Glossary of Technical Terms Used in Oil & Gas Processing: PDM Finish to Start Relationship

PDM Finish to Start Relationship

PDM Finish to Start: Optimizing Project Schedules in Oil & Gas

In the fast-paced and demanding world of oil & gas projects, optimizing timelines is crucial for profitability and efficiency. Project management tools, like Primavera P6 (PDM), offer a powerful arsenal of dependencies to ensure project activities are sequenced effectively. One such dependency type, Finish to Start (FS), plays a pivotal role in streamlining project schedules.

Understanding Finish to Start (FS) in PDM

A Finish to Start (FS) relationship in PDM indicates that a successor activity can only commence after the predecessor activity is completed. This dependency ensures a logical flow of work and prevents delays due to overlapping or premature initiation of tasks.

Key Applications of FS in Oil & Gas Projects

In the oil & gas industry, FS relationships find diverse applications across various project phases, including:

  • Construction and Installation: Installing a pipeline segment (successor activity) can only begin once the previous segment (predecessor activity) is fully welded and inspected.
  • Drilling and Completion: Commencing drilling operations (successor) depends on the completion of wellhead preparation (predecessor).
  • Production and Processing: The processing of crude oil (successor) can only begin after the completion of extraction and transportation (predecessor).
  • Maintenance and Repair: Repairing a leaking valve (successor) requires the completion of shutting down the affected pipeline (predecessor).

Benefits of Utilizing FS Relationships

  • Improved Scheduling Accuracy: FS dependencies establish a clear sequence of tasks, leading to more accurate project timelines.
  • Reduced Delays: Preventing overlap between activities minimizes delays and ensures efficient resource allocation.
  • Enhanced Project Visibility: Clear dependencies allow stakeholders to track progress and identify potential bottlenecks.
  • Enhanced Risk Management: FS relationships enable proactive risk mitigation by highlighting potential delays and allowing for contingency planning.

Implementing FS Relationships in PDM

PDM software provides intuitive interfaces for defining FS relationships:

  1. Define Activities: Enter all project activities with their expected durations.
  2. Establish Dependencies: Identify activities that depend on the completion of other activities and define them as FS relationships.
  3. Monitor Progress: Regularly monitor the progress of activities and adjust the schedule accordingly.

Conclusion

Finish to Start relationships in PDM are crucial for optimizing project schedules in the oil & gas industry. By ensuring logical dependencies, FS relationships lead to improved accuracy, reduced delays, enhanced visibility, and better risk management, ultimately contributing to successful project delivery.


Test Your Knowledge

Quiz: PDM Finish to Start

Instructions: Choose the best answer for each question.

1. What does a Finish to Start (FS) relationship in PDM indicate?

a) The successor activity can start before the predecessor activity is completed.

Answer

Incorrect. This describes a Start to Start relationship.

b) The successor activity must start at the same time as the predecessor activity.
Answer

Incorrect. This describes a Start to Finish relationship.

c) The successor activity can only commence after the predecessor activity is completed.
Answer

Correct! This is the definition of a Finish to Start relationship.

d) The successor activity must finish before the predecessor activity can start.
Answer

Incorrect. This describes a Finish to Finish relationship.

2. Which of the following is NOT a benefit of utilizing FS relationships in oil & gas projects?

a) Improved scheduling accuracy

Answer

Incorrect. This is a benefit of FS relationships.

b) Reduced delays
Answer

Incorrect. This is a benefit of FS relationships.

c) Increased project costs
Answer

Correct! FS relationships help optimize schedules, potentially leading to cost reduction, not increase.

d) Enhanced project visibility
Answer

Incorrect. This is a benefit of FS relationships.

3. In which of the following scenarios would an FS relationship be most appropriate?

a) Installing a new pump in a pipeline while the pipeline is still operational.

Answer

Incorrect. This scenario might require a Start to Finish relationship to ensure the pipeline remains operational during installation.

b) Ordering new drilling equipment before the existing equipment is decommissioned.
Answer

Incorrect. This scenario might require a Finish to Start relationship, but it's not the most appropriate given the lead time involved in ordering equipment.

c) Starting the drilling process after the wellhead preparation is complete.
Answer

Correct! This scenario clearly requires the predecessor activity (wellhead preparation) to be completed before the successor activity (drilling) can begin.

d) Performing maintenance on a pump during a scheduled shutdown.
Answer

Incorrect. This scenario might require a Start to Finish relationship to ensure the maintenance is completed before the pipeline resumes operation.

