project progress measurement and Earned Value Analysis.
  • Earned Value Management Association (EVMA): https://www.evma.org/
    • EVMA is a professional organization dedicated to promoting Earned Value Management (EVM) principles and practices. Their website offers resources, training materials, and certification opportunities for EVM practitioners.
  • ProjectManagement.com: https://www.projectmanagement.com/
    • This website provides articles, webinars, and other resources covering various aspects of project management, including in-depth discussions on progress measurement and Earned Value Analysis.

Search Tips

  • Use specific keywords: Instead of just "Percentage Completion," try "Percentage Completion Limitations," "Percentage Completion vs. Earned Value," or "Project Progress Measurement Methods."
  • Combine with project management terms: Search "Percentage Completion Project Management," "Percentage Completion Project Progress," or "Percentage Completion Earned Value."
  • Include academic sources: Add phrases like "academic research," "peer-reviewed articles," or "journal publications" to your search to find more scholarly content.
  • Explore Google Scholar: Utilize Google Scholar to specifically target academic articles and research papers related to percentage completion and project progress measurement.
Similar Terms
Drilling & Well Completion
Budgeting & Financial Control
Project Planning & Scheduling
Oil & Gas Processing
Oil & Gas Specific Terms
Cost Estimation & Control
Instrumentation & Control Engineering
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back