Project Cloud System

Job N° : 1200012

Task Detail

1
General Informations
Project752
Global Unique IDRHrXnZYT8E6aTOi+nhMl3A
Unique ID175169
Activity NamePiping Hydrotest
Added Date7 septembre 2009 09:58
Added Byadmin
Activity StatusTK_NotStart
WBS39097
Total Float120,0
Activity LocationNone
Est Weight1,0
Phys Complete Pct0,0
Calendar866
Percent Complete TypeCP_Drtn
Auto Compute ActualsN
Remaining Duration1472,0
2
Primary ConstraintNone
Secondary ConstraintNone
Primary Constraint DateNone
Secondary Constraint DateNone
  
  
Primary ResourceNone
Actual Nonlabor Units0,0
Actual This Period Nonlabor Units0,0
Actual This Period Labor Units0,0
Actual Labor Units0,0
Planned Labor Units
Budgeted or Planned Labor Units
0,0
Remaining Nonlabor Units0,0
Remaining Labor Units0,0
Planned Nonlabor Units
Budgeted or Planned Nonlabor Units
0,0
3
Last Modified Date30 octobre 2009 15:31
Planned Start1 avril 2012 08:00
Actual StartNone
Activity IDCCA04PP030
Early Start1 avril 2012 08:00
Late Start18 avril 2012 08:00
Remaining Early Finish31 octobre 2012 16:00
Remaining Early Start1 avril 2012 08:00
External Early StartNone
Expected FinishNone
Resume DateNone
  
New FeedbackN
Review Status
Activity Leveling PriorityPT_Normal
Methodology Global Unique ID6TCxbZ2H/USuAaOU1jFjww
Lock RemainingN
4
Last Modified Byadmin 
Planned Finish31 octobre 2012 16:00 
Actual FinishNone 
Activity TypeTT_Task 
Early Finish31 octobre 2012 16:00 
Late Finish18 novembre 2012 16:00 
Remaining Late Finish18 novembre 2012 16:00 
Remaining Late Start18 avril 2012 08:00 
External Late FinishNone 
Review Finish 
Suspend DateNone 
   
Longest PathN 
Free Float0,0 
Float Path 
Float Path Order 
Duration TypeDT_FixedDUR2 
Planned Duration
Original or Planned Duration
1472,0 

Predecessors

5
  Task Id    Lag (day)     Succ Type  
1751872504,0 PR_SS
1751880,0 PR_FF
1751720,0 PR_FF

Successors

6
  Task Id    Lag (day)     Succ Type  
175181632,0 PR_SS
1751890,0 PR_SS