4. What is the first step in implementing FS relationships in PDM?

a) Establishing dependencies between activities.

Answer

Incorrect. This is a later step in the process.

b) Monitoring progress and adjusting the schedule.
Answer

Incorrect. This is a final step in the process.

c) Defining all project activities with their expected durations.
Answer

Correct! You need to define the activities before you can establish dependencies between them.

d) Selecting the appropriate PDM software.
Answer

Incorrect. This is a preliminary step, but not the first one in implementing FS relationships.

5. What is the primary benefit of using FS relationships in PDM for risk management?

a) Identifying potential bottlenecks and allowing for contingency planning.

Answer

Correct! FS relationships highlight potential delays, allowing for proactive risk mitigation.

b) Eliminating all risks associated with project scheduling.
Answer

Incorrect. While FS relationships help manage risks, they cannot eliminate all risks entirely.

c) Providing detailed financial forecasts for risk assessment.
Answer

Incorrect. While financial forecasts are important, they are not the primary benefit of FS relationships for risk management.

d) Ensuring that all project activities are completed on time.
Answer

Incorrect. While FS relationships improve scheduling accuracy, they cannot guarantee that all activities will be completed on time.

Exercise: PDM Finish to Start Application

Scenario:

You are managing a pipeline construction project. The project involves the following activities:

  1. Site preparation: 2 weeks
  2. Pipeline welding: 4 weeks
  3. Pipeline inspection: 1 week
  4. Pipeline coating: 2 weeks
  5. Backfilling: 1 week

Task:

Identify the appropriate Finish to Start (FS) relationships between these activities. Explain your reasoning for each relationship.

Exercice Correction

Here are the appropriate FS relationships and the reasoning:

  1. Site preparation (FS) Pipeline welding: You need to prepare the site before starting the welding.
  2. Pipeline welding (FS) Pipeline inspection: You must complete the welding before inspecting the pipeline.
  3. Pipeline inspection (FS) Pipeline coating: The inspection must be done before applying the coating.
  4. Pipeline coating (FS) Backfilling: The coating needs to be completed before backfilling the pipeline.


Books

  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner: A comprehensive text covering project management principles including scheduling and dependency relationships.
  • Primavera P6 for Project Managers: A Comprehensive Guide by John M. Nicholas: A practical guide to using Primavera P6 software, including a section on defining and managing dependencies.
  • Oil and Gas Project Management: A Practical Guide by Simon Jones: A resource focusing on project management best practices specific to the oil & gas industry.

Articles

  • The Importance of Finish-to-Start Dependencies in Project Scheduling by Project Management Institute (PMI): A general overview of the importance and benefits of using FS dependencies in project management.
  • Optimizing Project Schedules in Oil & Gas Through Effective Dependency Management by Forbes: An article exploring the role of dependency management, including FS relationships, in achieving successful project delivery in the oil & gas sector.
  • The Impact of Dependency Relationships on Project Performance by Project Management Journal: An academic research article exploring the relationship between dependency types, project complexity, and project performance.

Online Resources

  • Primavera P6 Official Documentation: The official documentation from Oracle (the provider of Primavera P6) includes detailed information on using the software, including sections on dependency management and FS relationships.
  • PMI (Project Management Institute): The PMI website provides resources and publications on various project management topics, including scheduling and dependencies.
  • Project Management Institute (PMI) - Scheduling Management Knowledge Area: Provides a detailed overview of scheduling and dependency management concepts as part of the Project Management Body of Knowledge (PMBOK).

Search Tips

  • "PDM Finish to Start Relationship" + "Oil & Gas": This search will provide articles and resources specifically focused on the use of FS relationships in PDM software within the oil & gas industry.
  • "Primavera P6 Dependency Management": This search will yield results on using Primavera P6 to manage project dependencies, including FS relationships.
  • "Project Scheduling Best Practices" + "Oil & Gas": This search will highlight articles discussing the best practices for project scheduling in the oil & gas industry, including dependency management.
Similar Terms
Drilling & Well Completion
Safety Training & Awareness
Project Planning & Scheduling
Human Resources Management
Communication & Reporting
Instrumentation & Control Engineering
Oil & Gas Specific Terms
Risk Management
Oil & Gas Processing
IT Infrastructure
Lifting & Rigging
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back