Cost Estimation & Control

Budgeted Cost of Work Performed ("BCWP")

Understanding Budgeted Cost of Work Performed (BCWP): A Key Metric for Cost Estimation and Control

In the world of project management, accurately tracking progress and costs is paramount. One of the most crucial metrics for this is the Budgeted Cost of Work Performed (BCWP), often referred to as Earned Value. This article will delve into the significance of BCWP, providing a clear understanding of its meaning, calculation, and use in cost estimation and control.

What is BCWP?

BCWP represents the value of the work completed on a project up to a specific point in time, measured against the project budget. It essentially answers the question: "How much of the project budget should have been spent based on the work completed so far?"

The Calculation:

BCWP is calculated by summing the budgets for all completed work packages, plus the appropriate portion of budgets for level of effort and apportioned effort for the relevant time period. The process involves:

  1. Identifying work packages: Projects are broken down into manageable work packages with assigned budgets.
  2. Tracking progress: The percentage of work completed within each package is meticulously monitored.
  3. Calculating earned value: The budget for each work package is multiplied by the percentage of completion to determine the earned value.
  4. Summing earned values: The earned values for all completed and partially completed work packages are summed to arrive at the BCWP.

Example:

Imagine a project with three work packages:

  • Work Package 1: Budget - $10,000, Completion - 80%
  • Work Package 2: Budget - $5,000, Completion - 100%
  • Work Package 3: Budget - $8,000, Completion - 50%

The BCWP would be: ($10,000 x 0.8) + ($5,000 x 1) + ($8,000 x 0.5) = $15,000

The Importance of BCWP:

BCWP plays a critical role in cost estimation and control by providing valuable insights into:

  • Project Performance: Comparing BCWP with the Actual Cost of Work Performed (ACWP) allows for the identification of cost overruns or underruns.
  • Schedule Variance: By comparing BCWP with the Planned Value (PV), project managers can track schedule deviations.
  • Forecasting: BCWP forms the basis for accurate cost and schedule forecasts, helping anticipate future needs and potential problems.
  • Decision Making: Informed decisions regarding resource allocation, risk mitigation, and project scope changes can be made based on BCWP analysis.

Conclusion:

BCWP is an essential metric for effective project management, enabling organizations to monitor progress, identify potential problems, and make data-driven decisions. By understanding and utilizing BCWP, project teams can ensure projects stay on track, within budget, and deliver desired outcomes.


Test Your Knowledge

BCWP Quiz

Instructions: Choose the best answer for each question.

1. What does BCWP stand for? a) Budgeted Cost of Work Performed b) Budget Control of Work Progress c) Baseline Cost of Work Performed d) Budgeted Cost of Work Package

Answer

a) Budgeted Cost of Work Performed

2. What does BCWP measure? a) The actual cost of work completed b) The value of work completed based on the project budget c) The total project budget d) The percentage of work completed

Answer

b) The value of work completed based on the project budget

3. How is BCWP calculated? a) Summing the budgets for all completed work packages b) Multiplying the percentage of work completed by the total project budget c) Dividing the actual cost of work performed by the planned value d) Summing the earned values for all completed and partially completed work packages

Answer

d) Summing the earned values for all completed and partially completed work packages

4. Which of the following is NOT a use of BCWP in project management? a) Identifying cost overruns or underruns b) Tracking schedule deviations c) Forecasting future costs and schedule d) Determining the project's overall profitability

Answer

d) Determining the project's overall profitability

5. A project has three work packages with the following details: * Work Package 1: Budget - $12,000, Completion - 75% * Work Package 2: Budget - $6,000, Completion - 100% * Work Package 3: Budget - $9,000, Completion - 50% What is the BCWP for this project?

a) $15,000 b) $18,300 c) $21,000 d) $27,000

Answer

b) $18,300

BCWP Exercise

Scenario: You are managing a software development project with the following budget and progress:

Work Package | Budget | Completion ---|---|---| Requirements Gathering | $10,000 | 90% Design & Development | $25,000 | 60% Testing & Deployment | $15,000 | 30%

Task: Calculate the BCWP for this project.

Exercice Correction

* **Requirements Gathering:** $10,000 x 0.90 = $9,000 * **Design & Development:** $25,000 x 0.60 = $15,000 * **Testing & Deployment:** $15,000 x 0.30 = $4,500 * **BCWP:** $9,000 + $15,000 + $4,500 = **$28,500**


Books

  • A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - This comprehensive guide from the Project Management Institute (PMI) dedicates a chapter to Earned Value Management (EVM) and covers BCWP in detail.
  • Project Management: A Systems Approach to Planning, Scheduling, and Controlling by Harold Kerzner - This classic textbook offers a thorough explanation of EVM and its key metrics including BCWP.
  • Earned Value Management: A Practical Guide to Planning, Measuring, and Managing Projects by Robert K. Wysocki - This book provides a detailed overview of Earned Value Management, focusing on practical applications and real-world examples.

Articles

  • "Earned Value Management: A Primer" by PMI - This article provides a basic introduction to EVM, including the definition and calculation of BCWP.
  • "What is Earned Value Management (EVM)?" by ProjectManagement.com - This article offers a clear explanation of EVM and its benefits for project management.
  • "Earned Value Management: Understanding the Key Metrics" by The Balance Careers - This article explores the key metrics of EVM, including BCWP, and provides insights into their interpretation.

Online Resources

  • Project Management Institute (PMI) - The PMI website provides a wealth of information on EVM, including resources, articles, and certification programs.
  • Earned Value Management Association (EVMA) - This organization offers resources, training, and certification for professionals involved in EVM.
  • Wikipedia: Earned Value Management - A comprehensive overview of EVM with a section dedicated to BCWP.

Search Tips

  • Use "Budgeted Cost of Work Performed" or "Earned Value Management BCWP" for specific information on BCWP.
  • Combine with "calculation", "example", "benefits", or "applications" for targeted results.
  • Use "project management" or "cost estimation" as additional keywords to narrow down your search.

Techniques

Similar Terms