Glossary of Technical Terms Used in Cost Estimation & Control: Budgeted Cost of Work Performed ("BCWP")

Budgeted Cost of Work Performed ("BCWP")

Understanding Budgeted Cost of Work Performed (BCWP): A Key Metric for Cost Estimation and Control

In the world of project management, keeping track of costs and ensuring they stay within budget is crucial. This is where the Budgeted Cost of Work Performed (BCWP) comes into play. BCWP, a term used in the Cost/Schedule Control System Criteria (C/SCSC) system, is a powerful metric that helps project managers assess the financial health of their projects.

What is BCWP?

BCWP represents the value of the work completed based on the approved budget. It essentially measures how much money should have been spent on the work that has been finished.

Think of it this way: If you have a budget of $100,000 for a project and have completed 50% of the work, your BCWP should be $50,000.

How is BCWP Calculated?

BCWP is calculated by summing the budgets for all completed work packages and the budgets for portions of open work packages that are completed. Additionally, it includes the appropriate portion of the budgets for Level of Effort (LOE) and Apportioned Effort.

Level of Effort (LOE): This refers to the effort spent on activities that are not directly tied to a specific deliverable. For example, project management overhead.

Apportioned Effort: This refers to effort that is allocated across multiple work packages.

The Importance of BCWP:

BCWP is a crucial metric for several reasons:

  • Performance Tracking: By comparing BCWP to the Actual Cost of Work Performed (ACWP), project managers can assess the project's performance against budget. If BCWP is higher than ACWP, it means the project is under budget. Conversely, if ACWP is higher, the project is over budget.
  • Cost Variance Analysis: BCWP is a key component in calculating the Cost Variance (CV), which shows the difference between the budgeted cost of the work performed and the actual cost of the work performed.
  • Earned Value Management (EVM): BCWP is a fundamental element of EVM, a widely used project management methodology for tracking progress and managing costs.
  • Forecasting and Budgeting: BCWP can be used to forecast future costs and adjust the budget accordingly, ensuring the project remains on track.

Example:

Let's say a project has a total budget of $100,000. The project has four work packages with the following budgets:

  • Work Package 1: $20,000
  • Work Package 2: $30,000
  • Work Package 3: $40,000
  • Work Package 4: $10,000

If Work Package 1 is completed, Work Package 2 is 50% complete, and Work Package 3 is 25% complete, the BCWP would be:

  • BCWP = $20,000 (WP1) + ($30,000 x 0.5) (WP2) + ($40,000 x 0.25) (WP3) = $40,000

Conclusion:

BCWP is a valuable tool for project managers to monitor project costs, track progress, and ensure projects stay within budget. Understanding and using BCWP effectively can help improve project management practices and ultimately lead to more successful project outcomes.


Test Your Knowledge

Quiz on Budgeted Cost of Work Performed (BCWP)

Instructions: Choose the best answer for each question.

1. What does BCWP stand for?

a) Budgeted Cost of Work Performed b) Budgetary Cost of Work Progress c) Budget for Completed Work d) Budgeted Cost of Work Package

Answer

a) Budgeted Cost of Work Performed

2. Which of the following BEST describes BCWP?

a) The actual cost of the work completed. b) The planned cost of the work completed. c) The total budget allocated to the project. d) The difference between the actual cost and the planned cost.

Answer

b) The planned cost of the work completed.

3. How is BCWP calculated?

a) By summing the actual costs of all completed work packages. b) By subtracting the actual cost of work performed from the total budget. c) By adding the budgets of completed work packages and portions of partially completed work packages. d) By dividing the total budget by the number of work packages.

Answer

c) By adding the budgets of completed work packages and portions of partially completed work packages.

4. Which of the following is NOT a benefit of using BCWP?

a) Tracking project performance against budget. b) Assessing project risk and uncertainty. c) Forecasting future costs and adjusting the budget. d) Analyzing cost variance to identify areas for improvement.

Answer

b) Assessing project risk and uncertainty.

5. If a project has a total budget of $150,000 and 30% of the work is complete, what is the BCWP?

a) $150,000 b) $45,000 c) $105,000 d) $30,000

Answer

b) $45,000

Exercise: Calculate BCWP

Scenario:

A software development project has a total budget of $200,000 and is divided into 5 work packages:

  • Work Package 1: Design - $40,000
  • Work Package 2: Development - $80,000
  • Work Package 3: Testing - $50,000
  • Work Package 4: Deployment - $20,000
  • Work Package 5: Documentation - $10,000

The project is currently at this stage:

  • Work Package 1: Completed
  • Work Package 2: 75% complete
  • Work Package 3: 20% complete
  • Work Package 4: Not yet started
  • Work Package 5: Not yet started

Task: Calculate the BCWP for the project.

Exercice Correction

Here's how to calculate the BCWP: * **Work Package 1:** Completed, so BCWP = $40,000 * **Work Package 2:** 75% complete, so BCWP = $80,000 * 0.75 = $60,000 * **Work Package 3:** 20% complete, so BCWP = $50,000 * 0.20 = $10,000 * **Work Package 4 & 5:** Not started, so BCWP = $0 for both. **Total BCWP = $40,000 + $60,000 + $10,000 + $0 + $0 = $110,000**


Books

  • Project Management Institute (PMI). (2021). A Guide to the Project Management Body of Knowledge (PMBOK® Guide) - Seventh Edition. PMI. This comprehensive guide covers various project management topics, including cost management, and includes detailed explanations of EVM and BCWP.**
  • Kerzner, H. (2017). Project Management: A Systems Approach to Planning, Scheduling, and Controlling. Wiley. A classic textbook on project management, this book provides a thorough treatment of earned value management and its components.**
  • Lock, D. (2018). Project Management: An Integrated Approach. Routledge. This book offers a practical approach to project management, with a focus on applying earned value management techniques.**

Articles


Online Resources

  • ProjectManagement.com: This website offers numerous articles, tutorials, and resources on project management, including a comprehensive section on earned value management. https://www.projectmanagement.com/
  • PMI.org: The website of the Project Management Institute offers a wealth of resources for project managers, including information on EVM, BCWP, and other key metrics. https://www.pmi.org/
  • EarnedValue.com: This website is dedicated to providing resources and information about earned value management, including practical examples and tutorials. https://www.earnedvalue.com/

Search Tips

  • Use specific keywords: When searching for information on BCWP, use specific keywords such as "Budgeted Cost of Work Performed," "Earned Value Management," "EVM," "Cost Management," and "Project Management."
  • Include "definition" or "explanation" in your search: This will help you find articles and resources that provide a clear definition and explanation of BCWP.
  • Use quotation marks: If you want to find specific phrases, enclose them in quotation marks. For example, "Budgeted Cost of Work Performed" will only return results that contain that exact phrase.
  • Combine keywords: Use multiple keywords to narrow down your search results. For example, "Budgeted Cost of Work Performed AND Earned Value Management" will return results that include both terms.
  • Explore related resources: If you find an article or website that you find helpful, explore related links and resources to further your understanding.
Similar Terms
Oil & Gas Processing
Cost Estimation & Control
Project Planning & Scheduling
Budgeting & Financial Control
Oil & Gas Specific Terms
Pipeline Construction
General Technical Terms
Regulatory Compliance
Most Viewed

Comments


No Comments
POST COMMENT
captcha
Back