Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDp9tf+6rOLEWgWwllHapfSw
Unique ID175245
Activity NamePiping Insulation
Added Date7 septembre 2009 09:59
Added Byadmin
Activity StatusTK_NotStart
WBS39114
Total Float300,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1336,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start26 avril 2012 12:00
Actual StartNone
Activity IDCCA06PI020
Early Start26 avril 2012 12:00
Late Start10 juin 2012 08:00
Remaining Early Finish7 novembre 2012 12:00
Remaining Early Start26 avril 2012 12:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique IDThc6Ixs0CE2iiUBXSnReXA
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish7 novembre 2012 12:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish7 novembre 2012 12:00 
Late Finish20 décembre 2012 16:00 
Remaining Late Finish20 décembre 2012 16:00 
Remaining Late Start10 juin 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float172,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1336,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1752250,0 PR_SS

Successors

6
  Task Id    Lag (day)     Succ Type  
1752370,0 PR_FF
Back