Glossary of Technical Terms Used in Project Planning & Scheduling: Out-of-Sequence Progress

Out-of-Sequence Progress

Out-of-Sequence Progress: When Project Logic Takes a Detour

In the realm of project management, meticulous planning and adherence to a defined sequence of activities are crucial for success. However, sometimes, unforeseen circumstances necessitate a deviation from the established plan, leading to out-of-sequence progress. This phenomenon, while seemingly paradoxical, can occur in various scenarios and deserves careful consideration.

Understanding Out-of-Sequence Progress

Out-of-sequence progress refers to the reporting of progress on a particular activity even though its designated predecessors, according to project logic, have not been completed. In simpler terms, it means moving forward with a task even though prior, dependent tasks haven't been finished.

Causes of Out-of-Sequence Progress

Several factors can contribute to out-of-sequence progress:

  • Resource availability: A team might have access to resources necessary for a specific activity, even though its predecessors are not yet complete. This could be due to an unexpected opportunity or resource surplus.
  • Risk mitigation: If a critical path activity is facing significant delays, the project manager may choose to progress with a non-critical activity that can be completed independently.
  • Flexibility in project logic: In some projects, the dependency between tasks might not be strictly linear. There could be room for parallel activities, enabling progress on a task even if a predecessor is not fully completed.
  • Contingency planning: Projects often involve contingency plans for potential disruptions. If a specific contingency requires a task to be initiated before its predecessor is complete, out-of-sequence progress is necessary.

Impact of Out-of-Sequence Progress

While seemingly advantageous at first glance, out-of-sequence progress can have both positive and negative impacts:

Positive:

  • Potential for cost savings: Starting a task early could lead to faster completion and reduced overall project costs.
  • Improved project flexibility: By allowing for parallel activities, out-of-sequence progress can contribute to better resource utilization and overall project agility.
  • Mitigation of risks: Early action can help avoid potential delays or disruptions later in the project.

Negative:

  • Increased complexity: Managing out-of-sequence activities requires extra effort and can lead to confusion within the project team.
  • Increased risk: Progressing without completing predecessors can lead to rework and potential quality issues.
  • Inaccurate reporting: Reporting progress out of sequence can distort the true project status and impact decision-making.

Managing Out-of-Sequence Progress

Effective management of out-of-sequence progress is crucial for maintaining project control:

  • Clear communication: Transparency and clear communication with all stakeholders about the reasons for and implications of out-of-sequence progress are paramount.
  • Risk assessment: Thoroughly analyze the potential risks associated with the deviation from the original project plan.
  • Contingency plans: Establish clear contingency plans to address any potential issues arising from out-of-sequence progress.
  • Monitoring and tracking: Closely monitor the impact of out-of-sequence activities on the overall project timeline and budget.

Conclusion

Out-of-sequence progress is a reality in project management, often driven by practical considerations or unforeseen circumstances. While it can offer potential benefits, it also introduces complexities and risks. By understanding its causes, impacts, and effective management strategies, project managers can leverage this approach judiciously, ensuring project success even when the path deviates from the original plan.


Test Your Knowledge

Quiz: Out-of-Sequence Progress

Instructions: Choose the best answer for each question.

1. What does "out-of-sequence progress" refer to?

(a) Completing tasks in a random order. (b) Progressing with a task even though its predecessors are not finished. (c) Reporting progress on tasks that have not yet started. (d) Exceeding the planned progress for a specific task.

Answer

(b) Progressing with a task even though its predecessors are not finished.

2. Which of the following is NOT a potential cause of out-of-sequence progress?

(a) Availability of resources for a task, even if its predecessors are not complete. (b) Strict adherence to the original project plan. (c) Mitigation of risks associated with a critical path activity. (d) Flexibility in project logic allowing for parallel activities.

Answer

(b) Strict adherence to the original project plan.

