Cost Estimation & Control

Cost Variance ("CV")

Understanding Cost Variance: Keeping Your Project on Budget

In the world of project management, staying within budget is crucial. One of the key tools for tracking costs and identifying potential problems is Cost Variance (CV). CV helps measure how well a project is performing against its planned budget, alerting you to potential overruns or underspending.

What is Cost Variance?

Cost Variance (CV) is the difference between the Budgeted Cost of Work Performed (BCWP) and the Actual Cost of Work Performed (ACWP).

  • BCWP: This represents the value of work completed according to the project schedule and budget. It's the planned cost of the work that has been finished.
  • ACWP: This reflects the actual cost incurred to complete the work performed. It's the real money spent on the tasks that have been finished.

The Formula:

The most common formula for calculating CV is:

CV = BCWP - ACWP

Interpreting the Results:

  • Positive CV: A positive CV indicates that the project is under budget. This means that you've spent less than you planned to complete the work done.
  • Negative CV: A negative CV indicates that the project is over budget. This means that you've spent more than you planned to complete the work done.

Example:

Imagine a project with a BCWP of $50,000 and an ACWP of $45,000.

  • CV = $50,000 - $45,000 = $5,000

The positive CV of $5,000 signifies that the project is under budget by $5,000. This means that the project is performing well in terms of cost management.

Calculating Percentage Cost Variance:

To express CV as a percentage, use this formula:

CV(%) = (BCWP - ACWP) x 100 / BCWP

In the previous example:

CV(%) = ($50,000 - $45,000) x 100 / $50,000 = 10%

This indicates that the project is 10% under budget.

Why is Cost Variance Important?

  • Early Detection: CV allows you to identify cost issues early in the project lifecycle, giving you time to take corrective actions.
  • Financial Planning: Understanding cost variances helps with accurate budgeting and financial forecasting for future projects.
  • Performance Evaluation: CV is a key indicator of project performance, helping to track progress and identify areas for improvement.

Conclusion:

Cost Variance is a valuable tool for project management. By understanding and monitoring CV, you can gain valuable insights into project performance and ensure that your project remains on track financially. Using CV alongside other cost control methods empowers you to make informed decisions and achieve successful project outcomes.


Test Your Knowledge

Cost Variance Quiz

Instructions: Choose the best answer for each question.

1. What is the formula for calculating Cost Variance (CV)?

a) CV = ACWP - BCWP b) CV = BCWP + ACWP

Answer

a) CV = ACWP - BCWP

2. A positive Cost Variance indicates that the project is:

a) Over budget b) Under budget

Answer

b) Under budget

3. What does BCWP stand for?

a) Budgeted Cost of Work Performed b) Budgetary Cost of Work Performed c) Base Cost of Work Performed

Answer

a) Budgeted Cost of Work Performed

4. A project has a BCWP of $80,000 and an ACWP of $90,000. What is the Cost Variance (CV)?

a) $10,000 b) -$10,000

Answer

b) -$10,000

5. Which of the following is NOT a benefit of understanding Cost Variance?

a) Early detection of cost issues b) Improved team morale c) Accurate financial planning

Answer

b) Improved team morale

Cost Variance Exercise

Scenario:

You are managing a construction project with a budgeted cost of $250,000. The project is currently 60% complete. The actual cost incurred to date is $170,000.

Task:

  1. Calculate the Budgeted Cost of Work Performed (BCWP).
  2. Calculate the Cost Variance (CV).
  3. Interpret the CV result and explain what it means for the project.

Exercice Correction

1. **BCWP:** - 60% completion * $250,000 (budgeted cost) = $150,000 2. **CV:** - CV = BCWP - ACWP - CV = $150,000 - $170,000 = -$20,000 3. **Interpretation:** - The negative CV of -$20,000 indicates that the project is over budget by $20,000. This means that more money has been spent than planned to complete the work done so far. The project manager needs to investigate the reasons for the cost overrun and implement measures to get the project back on track financially.


Books

  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - This guide, published by the Project Management Institute (PMI), provides comprehensive information about project management methodologies, including cost management and variance analysis.
  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner - A classic text that discusses project cost management and variance analysis in detail.
  • Cost Engineering by R.S. Woodhead - A detailed resource on cost estimation, budgeting, and cost control techniques, including cost variance analysis.

Articles

  • "Understanding Cost Variance" by Project Management Institute (PMI) - A practical guide on calculating and interpreting cost variance.
  • "How to Use Cost Variance to Manage Your Projects" by ProjectManager.com - A step-by-step guide on implementing cost variance analysis.
  • "Cost Variance Analysis: A Comprehensive Guide" by Simplilearn - An article offering in-depth insights into cost variance, its calculation, and interpretation.

Online Resources

  • Project Management Institute (PMI): https://www.pmi.org/ - The PMI website offers extensive resources on project management, including cost management and variance analysis.
  • ProjectManager.com: https://www.projectmanager.com/ - This website provides free resources on project management, including articles and tutorials on cost variance.
  • Simplilearn: https://www.simplilearn.com/ - Simplilearn offers a range of online courses and resources on project management, including cost variance analysis.

Search Tips

  • Use specific keywords: Use phrases like "cost variance calculation," "cost variance analysis," "cost variance formula," "cost variance examples," etc.
  • Combine keywords: Use combinations of keywords like "cost variance project management," "cost variance excel," or "cost variance software."
  • Specify your needs: Use specific terms like "cost variance in construction," "cost variance in IT projects," or "cost variance in healthcare."

Techniques