Project Planning & Scheduling

Concurrency

Concurrency: Accelerating Oil & Gas Projects through Overlap

In the competitive world of oil and gas, time is money. Projects need to be completed swiftly and efficiently to maximize returns. This is where the concept of concurrency comes into play. Simply put, concurrency refers to the degree to which different phases, stages, or activities within a project can be overlapped and executed simultaneously.

The Essence of Overlap:

Imagine a traditional project timeline with activities happening in a linear sequence. Phase A must be completed before Phase B can start, and so on. This creates a longer overall project duration.

Concurrency, on the other hand, allows for certain activities to be started even before previous ones are fully finished. This is achieved by strategically planning and coordinating tasks, ensuring dependencies are met, and utilizing resources effectively.

Benefits of Concurrency in Oil & Gas:

  • Reduced Project Duration: By overlapping activities, the overall project timeline can be significantly shortened, leading to faster returns on investment.
  • Increased Efficiency: Utilizing resources more effectively and minimizing idle time leads to greater efficiency and productivity.
  • Enhanced Flexibility: Concurrency allows for more flexibility in project execution, enabling adjustments to be made in response to changing market conditions or unforeseen challenges.
  • Improved Communication & Collaboration: Planning and implementing concurrency requires strong communication and collaboration between different teams and departments, fostering a more integrated and efficient workflow.

Examples of Concurrency in Oil & Gas Projects:

  • Engineering and Procurement: Starting engineering design activities while simultaneously initiating procurement for long-lead items like equipment.
  • Construction and Commissioning: Overlapping construction activities with commissioning and testing of critical equipment.
  • Drilling and Production: Starting production operations while drilling additional wells to optimize production.

Challenges of Concurrency:

  • Complexity: Implementing concurrency requires meticulous planning, coordination, and management of complex dependencies.
  • Resource Management: Efficient allocation of resources to various overlapping activities is crucial to avoid conflicts and delays.
  • Communication & Collaboration: Maintaining clear and consistent communication between teams is vital for ensuring smooth coordination and avoiding potential issues.

Conclusion:

Concurrency is a powerful tool for accelerating oil & gas projects and achieving faster project completion. By strategically overlapping activities, companies can optimize resource utilization, improve efficiency, and ultimately achieve greater profitability. However, implementing concurrency successfully requires careful planning, robust communication, and a well-coordinated team effort. With proper management, concurrency can be a key driver for success in the competitive oil and gas industry.


Test Your Knowledge

Quiz: Concurrency in Oil & Gas

Instructions: Choose the best answer for each question.

1. What is the primary benefit of using concurrency in oil & gas projects? a) Reduced project costs b) Improved safety protocols c) Faster project completion d) Increased environmental impact

Answer

c) Faster project completion

2. Which of the following is NOT a key element of concurrency? a) Strategic planning b) Effective resource allocation c) Strict sequential execution of tasks d) Clear communication

Answer

c) Strict sequential execution of tasks

3. Which of these examples represents concurrency in an oil & gas project? a) Completing the design phase before starting construction. b) Starting procurement for equipment while engineering is ongoing. c) Waiting for a permit before beginning environmental impact assessments. d) Completing drilling before starting production.

Answer

b) Starting procurement for equipment while engineering is ongoing.

4. Which of the following is a potential challenge associated with concurrency? a) Reduced need for specialized expertise b) Simplified project management c) Increased complexity of project dependencies d) Less need for communication between teams

Answer

c) Increased complexity of project dependencies

5. How does concurrency contribute to a more efficient project workflow? a) Minimizing idle time for resources b) Reducing the number of tasks needed for completion c) Eliminating the need for communication between teams d) Allowing for fewer changes in project plans

Answer

a) Minimizing idle time for resources

Exercise:

Scenario: You are leading an oil & gas project with the following phases:

  1. Environmental Impact Assessment (EIA): 2 months
  2. Permitting: 3 months
  3. Engineering Design: 4 months
  4. Procurement: 6 months
  5. Construction: 8 months
  6. Commissioning and Testing: 2 months
  7. Production: Ongoing

Task:

  1. Identify potential overlaps between these phases for implementing concurrency.
  2. Create a revised timeline demonstrating concurrency, assuming a 2-month overlap is possible between each phase.
  3. Explain how this revised timeline utilizes concurrency to accelerate project completion.

Exercice Correction

Potential Overlaps:

  • EIA and Permitting can overlap.
  • Engineering Design can overlap with Permitting and Procurement.
  • Procurement can overlap with Construction.
  • Construction can overlap with Commissioning and Testing.

Revised Timeline:

| Phase | Original Duration | Concurrency Duration | Start Date | End Date | |----------------------|--------------------|----------------------|------------|----------| | Environmental Impact | 2 months | 2 months | 0 | 2 | | Permitting | 3 months | 3 months | 0 | 3 | | Engineering Design | 4 months | 4 months | 2 | 6 | | Procurement | 6 months | 6 months | 4 | 10 | | Construction | 8 months | 8 months | 6 | 14 | | Commissioning & Test | 2 months | 2 months | 12 | 14 | | Production | Ongoing | Ongoing | 14 | Ongoing |

Explanation:

This revised timeline demonstrates concurrency by overlapping phases. For example, Engineering Design starts while Permitting is still ongoing, and Procurement begins before Engineering Design is finished. This strategy significantly reduces the overall project duration. The original timeline would have taken approximately 25 months, while the concurrency-optimized timeline is completed within 14 months.


Books

  • Project Management for the Oil & Gas Industry: This book, by Peter E. D’Souza, offers a comprehensive guide to project management within the oil & gas sector. It covers topics like scheduling, risk management, and resource allocation, including strategies for implementing concurrency.
  • Oil & Gas Project Management: A Practical Guide: This book by William G. Kennedy focuses on the unique challenges of managing projects in the oil and gas industry, providing insights into project planning, risk assessment, and managing resources effectively.

Articles

  • Concurrency in Oil and Gas Projects: A Practical Guide to Overlapping Activities: This article provides a practical overview of concurrency in the oil & gas industry, highlighting the benefits and challenges. It also offers valuable tips on how to implement concurrency successfully.
  • The Importance of Concurrency in Oil & Gas Project Execution: This article discusses the importance of overlapping activities in reducing project duration and increasing efficiency in oil & gas projects.
  • Managing Complexity: Optimizing Project Execution through Concurrency: This article focuses on the role of concurrency in managing complex projects and its impact on resource allocation, communication, and overall project success.

Online Resources

  • Society of Petroleum Engineers (SPE): The SPE website offers a wealth of information on various aspects of the oil and gas industry, including project management, technical advancements, and industry trends. You can find relevant articles, research papers, and conference proceedings related to concurrency.
  • Project Management Institute (PMI): The PMI website provides resources and guidelines for project management professionals, including best practices for managing complex projects, risk assessment, and resource allocation.
  • Oil & Gas Journal: This online publication offers news, analysis, and technical articles related to the oil and gas industry, including articles on project management and the implementation of concurrency in various project phases.

Search Tips

  • Use specific keywords like "concurrency oil and gas," "overlapping activities in oil and gas," "project management oil and gas concurrency," and "accelerating oil and gas projects."
  • Combine keywords with industry-specific terms like "upstream," "midstream," or "downstream" to refine your search.
  • Use quotation marks to search for exact phrases. For example, "concurrency in project management."
  • Utilize advanced search operators like "site:" to limit your search to specific websites, for example "site:spe.org concurrency in oil and gas."

Techniques

Similar Terms
Most Viewed

Comments

No Comments
POST COMMENT
captcha
Back