Glossary of Technical Terms Used in Pipeline Construction: Lag

Lag

Understanding Lag in Oil & Gas Projects: A Crucial Time Management Tool

In the fast-paced world of oil and gas projects, where every minute counts, efficient scheduling and resource allocation are paramount. A key concept in project management that helps achieve this is lag, a crucial term that defines the time delay between the start or finish of one activity and the start or finish of its successor(s).

What is Lag?

Simply put, lag is a deliberate delay built into a project schedule to accommodate dependencies between activities. It's not a mistake or a setback but a calculated adjustment to ensure activities flow smoothly and efficiently.

Types of Lag

Lag comes in three distinct flavors, each with its own purpose and application:

  • Finish-to-Finish Lag: This type of lag ensures a specific amount of time passes after the finish of a preceding activity before the succeeding activity can be completed. This is useful when the succeeding activity requires the output of the preceding one to be fully processed or analyzed.

    • Example: After drilling a well, a specific amount of time needs to be allowed for the well to stabilize before flow testing can begin.
  • Finish-to-Start Lag: This type of lag requires a specific amount of time to pass after the finish of the preceding activity before the succeeding activity can start. This is useful when the succeeding activity depends on a specific outcome from the preceding one, but doesn't require the preceding activity to be fully completed.

    • Example: After a pipeline is laid, a period of time is needed for the weld inspection and verification before the pipeline can be pressurized and put into service.
  • Start-to-Start Lag: This type of lag requires a specific amount of time to pass after the start of the preceding activity before the succeeding activity can start. This is used when the two activities can happen simultaneously but require a certain amount of time offset.

    • Example: The construction of a platform's deck can start after the platform's legs are partially constructed, but the two activities can progress simultaneously.

Benefits of Lag in Oil & Gas Projects:

  • Realistic Scheduling: Lag helps create realistic schedules by accounting for dependencies and necessary waiting periods, minimizing unexpected delays and resource bottlenecks.
  • Enhanced Efficiency: By incorporating lag, project managers can optimize resource allocation, ensuring the right people and equipment are available when needed, leading to improved productivity.
  • Risk Mitigation: Lag allows for buffer time, which can help mitigate the impact of unforeseen delays and issues, ensuring project milestones are achieved within acceptable timeframes.

Lag in Action:

In a typical oil and gas project, lag is frequently used in:

  • Well drilling and completion: Lag is used to account for the time needed for cement curing, well testing, and equipment setup between different phases of well drilling and completion.
  • Pipeline construction and commissioning: Lag is employed to allow for welding inspection, pressure testing, and other critical activities before the pipeline becomes operational.
  • Facility construction: Lag is incorporated to ensure proper staging of activities like foundation work, equipment installation, and commissioning.

Conclusion:

Lag is a fundamental concept in oil and gas project management, offering a powerful tool for creating realistic, efficient, and risk-mitigated schedules. By understanding the different types of lag and how they can be implemented, project managers can optimize resource allocation, minimize delays, and ultimately, ensure project success in this demanding industry.


Test Your Knowledge

Quiz on Lag in Oil & Gas Projects

Instructions: Choose the best answer for each question.

1. What is the primary purpose of lag in project management?

(a) To identify potential problems in the project schedule. (b) To introduce delays into the project for strategic reasons. (c) To account for dependencies between activities and ensure a smooth workflow. (d) To track the progress of individual activities within the project.

Answer

(c) To account for dependencies between activities and ensure a smooth workflow.

2. Which type of lag ensures a specific amount of time passes after the finish of one activity before another activity can be completed?

(a) Start-to-Start Lag (b) Finish-to-Finish Lag (c) Finish-to-Start Lag (d) None of the above

Answer

(b) Finish-to-Finish Lag

3. In which scenario would Finish-to-Start Lag be most appropriate?

(a) Installing a platform's legs and deck simultaneously. (b) Waiting for cement to cure before starting well testing. (c) Conducting weld inspection before pressurizing a pipeline. (d) Analyzing flow data from a well after it stabilizes.

Answer

(c) Conducting weld inspection before pressurizing a pipeline.

4. What is a key benefit of incorporating lag into oil and gas project schedules?

(a) Reducing the overall project duration. (b) Eliminating the need for resource allocation planning. (c) Creating more realistic schedules by accounting for dependencies. (d) Increasing the complexity of the project schedule.

