In the dynamic world of drilling and well completion, abbreviations are commonplace, each carrying a specific meaning crucial for efficient communication and record-keeping. One such abbreviation, "WOC," stands for "Waiting On Cement" and is frequently used in drilling reports.
Understanding WOC:
WOC signifies a specific stage in the drilling and well completion process where operations are temporarily halted, pending the hardening of cement. This cement is often used in various crucial activities, including:
Why WOC is Important:
The WOC period is crucial for several reasons:
WOC in Drilling Reports:
In drilling reports, the WOC period is typically documented alongside:
Beyond the Report:
WOC is not merely an entry in a drilling report. It represents a critical phase in the well completion process, demanding careful planning, effective monitoring, and expert decision-making. Understanding the significance of WOC allows for optimal well performance and minimizes potential risks, ultimately contributing to the successful completion of the well.
Instructions: Choose the best answer for each question.
1. What does the abbreviation "WOC" stand for in drilling and well completion reports?
a) Waiting On Completion b) Waiting On Cable c) Waiting On Cement d) Waiting On Connections
c) Waiting On Cement
2. Why is the WOC period crucial in well completion?
a) To allow for the cement to harden and provide structural integrity. b) To give the drilling crew a break. c) To check for any equipment malfunctions. d) To measure the depth of the well.
a) To allow for the cement to harden and provide structural integrity.
3. Which of the following is NOT a common use of cement during the WOC period?
a) Setting casing strings in place. b) Isolating different zones of the well. c) Connecting drilling pipes. d) Sealing off unwanted or depleted zones.
c) Connecting drilling pipes.
4. What information is typically documented in a drilling report regarding the WOC period?
a) The type of cement used. b) The start time of the cementing operation. c) The expected and actual wait time. d) All of the above.
d) All of the above.
5. What is the primary reason for ensuring the WOC period is carefully monitored and managed?
a) To avoid delays in the drilling operation. b) To ensure the well is completed safely and efficiently. c) To comply with regulatory requirements. d) To minimize the cost of the well completion.
b) To ensure the well is completed safely and efficiently.
Scenario:
You are reviewing a drilling report that states a WOC period occurred from 10:00 AM to 4:00 PM on February 15th, 2023. The report indicates that the cement used was Class H high-performance cement, designed for a minimum setting time of 4 hours. The cementing operation was performed at a well depth of 5,000 feet.
Task:
1. **Actual WOC period:** 6 hours (4:00 PM - 10:00 AM = 6 hours)
2. **Adequacy of WOC:** Yes, the actual WOC period (6 hours) exceeded the minimum setting time of 4 hours for Class H cement.
3. **Additional information:** To assess the adequacy of the WOC period more comprehensively, you would need: