Glossary of Technical Terms Used in Project Planning & Scheduling: Lagging

Lagging

Lagging: A Scheduling Tool for Efficient Oil & Gas Operations

In the complex and fast-paced world of oil and gas, efficient project management is paramount. Every minute counts, and delays can translate into significant financial losses. This is where lagging, a crucial scheduling technique, comes into play.

Lagging, in its simplest form, is deliberately delaying the start or finish of an activity relative to another. This might seem counterintuitive at first glance. However, it's a powerful strategy that allows for concurrent progress on multiple activities, maximizing efficiency and ultimately, minimizing project timelines.

Here's a breakdown of how lagging works:

Types of Lagging:

  • Start-to-Start Lag: The start of one activity is delayed by a specified duration after the start of another activity. Example: Drilling a well can't begin until the platform construction is completed, but the construction can start before drilling begins.
  • Finish-to-Start Lag: The start of one activity is delayed until a specified duration after the completion of another activity. Example: Pipeline installation can't begin until the well is drilled and capped.
  • Finish-to-Finish Lag: The completion of one activity is delayed until a specified duration after the completion of another activity. Example: The completion of environmental impact assessment might be delayed until the completion of drilling operations.

Benefits of Lagging:

  • Resource Optimization: Lagging enables teams to efficiently utilize resources. Activities can overlap, allowing for the same equipment or personnel to be used on multiple tasks simultaneously.
  • Time Management: Lagging allows for more efficient project timelines by maximizing parallel activity progress.
  • Flexibility: Lagging provides flexibility in scheduling. If one activity encounters delays, the subsequent activity's start can be adjusted accordingly, minimizing the overall project impact.
  • Risk Mitigation: By allowing for the completion of critical tasks before starting others, lagging can mitigate risks associated with unforeseen delays or complications.

Example in Oil & Gas:

Imagine a project to construct an offshore platform for oil extraction. Lagging can be employed to ensure efficient completion:

  • Activity 1: Platform Construction: Begins immediately.
  • Activity 2: Well Drilling: Starts with a Finish-to-Start lag of 3 months after the completion of platform construction.
  • Activity 3: Pipeline Installation: Starts with a Finish-to-Start lag of 1 month after the completion of well drilling.

This strategy allows the construction and drilling teams to work concurrently, ultimately saving time and resources.

Key Considerations:

  • Dependencies: Careful identification of dependencies between activities is essential for successful lagging.
  • Duration Estimation: Accurate estimation of task durations is crucial. Overestimated durations can create unnecessary delays, while underestimated ones can lead to project complications.
  • Flexibility: While lagging provides flexibility, it's crucial to maintain a balance between allowing for concurrent progress and ensuring timely completion of critical tasks.

In conclusion, lagging is a powerful tool in the oil and gas industry. By enabling concurrent progress on multiple activities, lagging optimizes resources, minimizes project timelines, and mitigates risks. Understanding and implementing lagging strategies effectively can significantly contribute to the success of oil and gas projects.


Test Your Knowledge

Quiz on Lagging in Oil & Gas Scheduling

Instructions: Choose the best answer for each question.

1. What is the core principle of lagging in project management? a) Starting every activity simultaneously.

Answer

b) Delaying the start or finish of an activity relative to another.

c) Finishing one activity before starting the next. d) Utilizing resources for only one activity at a time.

2. Which type of lagging delays the start of one activity until a specified time after the completion of another activity? a) Start-to-Start Lag

Answer

b) Finish-to-Start Lag

c) Finish-to-Finish Lag d) None of the above

3. What is NOT a benefit of using lagging in oil and gas projects? a) Optimized resource utilization b) Reduced project timelines c) Increased project complexity

Answer

d) Reduced flexibility in scheduling

4. In the example of offshore platform construction, what type of lagging is applied to well drilling? a) Start-to-Start Lag

Answer

b) Finish-to-Start Lag

c) Finish-to-Finish Lag d) No lagging is applied

5. Which factor is NOT crucial for successful lagging implementation? a) Identifying dependencies between activities

Answer

b) Minimizing the number of activities in the project

c) Accurate estimation of task durations d) Balancing concurrent progress with timely completion of critical tasks

Exercise on Lagging in Oil & Gas Scheduling

Scenario: You are managing the construction of an onshore oil processing facility. The project involves the following activities:

  • Activity 1: Site Preparation: 2 months
  • Activity 2: Foundation Construction: 3 months (depends on site preparation completion)
  • Activity 3: Building Construction: 4 months (depends on foundation construction completion)
  • Activity 4: Equipment Installation: 2 months (depends on building construction completion)
  • Activity 5: Testing and Commissioning: 1 month (depends on equipment installation completion)

Task:

  1. Identify potential lagging opportunities in this project. Explain the type of lagging (Start-to-Start, Finish-to-Start, or Finish-to-Finish) you would apply for each opportunity.
  2. Draw a simple Gantt chart illustrating your chosen lagging strategies.

Exercice Correction

1. Potential Lagging Opportunities:

  • Activity 2 (Foundation Construction) & Activity 3 (Building Construction): Apply Finish-to-Start Lag of 1 month. This allows the building construction team to begin 1 month after the foundation construction is completed, enabling some overlap and potential resource optimization.
  • Activity 3 (Building Construction) & Activity 4 (Equipment Installation): Apply Finish-to-Start Lag of 1 month. This allows the equipment installation team to begin 1 month after the building construction is completed, enabling parallel work and reducing overall project duration.

2. Gantt Chart (Simplified):

[Insert a simple Gantt chart showing the activities with the identified lagging strategies applied.]

Explanation: By applying Finish-to-Start lagging with a 1-month delay in both instances, the project timeline is potentially shortened, allowing for concurrent work and optimizing resource utilization. It's important to note that the specific lagging durations should be carefully assessed based on resource availability and project constraints.


Books

  • Project Management for the Oil & Gas Industry by J.D. Wellborn: Covers various aspects of project management including scheduling techniques like lagging.
  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner: A comprehensive book on project management, with dedicated sections on scheduling techniques like lagging.
  • Planning and Scheduling for Construction by Charles E. Harris: While focusing on construction, this book delves into advanced scheduling methods like lagging and its applications.

Articles

  • "Lagging in Project Scheduling: A Guide for Oil & Gas Professionals" by [Your Name] (This article can be written by you, explaining the concept of lagging in detail for an oil and gas audience.)
  • "Optimize Oil & Gas Projects with Lagging: A Case Study" (This can be a case study demonstrating the benefits of lagging in a specific oil and gas project.)
  • "Lagging: A Powerful Tool for Resource Optimization in Oil & Gas Projects" (An article emphasizing the resource optimization aspect of lagging in oil and gas.)

Online Resources

  • Project Management Institute (PMI): Provides resources, articles, and webinars on various project management topics, including scheduling. https://www.pmi.org/
  • Oil & Gas Journal: Offers industry news and analysis, including articles on project management and scheduling. https://www.ogj.com/
  • Society of Petroleum Engineers (SPE): A professional organization for oil and gas professionals, offering resources on various topics, including project management. https://www.spe.org/

Search Tips

  • "Lagging in project scheduling oil and gas"
  • "Lagging technique for resource optimization in oil and gas"
  • "Case studies on lagging in oil and gas projects"
  • "Project management software for oil and gas with lagging feature"
Similar Terms
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back