Answer

(c) Creating more realistic schedules by accounting for dependencies.

5. Which of the following is NOT an example of a typical application of lag in oil and gas projects?

(a) Allowing time for well testing after drilling. (b) Scheduling pipeline commissioning after pressure testing. (c) Ensuring equipment availability for facility construction. (d) Tracking the progress of individual drilling crews.

Answer

(d) Tracking the progress of individual drilling crews.

Exercise: Lag in Pipeline Construction

Scenario: You are managing a pipeline construction project. The following activities are planned:

  1. Laying the pipeline: Estimated duration: 10 days
  2. Welding inspection and verification: Estimated duration: 3 days
  3. Pressure testing: Estimated duration: 2 days
  4. Commissioning and handover: Estimated duration: 1 day

Task:

  1. Identify the dependencies between these activities.
  2. Determine the appropriate type of lag to be applied between each activity.
  3. Draw a simple Gantt chart to visualize the project schedule with the implemented lag.

Note: You can assume that welding inspection and verification must be completed before pressure testing, and commissioning can only begin after the pipeline is pressure tested.

Exercice Correction

**Dependencies:** * Welding inspection and verification depends on the completion of laying the pipeline (Finish-to-Start). * Pressure testing depends on the completion of welding inspection and verification (Finish-to-Start). * Commissioning and handover depends on the completion of pressure testing (Finish-to-Start). **Lag Application:** * Apply Finish-to-Start Lag between laying the pipeline and welding inspection (3 days). * Apply Finish-to-Start Lag between welding inspection and pressure testing (0 days, as the activity can start immediately after the previous one). * Apply Finish-to-Start Lag between pressure testing and commissioning (0 days, as the activity can start immediately after the previous one). **Gantt Chart:** | Activity | Start Date | End Date | Duration | |---------------------------|------------|-----------|---------| | Laying the pipeline | Day 1 | Day 10 | 10 days | | Welding inspection/verification | Day 11 | Day 13 | 3 days | | Pressure testing | Day 14 | Day 15 | 2 days | | Commissioning/handover | Day 16 | Day 16 | 1 day |


Books

  • Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Seventh Edition. Project Management Institute. This is the definitive guide to project management best practices, including detailed sections on scheduling, dependencies, and lag.
  • Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. John Wiley & Sons. This comprehensive textbook covers various project management aspects, including a dedicated section on lag and its application.
  • Meredith, J. R., & Mantel, S. J. (2019). Project Management: A Managerial Approach. John Wiley & Sons. This textbook offers a practical approach to project management, with a specific chapter on scheduling and lag.

Articles

  • "Lag in Project Management: Definition, Types, and Benefits" by Project Management Institute (PMI): [Link to article] - This PMI article provides a detailed explanation of different lag types and their benefits.
  • "The Importance of Lag in Project Scheduling" by ProjectManager.com: [Link to article] - This article focuses on the practical application of lag and its impact on project schedules.
  • "How to Use Lag in Project Scheduling" by Smartsheet: [Link to article] - This article provides a step-by-step guide on using lag in project scheduling software.

Online Resources

  • Project Management Institute (PMI) Website: [Link to website] - The PMI website offers a wealth of information on project management, including resources on scheduling and lag.
  • ProjectManager.com: [Link to website] - This website offers articles, tutorials, and resources on various project management topics, including lag.
  • Smartsheet: [Link to website] - This website provides project management software and resources, with a focus on scheduling and lag.

Search Tips

  • "Lag in Project Management": Start with this general search term to find articles and resources on the topic.
  • "Types of Lag in Project Management": Use this term to explore the different types of lag and their applications.
  • "Lag in Oil and Gas Project Management": This specific search term will retrieve articles and resources relevant to the oil and gas industry.
  • "Lag in Project Scheduling Software": This search term will help you find software solutions that incorporate lag functionality.
Similar Terms
Communication & Reporting
Oil & Gas Processing
  • Deflagration Deflagration: A Controlled Bu…
  • Lag Lag: A Critical Concept in Oi…
Drilling & Well Completion
Project Planning & Scheduling
  • Lag Understanding Lag in Oil &…
  • Lag Understanding Lag in Oil &…
  • Lagging Lagging: A Scheduling Tool fo…
  • Lag Relationship Understanding Lag Relationshi…
  • Lag Time Lag Time: A Critical Factor i…
Human Resources Management
Pipeline Construction
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back