3. What is a potential positive impact of out-of-sequence progress?

(a) Increased complexity in project management. (b) Potential for cost savings due to earlier task completion. (c) Increased risk of rework and quality issues. (d) Inaccurate project status reporting.

Answer

(b) Potential for cost savings due to earlier task completion.

4. Which of the following is NOT a recommended strategy for managing out-of-sequence progress?

(a) Communicating the reasons and implications to all stakeholders. (b) Ignoring potential risks associated with the deviation from the plan. (c) Developing contingency plans for potential issues. (d) Monitoring the impact of out-of-sequence activities on the overall project.

Answer

(b) Ignoring potential risks associated with the deviation from the plan.

5. Out-of-sequence progress can be a valuable tool for project managers, but it is crucial to:

(a) Use it for all tasks regardless of dependencies. (b) Avoid it at all costs to maintain a predictable schedule. (c) Implement it carefully, considering both benefits and potential drawbacks. (d) Report progress out of sequence regardless of the actual completion status.

Answer

(c) Implement it carefully, considering both benefits and potential drawbacks.

Exercise: Out-of-Sequence Scenario

Scenario: You are managing a software development project. Task "A" (design) is a predecessor to Task "B" (development). However, due to a delay in the design process, the development team has access to the required resources and could start working on Task "B" ahead of schedule.

Task:

  1. Analyze the potential risks and benefits of starting Task "B" out of sequence. Consider factors like resource availability, risk mitigation, potential for rework, and impact on project deadlines.
  2. Outline a plan for managing this out-of-sequence progress. Include steps for communicating the decision, monitoring progress, and mitigating potential issues.

Exercice Correction

**Potential Risks and Benefits:**

**Benefits:**

  • **Faster project completion:** Starting development early could potentially accelerate the overall project timeline, especially if the design delay is significant.
  • **Resource utilization:** The development team's availability could be leveraged to make progress, even if the design is not fully finalized.

**Risks:**

  • **Rework:** If the design changes significantly during development, it could lead to rework and potentially impact the overall project quality.
  • **Increased complexity:** Managing parallel activities with potential dependencies can be more complex and require increased coordination.
  • **Communication challenges:** Ensuring clear communication between the design and development teams to avoid conflicts and ensure compatibility is critical.

**Management Plan:**

  • **Communicate the decision:** Clearly inform stakeholders of the decision to start development out of sequence, explaining the reasons and potential risks.
  • **Define clear scope:** Establish a well-defined scope for the development work based on the available design documentation, outlining any assumptions and potential limitations.
  • **Risk mitigation:** Develop contingency plans for potential design changes, including potential for rework, time buffers, and communication protocols.
  • **Monitor progress:** Track both design and development progress closely. Regularly review the impact of the out-of-sequence activity on the overall project schedule and budget.
  • **Open communication:** Maintain open communication channels between the design and development teams to address any issues or questions promptly.


Books

  • Project Management Institute. (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) (7th ed.). Project Management Institute. - This comprehensive guide provides a detailed explanation of project management best practices, including managing dependencies and critical path analysis, which are relevant to understanding out-of-sequence progress.

Articles

  • "Out-of-Sequence Progress: Why it's Not Always a Bad Thing" by ProjectManagement.com - This article discusses the pros and cons of out-of-sequence progress, providing insights into managing its potential risks and benefits.

Online Resources

  • Project Management Institute (PMI) - The PMI website provides a vast repository of resources, including articles, case studies, and webinars related to project management principles. You can search for content specifically related to dependencies, risk management, and project schedule optimization.

Search Tips

  • Use specific keywords: When searching for relevant information, use keywords like "out-of-sequence progress," "project dependencies," "schedule deviations," and "risk management."
Similar Terms
Human Resources Management
Emergency Response Planning
Oil & Gas Processing
Project Planning & Scheduling
Pipeline Construction
Communication & Reporting
  • Progress Progress: The Pulse of Projec…
  • Progress Progress: A Guiding Star in P…
Commissioning Procedures
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back