Glossary of Technical Terms Used in Project Planning & Scheduling: Lag Relationship

Lag Relationship

Understanding Lag Relationships in Oil & Gas Projects

In the dynamic and complex world of oil and gas projects, effective project management is crucial to success. One key concept that plays a vital role is the understanding and utilization of lag relationships. Lag relationships define the time delay between the start or finish of one activity and the start or finish of another activity within a project schedule. These relationships are crucial for establishing the correct sequencing of tasks and ensuring a smooth workflow.

The Four Basic Types of Lag Relationships

There are four fundamental types of lag relationships used in oil and gas project management:

  1. Finish to Start (FS): This is the most common type of lag relationship. It states that an activity cannot start until a preceding activity has finished.

    • Example: Drilling a well cannot start until the rig is assembled (the assembly process must finish before drilling can begin).
  2. Start to Finish (SF): This relationship specifies that a preceding activity cannot finish until a following activity has started.

    • Example: A pipeline installation cannot be completed until the welding crew starts working on the pipe sections.
  3. Finish to Finish (FF): This lag relationship requires both activities to finish at the same time.

    • Example: The installation of a platform's deck and the completion of the substructure must both be finished simultaneously before the platform can be considered fully operational.
  4. Start to Start (SS): This relationship indicates that both activities must start at the same time.

    • Example: The procurement of drilling equipment and the mobilization of the drilling crew must start simultaneously to ensure the timely commencement of drilling operations.

Implementing Lag Relationships in Oil & Gas Projects

Implementing these lag relationships effectively requires careful consideration of the following:

  • Project Scope: Understanding the overall project scope and the dependencies between different activities is essential.
  • Resource Availability: Lag relationships must be aligned with the availability of resources such as equipment, personnel, and materials.
  • Potential Risks: Analyzing potential risks and their impact on project timelines is critical for optimizing lag relationships.
  • Communication: Clear communication between project stakeholders ensures that everyone understands the lag relationships and their implications.

Benefits of Using Lag Relationships

  • Improved Project Scheduling: Lag relationships facilitate a more accurate and realistic project schedule, minimizing delays and ensuring efficient resource allocation.
  • Enhanced Risk Management: By defining dependencies, potential risks can be identified and mitigated early on.
  • Increased Efficiency: Lag relationships promote smooth workflows and prevent unnecessary delays, leading to increased project efficiency.
  • Improved Communication: Clearly defined lag relationships enhance communication between project team members and stakeholders.

Conclusion

Lag relationships are an essential tool for effective project management in the oil and gas industry. By understanding the different types of lag relationships and implementing them strategically, project managers can optimize schedules, mitigate risks, and ultimately drive project success. Properly utilizing these relationships empowers stakeholders to navigate complex projects with greater efficiency and accuracy.


Test Your Knowledge

Quiz: Understanding Lag Relationships in Oil & Gas Projects

Instructions: Choose the best answer for each question.

1. Which lag relationship describes the scenario where a pipeline installation cannot be completed until the welding crew starts working on the pipe sections? a) Finish to Start (FS) b) Start to Finish (SF) c) Finish to Finish (FF) d) Start to Start (SS)

Answer

b) Start to Finish (SF)

2. Which of the following is NOT a benefit of using lag relationships in oil & gas projects? a) Improved Project Scheduling b) Enhanced Risk Management c) Increased Cost Savings d) Improved Communication

Answer

c) Increased Cost Savings

3. A drilling rig cannot start drilling a well until the rig is assembled. This is an example of what type of lag relationship? a) Finish to Start (FS) b) Start to Finish (SF) c) Finish to Finish (FF) d) Start to Start (SS)

Answer

a) Finish to Start (FS)

4. What is the most crucial factor to consider when implementing lag relationships in a project? a) Project Budget b) Project Scope c) Project Timeline d) Project Team Size

Answer

b) Project Scope

5. Which lag relationship ensures that two activities start simultaneously? a) Finish to Start (FS) b) Start to Finish (SF) c) Finish to Finish (FF) d) Start to Start (SS)

Answer

d) Start to Start (SS)

Exercise: Implementing Lag Relationships

Scenario: You are managing an offshore oil platform construction project. The following activities are scheduled:

  1. Transport Platform to Location (Activity A): 10 days
  2. Install Platform Legs (Activity B): 7 days
  3. Install Deck on Platform (Activity C): 5 days
  4. Connect Pipelines to Platform (Activity D): 3 days

Requirement:

  • Activity B (Install Platform Legs) cannot start until Activity A (Transport Platform to Location) is finished.
  • Activity C (Install Deck on Platform) cannot start until Activity B (Install Platform Legs) is finished.
  • Activity D (Connect Pipelines to Platform) cannot start until Activity C (Install Deck on Platform) is finished.

Task:

  1. Using the information provided, create a simple project schedule diagram outlining the activities and their lag relationships.
  2. Calculate the total project duration based on the defined dependencies and activity durations.

Exercice Correction

Project Schedule Diagram:

Activity A (Transport Platform to Location) -> Activity B (Install Platform Legs) -> Activity C (Install Deck on Platform) -> Activity D (Connect Pipelines to Platform) 10 days 7 days 5 days 3 days

Total Project Duration:

Total duration = Activity A + Activity B + Activity C + Activity D = 10 + 7 + 5 + 3 = 25 days


Books

  • Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Seventh Edition. This comprehensive guide covers various aspects of project management, including scheduling and dependency relationships.
  • Harold Kerzner. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling, 12th Edition. A widely recognized textbook that provides detailed insights into project management, including scheduling techniques and lag relationships.
  • Meredith, J. R., & Mantel, S. J. (2018). Project Management: A Managerial Approach. A textbook focusing on the practical aspects of project management, with dedicated chapters on scheduling and dependency relationships.

Articles

  • "Lag Relationships in Project Management: Definition, Types, and Examples" by ProjectManager.com. This article provides a comprehensive overview of lag relationships, explaining their types and applications in project management.
  • "Understanding and Using Lags in Project Scheduling" by ProjectManagement.com. This article delves into the importance of using lags in project scheduling, emphasizing their role in achieving accurate timelines and efficient resource allocation.
  • "Lag Relationships: A Key Element of Effective Project Scheduling" by ProjectManagementHacks.com. This article highlights the impact of lag relationships on project efficiency and success, providing real-world examples and practical tips.

Online Resources

  • ProjectManagement.com: Offers a wealth of resources on project management, including articles, tutorials, and templates related to scheduling and lag relationships.
  • PMI.org: Provides access to a vast library of project management knowledge, including resources specifically addressing scheduling and dependency relationships.
  • ProjectManagementHacks.com: Offers practical guidance and tips on various aspects of project management, including scheduling techniques and lag relationships.

Search Tips

  • Use specific keywords: Combine "lag relationships" with "project management," "oil & gas," "scheduling," and "dependency relationships."
  • Include industry-specific terms: Use terms like "upstream," "downstream," "drilling," "pipeline," and "platform construction" to find more relevant results.
  • Utilize advanced operators: Employ operators like "site:edu" to search academic websites or "site:gov" for government resources.
  • Try different search phrases: Experiment with different combinations of keywords and phrases to discover relevant content.
Similar Terms
Communication & Reporting
Oil & Gas Processing
Drilling & Well Completion
Mechanical Engineering
Project Planning & Scheduling
Pipeline Construction
  • Lag Understanding Lag in Oil &…
Human Resources Management
Oil & Gas Specific Terms
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back