Cost Estimation & Control

Estimate to Complete ("ETC")

Understanding Estimate to Complete (ETC) in Cost Estimation & Control

In the realm of project management and cost control, accurately predicting the remaining resources needed to finish a project is crucial. This is where the concept of Estimate to Complete (ETC) comes into play. ETC is a key metric used to gauge the expected cost of finishing the remaining work on a project, taking into account past performance and any unforeseen changes.

Defining ETC

Put simply, ETC is an estimate of the time and/or effort required to complete an activity or project. It's a forward-looking calculation that helps project managers and stakeholders understand the financial implications of finishing the project.

Calculating ETC

Calculating ETC requires a few key pieces of information:

  • Actual Costs Incurred (AC): The total amount spent on the project so far.
  • Budget at Completion (BAC): The total planned budget for the project.
  • Earned Value (EV): The value of work completed so far.

There are two primary methods for calculating ETC:

  1. Bottom-up approach: This method involves breaking down the remaining work into smaller tasks and estimating the cost of each task individually. This approach is more precise but also more time-consuming.
  2. Top-down approach: This method uses historical data and experience to estimate the remaining costs. It's faster and less detailed but may be less accurate.

Utilizing ETC in Project Management

ETC plays a crucial role in effective project management:

  • Forecasting Costs: ETC helps in predicting the total cost of the project, allowing for adjustments to be made if necessary.
  • Monitoring Progress: By comparing ETC with the original budget, project managers can identify potential cost overruns or savings.
  • Making Informed Decisions: ETC provides valuable data to support decisions like resource allocation, scope changes, and risk mitigation.
  • Improving Accuracy: By consistently reviewing and updating ETC estimates, project managers can refine their estimations and improve project control.

Importance of Accuracy

While ETC is a valuable tool, it's essential to remember that it's an estimate and not a guarantee. Factors like unexpected delays, scope changes, and fluctuating market conditions can significantly impact the final cost. Therefore, project managers must be cautious when using ETC and regularly review and adjust their estimates as the project progresses.

Summary

Estimate to Complete (ETC) is a critical element of cost estimation and control in project management. By accurately forecasting the remaining cost of a project, ETC empowers stakeholders to make informed decisions, monitor project progress, and achieve successful project outcomes.


Test Your Knowledge

Quiz: Understanding Estimate to Complete (ETC)

Instructions: Choose the best answer for each question.

1. What does ETC stand for?

a) Estimate to Complete b) Estimate to Close c) Expected Time Completion d) Estimated Time Cost

Answer

a) Estimate to Complete

2. Which of the following is NOT a key input for calculating ETC?

a) Actual Costs Incurred (AC) b) Budget at Completion (BAC) c) Earned Value (EV) d) Project Charter

Answer

d) Project Charter

3. The bottom-up approach to calculating ETC is:

a) Faster but less accurate b) Slower but more accurate c) Easier to implement d) Based on historical data

Answer

b) Slower but more accurate

4. How can ETC be used in project management?

a) To predict the total cost of the project b) To monitor project progress c) To make informed decisions about resource allocation d) All of the above

Answer

d) All of the above

5. What is the most important factor to consider when using ETC?

a) The project manager's experience b) The availability of resources c) The accuracy of the estimates d) The complexity of the project

Answer

c) The accuracy of the estimates

Exercise: ETC Calculation

Scenario:

You are managing a software development project with a budget of $100,000 (BAC). So far, you have spent $60,000 (AC) and have completed 70% of the planned work (EV).

Task: Calculate the ETC using the bottom-up approach.

Instructions:

  1. Break down the remaining work: Identify the tasks that still need to be completed and estimate the cost of each task.
  2. Sum the costs: Add up the estimated costs of all remaining tasks to get the ETC.

Exercice Correction

Here's a possible approach to the exercise:

**1. Remaining work:**

  • Code review and testing (30% of the project): $15,000 (assuming 50% of the remaining budget)
  • Documentation and deployment (10% of the project): $5,000 (assuming 17% of the remaining budget)

**2. ETC:**

  • Total ETC: $15,000 + $5,000 = $20,000

**Note:** This is just one possible breakdown of the remaining work and cost estimates. The actual ETC may vary depending on the specific tasks and their associated costs.


Books

  • Project Management Institute (PMI). (2017). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition. PMI Publishing. This comprehensive guide covers the entire scope of project management, including earned value management and ETC calculations.
  • Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. John Wiley & Sons. This classic textbook provides a detailed explanation of project management principles, including cost estimation and ETC analysis.
  • Verzuh, D. (2010). The Complete Guide to Earned Value Management. John Wiley & Sons. This book delves specifically into earned value management, providing detailed explanations of ETC calculations and their applications.

Articles


Online Resources

  • Project Management Institute (PMI) website. https://www.pmi.org/ The PMI website offers a wealth of resources for project managers, including articles, webinars, and training materials on topics such as earned value management and ETC.
  • Earned Value Management (EVM) - Wikipedia. https://en.wikipedia.org/wiki/Earnedvaluemanagement This Wikipedia article provides a comprehensive overview of EVM, including the calculation of ETC and its significance in project control.
  • "Estimate to Complete (ETC) Calculator" by ProjectManager. https://www.projectmanager.com/features/earned-value-management/ This online calculator provides a convenient tool for calculating ETC, based on inputting relevant project data.

Search Tips

  • "Estimate to Complete (ETC) definition" This will provide numerous definitions and explanations of the term.
  • "Estimate to Complete (ETC) calculation" This will return search results showcasing various formulas and methods used to calculate ETC.
  • "Estimate to Complete (ETC) example" This will offer real-world scenarios demonstrating how ETC is applied in project management.
  • "Estimate to Complete (ETC) software" This will lead to a list of software programs and tools that incorporate ETC calculations into their project management features.

Techniques

Similar Terms
Drilling & Well CompletionAsset Integrity ManagementInstrumentation & Control EngineeringProcess EngineeringProject Planning & SchedulingData Management & AnalyticsFunctional TestingMechanical EngineeringCost Estimation & ControlReservoir Engineering
Most Viewed
Categories

Comments


No Comments
POST COMMENT
captcha
Back